Quick Answer
A subcontractor or supplier in Alabama needs, in order, a written notice of lien to the owner, a verified statement of lien filed with the judge of probate, and a suit to enforce within 6 months after the debt matures (Ala. Code §§ 35-11-218, 35-11-213, 35-11-221). Original contractors skip the owner notice.
The verified statement is due within 6 months after last work for an original contractor, 30 days for journeymen and day laborers, and 4 months for every other claimant (§ 35-11-215). It must be sworn under oath; an acknowledgment alone does not satisfy the verification requirement.
A material supplier that serves an advance notice on the owner before furnishing, listing the materials and prices, can claim a full-price lien rather than a lien limited to the unpaid balance (§ 35-11-210). Without it, the lien reaches only the balance the owner still owes the contractor when the notice of lien is served.
On public works, the claimant serves written notice of the claim on the surety, waits 45 days, and sues on the payment bond within 1 year after final settlement (§ 39-1-1(b)). After full payment, a lienholder must enter an acknowledgment of satisfaction on the lien record (§ 35-11-231).
Alabama mechanics lien practice turns on a short set of documents: an optional advance notice for material suppliers, a written notice of lien to the owner for every claimant other than the original contractor, the verified statement of lien filed with the judge of probate, and a suit to enforce.
Alabama supplies a sufficient statutory form for the verified statement and for the supplier's advance notice, but neither form is exclusive. The verified statement must be sworn. Public projects run through the contractor's payment bond under Ala. Code § 39-1-1 rather than a lien on public property.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
Alabama Preliminary Notices
Notice to Owner Before Furnishing Materials
- Who uses it
- Material suppliers furnishing through a contractor or subcontractor
- When
- Before the materials are furnished
- Served on or filed with
- The owner or proprietor, or the owner's agent
- Notarization
- Not required
- The notice identifies the materials, their prices, the contractor or subcontractor receiving them, and the project. The statute supplies a sufficient form, not an exclusive one.
- A proper notice gives the supplier a full-price lien. The owner can defeat that result by written notice, before the materials are used, that it will not be responsible for the price.
Ala. Code § 35-11-210
Alabama Notices Before Filing a Lien
Notice of Lien Claimed by Persons Other Than Original Contractor
- Who uses it
- Subcontractors, suppliers, laborers and every other claimant without a direct contract with the owner
- When
- Before the verified statement of lien is filed; no fixed number of days, but the filing deadline still controls
- Served on or filed with
- The owner or proprietor, or the owner's agent
- Notarization
- Not required
- The written notice states that a lien is claimed, the amount, what it is for, and from whom it is owed.
- The unpaid balance the owner holds when the notice is served becomes subject to the lien, so earlier service protects a larger amount.
Ala. Code § 35-11-218
Alabama Lien Claim and Service
Verified Statement of Lien
- Who uses it
- Every lien claimant, including original contractors
- When
- Within 6 months after last work for original contractors, 30 days for journeymen and day laborers, and 4 months for all other claimants
- Served on or filed with
- Filed with the judge of probate in the county where the property is located
- Notarization
- Required (sworn verification by the claimant or another person with knowledge)
- The statement gives the amount due after all just credits, a description of the property sufficient to identify it, and the name of the owner or proprietor.
- The statutory form is deemed sufficient but is not exclusive. An oath taken outside Alabama may be administered by an officer authorized to take acknowledgments there.
Ala. Code §§ 35-11-213, 35-11-214, 35-11-215
Alabama Enforcing the Lien
Complaint to Enforce Lien
- Who uses it
- Lien claimants
- When
- Within 6 months after the entire debt secured by the lien matures
- Served on or filed with
- Filed in the court of the county where the property is located; circuit court for claims over $50
- Notarization
- Not required
- The complaint must describe the property and allege the facts that support the lien. The enforcement deadline is separate from the filing deadline for the verified statement.
Ala. Code §§ 35-11-220, 35-11-221, 35-11-222
Notice of Lis Pendens
- Who uses it
- The claimant who brings the enforcement action
- When
- When the enforcement action is filed
- Served on or filed with
- Filed in the probate office of each county where the affected land lies
- Notarization
- Not required
- The notice names the parties, describes the real estate, and states briefly the nature of the lien and the action.
Ala. Code § 35-4-131
Alabama Releasing or Bonding Off a Lien
Transfer of Lien to Cash or Surety Bond
- Who uses it
- Owners and others with an interest in the property or the underlying contract
- When
- At any time; filed with a copy of the recorded lien
- Served on or filed with
- Filed with the court; the certificate of transfer is mailed to the lienholder and then filed where the lien was filed
- Notarization
- Not required
- The security must cover the lien demand plus interest at 8 percent for 3 years and $100 in costs. The lienholder has 10 days after receiving the certificate to challenge the amount or the surety.
- The transfer moves the lien to the security. It does not decide or extinguish the debt.
Ala. Code § 35-11-233
Acknowledgment of Satisfaction
- Who uses it
- Lienholders who have been paid in full
- When
- Upon full satisfaction of the lien
- Served on or filed with
- Entered on the lien record in the probate office
- Notarization
- Not required by the statute
- If the lienholder fails to enter satisfaction within 30 days after a written demand, it is liable for the resulting injury, with a minimum of $200.
Ala. Code § 35-11-231
Alabama Owner Notices and Forms
Owner's Notice of Nonresponsibility to a Material Supplier
- Who uses it
- Owners who receive a supplier's advance notice
- When
- After the supplier's notice and before the materials are used
- Served on or filed with
- The material supplier
- Notarization
- Not required
- The written objection defeats the supplier's full-price lien. It does not eliminate the supplier's lien on the unpaid balance.
Ala. Code § 35-11-210
Owner's Request for List of Materialmen, Laborers and Employees
- Who uses it
- Owners; the original contractor must answer
- When
- When the owner requests it; no fixed number of days
- Served on or filed with
- The original contractor, who delivers the list to the owner
- Notarization
- Not required
- The list covers materialmen, laborers and employees, with the terms and prices of each engagement. A contractor that fails or refuses to furnish it can forfeit its own lien.
Ala. Code § 35-11-219
Alabama Public Works and Payment Bond Claims
Notice of Payment Bond Claim
- Who uses it
- Unpaid subcontractors, suppliers and laborers on bonded public works
- When
- At least 45 days before suit on the bond
- Served on or filed with
- The surety; registered or certified mail to any office of the surety is sufficient
- Notarization
- Not required
- The notice states the amount due and the nature of the claim. Public buildings and land cannot be liened, so the payment bond is the claimant's principal security.
Ala. Code § 39-1-1(b)
Suit on the Payment Bond
- Who uses it
- Claimants who served the bond claim notice
- When
- After the 45-day notice period and within 1 year after final settlement of the contract
- Served on or filed with
- Filed against the contractor and surety, or either, in the county where the work was performed or another lawful venue
- Notarization
- Not required
Ala. Code § 39-1-1(b)
Lien on Unpaid Contract Balance (Public Projects)
- Who uses it
- Subcontractors and suppliers on public projects, against the prime contractor's unpaid contract balance
- When
- Notice of lien to the public owner before filing; verified statement within the ordinary 4-month or 6-month periods; suit within 6 months after the debt matures
- Served on or filed with
- Notice to the public owner; verified statement filed with the judge of probate
- Notarization
- Required for the verified statement; verifying the owner notice is prudent
- The lien reaches only the contractor's interest in an actual unpaid balance. It never encumbers the public building, land or treasury (Martin v. Holtville High School Building, 145 So. 491 (Ala. 1933); Rayborn v. Housing Authority of Washington County, 164 So. 2d 494 (Ala. 1964)).
Ala. Code §§ 35-11-210, 35-11-218
Contractor's Notice of Completion
- Who uses it
- Prime contractors on public contracts of $100,000 or more
- When
- Immediately after completion, published for at least 3 weeks; final settlement may not occur until 30 days after publication ends
- Served on or filed with
- Published in a newspaper of general circulation in the county, its website, or the awarding authority's notice website; proof by publisher's affidavit goes to the awarding authority
- Notarization
- Publisher's or website owner's affidavit required as proof
- The final settlement date starts the 1-year bond suit period, so claimants should track the completion notice closely.
Ala. Code § 39-1-1(f)
Frequently Asked Questions
Is there a statutory mechanics lien form in Alabama?
Yes. Ala. Code § 35-11-213 sets out a form of verified statement of lien that is deemed sufficient, and § 35-11-210 supplies a sufficient form for a material supplier's advance notice. Neither form is exclusive; a document that contains the required content and verification also complies.
Does an Alabama mechanics lien have to be notarized?
The statement must be verified by oath of the claimant or another person with knowledge of the facts (Ala. Code § 35-11-213). In practice the oath is taken before a notary. A signature with only an acknowledgment is not a substitute for the sworn verification.
Where do I file a mechanics lien in Alabama?
The verified statement of lien is filed in the office of the judge of probate in the county where the property is located (Ala. Code § 35-11-213). Original contractors have 6 months after last work, journeymen and day laborers 30 days, and other claimants 4 months (§ 35-11-215).
Do subcontractors have to send a notice before filing an Alabama lien?
Yes. Every claimant other than the original contractor must give the owner written notice of the lien claim before filing the verified statement (Ala. Code § 35-11-218). The statute sets no fixed number of days, but the notice must precede the filing, and the lien reaches the unpaid balance the owner holds when it is served.
What form releases a mechanics lien in Alabama?
A paid lienholder enters an acknowledgment of satisfaction on the lien record in the probate office (Ala. Code § 35-11-231). An owner who disputes the lien may instead transfer it to a cash deposit or surety bond through the court under § 35-11-233, which frees the real property while the claim proceeds against the security.
What form do I use for an Alabama public project bond claim?
Alabama prescribes no template. The claimant serves written notice of the amount due and the nature of the claim on the surety, by registered or certified mail to any surety office, then waits 45 days before suing on the bond. Suit must be filed within 1 year after final settlement (Ala. Code § 39-1-1(b)).
How long do I have to enforce an Alabama mechanics lien?
Suit to enforce must be filed within 6 months after the entire debt secured by the lien matures (Ala. Code § 35-11-221). This deadline runs separately from the deadline to file the verified statement, and the claimant should also file a lis pendens in the probate office (§ 35-4-131).
Related Alabama Resources
Alabama Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Alabama Notice Requirements
Who must give notice, when, and how.
Alabama Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Alabama Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Alabama law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.