HomeNew Jersey
NJ Construction Law

New Jersey Mechanic Lien Law: Complete Guide

Your Complete Guide to Construction Lien Rights Under N.J.S.A. 2A:44A-1 et seq. — Residential Works, Commercial Works & Payment Bond Claims

New Jersey mechanic lien deadline table with toggles for project type and claimant type.

New Jersey Preliminary Notice & Mechanic Lien Deadlines

Select your project type and role to see the deadlines that apply to you.

Project Type
Select Your Tier

Prime Contractor — In privity with the property owner

Preliminary Notice

60 days

Commercial projects: no preliminary notice is required. The prime contractor may proceed directly to filing a Construction Lien Claim.

Residential projects (owner-occupied one- or two-family dwelling): the prime must first lodge a Notice of Unpaid Balance and Right to File Lien (NUB) with the county clerk within 60 days after last furnishing, and then submit the dispute to arbitration before a Construction Lien Claim may be filed.

Mechanic Lien

90 days

Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment.

Residential projects: after the NUB is lodged and the claim has proceeded to arbitration, the Construction Lien Claim must be lodged within 120 days after last furnishing, and in no event later than 10 days after receipt of the arbitration award.

Serve a copy of the Construction Lien Claim on the owner and prior lien claimants within 10 business days of lodging.

Enforcement

1 year

Commence an action to enforce the Construction Lien Claim within 1 year after last furnishing, or within 30 days after written demand by the owner to commence suit, whichever is earlier.

New Jersey private project deadlines

Prime Contractor

Preliminary Notice: Commercial projects: no preliminary notice is required. The prime contractor may proceed directly to filing a Construction Lien Claim. Residential projects (owner-occupied one- or two-family dwelling): the prime must first lodge a Notice of Unpaid Balance and Right to File Lien (NUB) with the county clerk within 60 days after last furnishing, and then submit the dispute to arbitration before a Construction Lien Claim may be filed.

Mechanic Lien: Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment. Residential projects: after the NUB is lodged and the claim has proceeded to arbitration, the Construction Lien Claim must be lodged within 120 days after last furnishing, and in no event later than 10 days after receipt of the arbitration award. Serve a copy of the Construction Lien Claim on the owner and prior lien claimants within 10 business days of lodging.

Enforcement: Commence an action to enforce the Construction Lien Claim within 1 year after last furnishing, or within 30 days after written demand by the owner to commence suit, whichever is earlier.

Subcontractors & Suppliers

Preliminary Notice: Commercial projects: no preliminary notice is required. Subcontractors and suppliers may proceed directly to filing a Construction Lien Claim. Residential projects: a Notice of Unpaid Balance and Right to File Lien (NUB) must be lodged with the county clerk and served on the owner and prime contractor within 60 days after last furnishing. The claimant must then submit the dispute to arbitration before a Construction Lien Claim may be filed. Best practice: issue a Residential Construction Contract Notice at project start on owner-occupied residential work to preserve all statutory remedies.

Mechanic Lien: Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment. Residential projects: after the NUB is lodged and arbitration has concluded, the Construction Lien Claim must be lodged within 120 days after last furnishing, and in no event later than 10 days after receipt of the arbitration award. Serve a copy of the Construction Lien Claim on the owner, the prime contractor, and any intervening contractor within 10 business days of lodging.

Enforcement: Commence an action to enforce the Construction Lien Claim within 1 year after last furnishing, or within 30 days after written demand by the owner to commence suit, whichever is earlier.

Remote Claimants

Preliminary Notice: Commercial projects: no preliminary notice is required. Remote claimants may proceed directly to filing a Construction Lien Claim. Residential projects: a Notice of Unpaid Balance and Right to File Lien (NUB) must be lodged with the county clerk and served on the owner, the prime contractor, and any intervening contractor within 60 days after last furnishing. The claimant must then submit the dispute to arbitration before a Construction Lien Claim may be filed. Best practice: issue a Residential Construction Contract Notice at project start on owner-occupied residential work to preserve all statutory remedies.

Mechanic Lien: Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment. Residential projects: after the NUB is lodged and arbitration has concluded, the Construction Lien Claim must be lodged within 120 days after last furnishing, and in no event later than 10 days after receipt of the arbitration award. Serve a copy of the Construction Lien Claim on the owner, the prime contractor, and any intervening contractor within 10 business days of lodging.

Enforcement: Commence an action to enforce the Construction Lien Claim within 1 year after last furnishing, or within 30 days after written demand by the owner to commence suit, whichever is earlier.

New Jersey public works deadlines

Prime Contractor

Preliminary Notice: Not applicable. The prime contractor is the principal on the payment bond and pursues payment through contract remedies, not a bond claim.

Bond Claim: Not applicable. Mechanic liens cannot attach to public property in New Jersey. Prime contractors pursue payment through contract remedies.

Lawsuit to Enforce Bond Claim: Contract remedies against the public owner, subject to any applicable notice-of-claim and limitations periods.

Subcontractors & Suppliers

Preliminary Notice: Serve written notice of the claim, stating the amount due, on the prime contractor and surety by certified mail within 1 year from the date the claimant last furnished labor or materials. Suit may not be commenced until 90 days after service of the statement. New Jersey also provides a parallel lien on public funds held by the public body under the Municipal Mechanics' Lien Law; the payment bond claim is the primary public-works remedy.

Bond Claim: The 90-day notice of claim perfects the bond claim. Mechanic liens cannot attach to public property in New Jersey; payment rights run through the payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond within 1 year after the claimant's last furnishing of labor or materials, and no sooner than 90 days after serving the statement of amount due on the prime and surety.

Remote Claimants

Preliminary Notice: Serve written notice of the claim, stating the amount due, on the prime contractor and surety by certified mail within 1 year from the date the claimant last furnished labor or materials. Suit may not be commenced until 90 days after service of the statement. New Jersey also provides a parallel lien on public funds held by the public body under the Municipal Mechanics' Lien Law; the payment bond claim is the primary public-works remedy.

Bond Claim: The 90-day notice of claim perfects the bond claim. Mechanic liens cannot attach to public property in New Jersey; payment rights run through the payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond within 1 year after the claimant's last furnishing of labor or materials, and no sooner than 90 days after serving the statement of amount due on the prime and surety.

New Jersey Mechanic Lien Law Overview

Last updated April 2026 · Reviewed by Thomas Emalfarb, Esq.

New Jersey construction lien rights are governed by the New Jersey Construction Lien Law, N.J.S.A. 2A:44A-1 et seq. This statutory framework protects the payment rights of contractors, subcontractors, and suppliers who furnish labor, services, materials, or equipment for the improvement of real property in the State of New Jersey.

New Jersey distinguishes between residential and commercial construction for lien purposes. On residential construction projects, a lien claimant must file a Notice of Unpaid Balance and Right to File Lien (NUB) within 60 days of the last date materials were delivered or services performed, or within 60 days after completion, acceptance, or termination of the contract, whichever is earlier. The NUB must be served on the owner by certified mail, return receipt requested, or by personal service. On commercial construction projects, no preliminary notice is required, but the lien claim must be filed within 90 days after the last date the claimant provided work, services, material, or equipment.

Lien claims in New Jersey are filed with the office of the County Clerk in the county where the property is located. The lien amount is limited to the amount the owner owes the contractor at the time of service of the lien claim, unless the owner has made payments in violation of the Construction Lien Law. Disputes on residential projects over lien validity are resolved through arbitration, while commercial lien disputes are adjudicated in the Superior Court of New Jersey.

For public works projects, New Jersey requires payment bonds on public contracts exceeding $100 under N.J.S.A. 2A:44-143 et seq. Subcontractors and suppliers must serve a notice of claim within 90 days after the last date of furnishing labor, materials, or equipment. Suit on the payment bond must be filed within one year after the last date of furnishing. New Jersey also provides strong anti-waiver protections under N.J.S.A. 2A:44A-38, invalidating any contractual provision that purports to waive lien rights in advance.

National Lien & Bond provides authoritative guidance on every aspect of New Jersey construction lien compliance, from Notice of Unpaid Balance requirements through lien claim filing, payment bond claims, and lien enforcement proceedings.

Frequently Asked Questions

What are the construction lien rights available in New Jersey?

New Jersey provides construction lien rights under N.J.S.A. 2A:44A-1 et seq. for contractors, subcontractors, and suppliers who furnish labor, services, materials, or equipment for the improvement of private real property. Residential projects require a Notice of Unpaid Balance within 60 days. Commercial liens must be filed within 90 days of last furnishing. Suit must be filed within one year.

Is a preliminary notice required to file a construction lien in New Jersey?

On residential projects, a Notice of Unpaid Balance and Right to File Lien (NUB) must be served on the owner within 60 days of last furnishing or completion, acceptance, or termination, whichever is earlier, under N.J.S.A. 2A:44A-6. On commercial projects, no preliminary notice is required.

What is the deadline to file a construction lien in New Jersey?

On both residential and commercial projects, the construction lien claim must be filed within 90 days after the last date the claimant provided work, services, material, or equipment. On residential projects, the NUB must be served first within 60 days. The lien is filed with the County Clerk in the county where the property is located.

How are public works payment rights protected in New Jersey?

Public works projects with contracts exceeding $100 require payment bonds under N.J.S.A. 2A:44-143 et seq. Subcontractors and suppliers not in direct privity with the general contractor must serve a notice of claim within 90 days after last furnishing. Suit must be filed within one year of last furnishing.

How does New Jersey distinguish between residential and commercial lien procedures?

Residential construction involves an owner-occupied dwelling of no more than three units. It requires a NUB and disputes go to arbitration. Commercial construction includes all other projects. It requires no preliminary notice and disputes are resolved in Superior Court. Both require lien filing within 90 days and suit within one year.

Can construction lien rights be waived in a New Jersey contract?

No. Under N.J.S.A. 2A:44A-38, any contractual provision that purports to waive the right to file a construction lien is void and unenforceable. Only a lien waiver executed after the work has been performed and payment has been received is valid under New Jersey law.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us