HomeUtah
UT Construction Law

Utah Mechanic Lien Law: Complete Guide

Your Complete Guide to Mechanic Lien Rights Under Utah Code §38-1a-101 et seq. — Private Works, Payment Bonds, Mechanic Lien Recovery Fund & Public Projects

Utah mechanic lien deadline table with toggles for project type and claimant type.

Utah Preliminary Notice & Mechanic Lien Deadlines

Select your project type and role to see the deadlines that apply to you.

Project Type
Select Your Tier

Prime Contractor — In privity with the property owner

Preliminary Notice

Not Required

Mechanic Lien

180 days

Record the Notice of Construction Lien with the county recorder within 180 days after completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Serve a copy on the owner within 30 days of recording.

Enforcement

180 days

Commence an action to enforce the lien within 180 days after recording the Notice of Construction Lien.

Utah private project deadlines

Prime Contractor

Preliminary Notice: Not required for the original contractor. Utah's State Construction Registry preliminary notice requirement does not apply to the original contractor in direct contract with the owner. Primes are, however, typically required to file a Notice of Commencement with the SCR on behalf of the project.

Mechanic Lien: Record the Notice of Construction Lien with the county recorder within 180 days after completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Serve a copy on the owner within 30 days of recording.

Enforcement: Commence an action to enforce the lien within 180 days after recording the Notice of Construction Lien.

Subcontractors & Suppliers

Preliminary Notice: File a Preliminary Notice with the State Construction Registry (SCR) within 20 days of first furnishing labor or materials. Failure to file within 20 days forfeits lien rights for the affected period. Best practice is to file the Preliminary Notice on the first day of furnishing.

Mechanic Lien: Record the Notice of Construction Lien with the county recorder within 180 days after completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Serve a copy on the owner within 30 days of recording.

Enforcement: Commence an action to enforce the lien within 180 days after recording the Notice of Construction Lien.

Remote Claimants

Preliminary Notice: File a Preliminary Notice with the State Construction Registry (SCR) within 20 days of first furnishing labor or materials. Remote claimants not in privity with the prime contractor must file the Preliminary Notice to preserve lien rights. Failure to file within 20 days forfeits lien rights for the affected period.

Mechanic Lien: Record the Notice of Construction Lien with the county recorder within 180 days after completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Serve a copy on the owner within 30 days of recording.

Enforcement: Commence an action to enforce the lien within 180 days after recording the Notice of Construction Lien.

Utah public works deadlines

Prime Contractor

Preliminary Notice: Not applicable. The prime contractor is the principal on the payment bond and pursues payment through contract remedies, not a bond claim.

Bond Claim: Not applicable. Mechanic liens cannot attach to public property in Utah. Prime contractors pursue payment through contract remedies.

Lawsuit to Enforce Bond Claim: Contract remedies against the public owner, subject to any applicable notice-of-claim and limitations periods.

Subcontractors & Suppliers

Preliminary Notice: File a Preliminary Notice with the State Construction Registry (SCR) within 20 days of first furnishing labor or materials. The same 20-day SCR filing rule that applies on private projects applies on public works.

Bond Claim: Serve a written bond claim notice on the prime contractor within 90 days of last furnishing labor or materials. Mechanic liens cannot attach to public property; payment rights run through the payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond more than 90 days but less than 1 year after the claimant's last furnishing of labor or materials.

Remote Claimants

Preliminary Notice: File a Preliminary Notice with the State Construction Registry (SCR) within 20 days of first furnishing labor or materials. Remote claimants must file the Preliminary Notice to preserve bond claim rights on public works.

Bond Claim: Serve a written bond claim notice on the prime contractor within 90 days of last furnishing labor or materials. Mechanic liens cannot attach to public property; payment rights run through the payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond more than 90 days but less than 1 year after the claimant's last furnishing of labor or materials.

Utah Mechanic Lien Law Overview

Last updated April 2026 · Reviewed by Thomas Emalfarb, Esq.

Utah construction mechanic lien rights are governed by Utah Code §38-1a-101 et seq. and §38-11-20 et seq. This statutory framework provides Mechanic's Lien rights to contractors, subcontractors, and material suppliers who furnish labor or materials for the improvement of real property in the State of Utah.

Utah requires contractors to file a Notice of Commencement within 15 days of the issuance of the building permit (or within 15 days of beginning work if no permit is issued). Subcontractors and material suppliers must file a Preliminary Notice to the original contractor within 20 days of first performance or within 20 days of the Notice of Subcontract.

All claimants must record a Notice of Mechanic Lien within 90 days of filing a Notice of Completion, or within 180 days from 'final completion' of the original contract if no Notice of Completion is filed (whichever is earlier). Utah severely restricts mechanic lien rights on single-family and duplex residential property — subcontractors and suppliers on such projects must pursue claims through the Mechanic Lien Recovery Fund instead.

Utah requires 100% payment bonds on all commercial projects over $50,000 under §14-2-1 and on public works under §14-1-1.

Frequently Asked Questions

What statute governs mechanic liens in Utah?

Mechanic's liens are governed by Utah Code §38-1a-101 et seq. and §38-11-20 et seq. Private commercial bonds are governed by §14-2-1 et seq. and public works bonds by §14-1-1 et seq.

Is a preliminary notice required to file a mechanic lien in Utah?

Yes. Contractors must file a Notice of Commencement within 15 days of the building permit. Subcontractors must file a Preliminary Notice within 20 days of first performance. A signed invoice must be provided 15 days before recording the mechanic lien.

What is the deadline to file a mechanic lien in Utah?

Record a Notice of Mechanic Lien within 90 days of a Notice of Completion or within 180 days from final completion if no Notice of Completion is filed, whichever is earlier. §38-1-7.

How does Utah mechanic lien law differ from other states?

Utah has several unique features: an electronic database system, the Mechanic Lien Recovery Fund for residential projects (subcontractors cannot mechanic lien single-family/duplex property), mandatory 100% bonds on commercial projects over $50,000, Notice of Commencement filing, and owner liability for failure to require bonds.

What are the notice requirements for Utah public works bond claims?

First-tier subcontractors need no preliminary notice. Second-tier claimants must file Preliminary Notice to the bond principal within 20 days of first performance. If no bond was required, notice within 90 days of final furnishing preserves the right to sue the owner.

What is the deadline to file suit to enforce a Utah construction mechanic lien?

Suit must be filed within 180 days after recording the Notice of Mechanic Lien. For bond claims (private and public), suit must be filed between 90 days and 1 year after last performance by the claimant.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us