Alaska Mechanics Lien Forms

Alaska Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Alaska construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Alaska subcontractor or supplier should give and record a Notice of Right to Lien, record a verified Claim of Lien within 120 days after completing its contract or ceasing to furnish, and file suit to foreclose within 6 months after recording (AS 34.35.064, 34.35.067, 34.35.068, 34.35.080).

The Notice of Right to Lien is optional, but it matters. Giving it to the owner before furnishing shifts the burden on the owner's knowledge and consent, and recording it protects priority and preserves the 120-day period if the owner later records a Notice of Completion.

After a valid Notice of Completion is recorded, a claimant that received the owner's advance notice, or that has not given a Notice of Right to Lien, must record a Claim of Lien or a Notice of Right to Lien within 15 days (AS 34.35.068, 34.35.071).

On public works, a claimant that contracted with a subcontractor rather than the prime must give the prime written notice within 90 days after last furnishing. Suit follows after 90 days and no later than 1 year after final settlement of the prime contract (AS 36.25.020).

Alaska's lien statute, AS 34.35.050 to 34.35.120, uses a small set of core documents: the optional Notice of Right to Lien, the verified Claim of Lien, the owner's Notice of Completion, and a foreclosure action within 6 months.

Alaska prescribes the content of each document rather than a fill-in template. It also offers a stop-lending notice to construction lenders and a statutory bond that substitutes for the lien. Public works claims run against the contractor's payment bond under AS 36.25.020.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Alaska Preliminary Notices

Notice of Right to Lien

Statutory Form
Optional
Who uses it
Contractors, subcontractors, suppliers, design professionals and other potential lien claimants
When
Given to the owner before furnishing; may be recorded after contracting or first furnishing
Served on or filed with
The owner or owner's agent, and recorded in the recording district where the property is located
Notarization
Not expressly required; a verified recorded copy is the safer practice
  • The statute prescribes its content, including the legal description, the parties, a description of the furnishing, and a warning in specified type size.
  • Giving and recording are separate steps with separate effects. Recording preserves the 120-day lien period after a Notice of Completion.

AS 34.35.064, 34.35.067

Stop-Lending Notice

Notarized
Optional
Who uses it
Claimants whose payment is past due on a construction-financed project
When
While financing disbursements remain; it expires on the 91st day after the lender receives it unless suit is filed and the lender is notified
Served on or filed with
The construction lender, with copies to the owner and each prime contractor in the chain
Notarization
Required (claimant verification)
  • The notice directs the lender to stop disbursements and states the unpaid amount. It must be revoked promptly after payment in full.

AS 34.35.062

Alaska Lien Claim and Service

Claim of Lien

Notarized
Required When It Applies
Who uses it
All lien claimants
When
Within 120 days after completing the construction contract or ceasing to furnish; a shorter 15-day rule may apply after a Notice of Completion
Served on or filed with
Recorded in the recording district where the property is located
Notarization
Required (verified by oath of the claimant or another person with knowledge)
  • The claim states the legal description, owner, claimant and hiring party, a description of the furnishing and contract price, the amount due, and the last furnishing date.
  • The statute does not separately require service of the recorded claim on the owner.

AS 34.35.068, 34.35.070

Alaska Enforcing the Lien

Extension Notice

Optional
Who uses it
Lien claimants who need more time to sue
When
Within the original 6 months after the Claim of Lien is recorded
Served on or filed with
Recorded in the same office as the Claim of Lien
Notarization
Not expressly required
  • The notice identifies the original recording and the balance owed. Suit must then be filed within 6 months after the extension is recorded.

AS 34.35.080

Complaint to Foreclose Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 6 months after recording the Claim of Lien, or within the extended period
Served on or filed with
Filed in superior court; join persons personally liable and recorded lienholders
Notarization
Not required

AS 34.35.080

Notice of Pendency of Action (Lis Pendens)

Required When It Applies
Who uses it
Foreclosing claimants
When
When the complaint is filed or afterward, before a protected later interest is recorded
Served on or filed with
Recorded in the recording district where the property is located
Notarization
Not required

AS 09.45.940; AS 34.35.080

Alaska Releasing or Bonding Off a Lien

Bond (Lien Release Bond)

Optional
Who uses it
Owners, prime contractors or subcontractors
When
Before or after the enforcement suit is filed
Served on or filed with
Recorded where the lien is recorded
Notarization
Not required
  • The bond must equal 150 percent of the lien claim and guarantee payment of any recovery plus reasonable costs of suit.

AS 34.35.072

Release of Lien

Required When It Applies
Who uses it
Lien claimants
When
Promptly after full payment, or after discovering the lien is erroneous, unjust, premature or excessive
Served on or filed with
Recorded in the recording district, referencing the released instrument
Notarization
Not required by the lien statute; general recording rules apply
  • A claimant that fails to remove a lien when required is exposed to statutory damages and injunctive relief.

AS 34.35.074

Alaska Owner Notices and Forms

Notice of Completion

Notarized
Optional
Who uses it
Owners
When
After actual completion; the owner must first give qualifying claimants at least 5 days' advance notice with a copy
Served on or filed with
Recorded in the recording district where the property is located
Notarization
Required (signed and verified by the owner)
  • A Notice of Completion recorded before actual completion is ineffective.

AS 34.35.071

Notice of Nonresponsibility

Notarized
Optional
Who uses it
Owners or others with an interest who did not order the work
When
Posted within 3 days after learning of the construction and recorded within 3 days after posting
Served on or filed with
Posted conspicuously on the property and recorded in the recording district
Notarization
Required (signed before two witnesses or acknowledged before a notary)

AS 34.35.065

Alaska Public Works and Payment Bond Claims

Notice of Claim on Payment Bond

Required When It Applies
Who uses it
Claimants that contracted with a subcontractor and have no contract with the prime contractor
When
Within 90 days after the last furnishing for which the claim is made
Served on or filed with
The prime contractor, by prepaid registered mail or a method authorized for service of summons
Notarization
Not required
  • The notice states with substantial accuracy the amount claimed and the person to whom material was furnished or for whom labor was performed. Claimants with a direct contract with the prime need no notice.

AS 36.25.020(b)

Suit on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works over $100,000
When
After 90 days following last furnishing and no later than 1 year after final settlement of the prime contract
Served on or filed with
Filed in the name of the state or political subdivision for the claimant's use
Notarization
Not required
  • Final settlement is an administrative determination on completion and final payment. Obtain the public owner's records rather than counting from the claimant's own last invoice.

AS 36.25.010, 36.25.020

Frequently Asked Questions

Is there a statutory mechanics lien form in Alaska?

Alaska prescribes the content of its lien documents rather than templates. AS 34.35.064 lists what the Notice of Right to Lien must contain, including a warning in specified type size, and AS 34.35.070 lists the contents of the Claim of Lien.

Does an Alaska Claim of Lien have to be notarized?

The Claim of Lien must be verified by the oath of the claimant or another person with knowledge of the facts (AS 34.35.070). In practice the oath is taken before a notary. The owner's Notice of Completion must also be verified (AS 34.35.071).

Where do I file a mechanics lien in Alaska?

The Claim of Lien is recorded in the recording district where the property is located, within 120 days after completing the contract or ceasing to furnish (AS 34.35.068). The recorded document must also meet Alaska's general recording requirements.

How does a Notice of Completion affect my Alaska lien deadline?

After a valid Notice of Completion is recorded, a claimant that received the owner's advance notice, or that has not given a Notice of Right to Lien, must record a Claim of Lien or a Notice of Right to Lien within 15 days (AS 34.35.068). Recording a Notice of Right to Lien preserves the 120-day period.

What form releases a mechanics lien in Alaska?

Alaska has no prescribed release template. A claimant must promptly remove a recorded lien after full payment (AS 34.35.074). An owner or contractor may also record a bond for 150 percent of the claim, which substitutes for the lien (AS 34.35.072).

What form do I use for an Alaska public project bond claim?

A claimant that contracted with a subcontractor serves written notice on the prime contractor within 90 days after last furnishing, stating the amount and for whom the work was done. Suit is filed after 90 days and within 1 year after final settlement (AS 36.25.020).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.