Quick Answer
An Alaska subcontractor or supplier should give and record a Notice of Right to Lien, record a verified Claim of Lien within 120 days after completing its contract or ceasing to furnish, and file suit to foreclose within 6 months after recording (AS 34.35.064, 34.35.067, 34.35.068, 34.35.080).
The Notice of Right to Lien is optional, but it matters. Giving it to the owner before furnishing shifts the burden on the owner's knowledge and consent, and recording it protects priority and preserves the 120-day period if the owner later records a Notice of Completion.
After a valid Notice of Completion is recorded, a claimant that received the owner's advance notice, or that has not given a Notice of Right to Lien, must record a Claim of Lien or a Notice of Right to Lien within 15 days (AS 34.35.068, 34.35.071).
On public works, a claimant that contracted with a subcontractor rather than the prime must give the prime written notice within 90 days after last furnishing. Suit follows after 90 days and no later than 1 year after final settlement of the prime contract (AS 36.25.020).
Alaska's lien statute, AS 34.35.050 to 34.35.120, uses a small set of core documents: the optional Notice of Right to Lien, the verified Claim of Lien, the owner's Notice of Completion, and a foreclosure action within 6 months.
Alaska prescribes the content of each document rather than a fill-in template. It also offers a stop-lending notice to construction lenders and a statutory bond that substitutes for the lien. Public works claims run against the contractor's payment bond under AS 36.25.020.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
Alaska Preliminary Notices
Notice of Right to Lien
- Who uses it
- Contractors, subcontractors, suppliers, design professionals and other potential lien claimants
- When
- Given to the owner before furnishing; may be recorded after contracting or first furnishing
- Served on or filed with
- The owner or owner's agent, and recorded in the recording district where the property is located
- Notarization
- Not expressly required; a verified recorded copy is the safer practice
- The statute prescribes its content, including the legal description, the parties, a description of the furnishing, and a warning in specified type size.
- Giving and recording are separate steps with separate effects. Recording preserves the 120-day lien period after a Notice of Completion.
AS 34.35.064, 34.35.067
Stop-Lending Notice
- Who uses it
- Claimants whose payment is past due on a construction-financed project
- When
- While financing disbursements remain; it expires on the 91st day after the lender receives it unless suit is filed and the lender is notified
- Served on or filed with
- The construction lender, with copies to the owner and each prime contractor in the chain
- Notarization
- Required (claimant verification)
- The notice directs the lender to stop disbursements and states the unpaid amount. It must be revoked promptly after payment in full.
AS 34.35.062
Alaska Lien Claim and Service
Claim of Lien
- Who uses it
- All lien claimants
- When
- Within 120 days after completing the construction contract or ceasing to furnish; a shorter 15-day rule may apply after a Notice of Completion
- Served on or filed with
- Recorded in the recording district where the property is located
- Notarization
- Required (verified by oath of the claimant or another person with knowledge)
- The claim states the legal description, owner, claimant and hiring party, a description of the furnishing and contract price, the amount due, and the last furnishing date.
- The statute does not separately require service of the recorded claim on the owner.
AS 34.35.068, 34.35.070
Alaska Enforcing the Lien
Extension Notice
- Who uses it
- Lien claimants who need more time to sue
- When
- Within the original 6 months after the Claim of Lien is recorded
- Served on or filed with
- Recorded in the same office as the Claim of Lien
- Notarization
- Not expressly required
- The notice identifies the original recording and the balance owed. Suit must then be filed within 6 months after the extension is recorded.
AS 34.35.080
Complaint to Foreclose Lien
- Who uses it
- Lien claimants
- When
- Within 6 months after recording the Claim of Lien, or within the extended period
- Served on or filed with
- Filed in superior court; join persons personally liable and recorded lienholders
- Notarization
- Not required
AS 34.35.080
Notice of Pendency of Action (Lis Pendens)
- Who uses it
- Foreclosing claimants
- When
- When the complaint is filed or afterward, before a protected later interest is recorded
- Served on or filed with
- Recorded in the recording district where the property is located
- Notarization
- Not required
AS 09.45.940; AS 34.35.080
Alaska Releasing or Bonding Off a Lien
Bond (Lien Release Bond)
- Who uses it
- Owners, prime contractors or subcontractors
- When
- Before or after the enforcement suit is filed
- Served on or filed with
- Recorded where the lien is recorded
- Notarization
- Not required
- The bond must equal 150 percent of the lien claim and guarantee payment of any recovery plus reasonable costs of suit.
AS 34.35.072
Release of Lien
- Who uses it
- Lien claimants
- When
- Promptly after full payment, or after discovering the lien is erroneous, unjust, premature or excessive
- Served on or filed with
- Recorded in the recording district, referencing the released instrument
- Notarization
- Not required by the lien statute; general recording rules apply
- A claimant that fails to remove a lien when required is exposed to statutory damages and injunctive relief.
AS 34.35.074
Alaska Owner Notices and Forms
Notice of Completion
- Who uses it
- Owners
- When
- After actual completion; the owner must first give qualifying claimants at least 5 days' advance notice with a copy
- Served on or filed with
- Recorded in the recording district where the property is located
- Notarization
- Required (signed and verified by the owner)
- A Notice of Completion recorded before actual completion is ineffective.
AS 34.35.071
Notice of Nonresponsibility
- Who uses it
- Owners or others with an interest who did not order the work
- When
- Posted within 3 days after learning of the construction and recorded within 3 days after posting
- Served on or filed with
- Posted conspicuously on the property and recorded in the recording district
- Notarization
- Required (signed before two witnesses or acknowledged before a notary)
AS 34.35.065
Alaska Public Works and Payment Bond Claims
Notice of Claim on Payment Bond
- Who uses it
- Claimants that contracted with a subcontractor and have no contract with the prime contractor
- When
- Within 90 days after the last furnishing for which the claim is made
- Served on or filed with
- The prime contractor, by prepaid registered mail or a method authorized for service of summons
- Notarization
- Not required
- The notice states with substantial accuracy the amount claimed and the person to whom material was furnished or for whom labor was performed. Claimants with a direct contract with the prime need no notice.
AS 36.25.020(b)
Suit on Payment Bond
- Who uses it
- Unpaid claimants on bonded public works over $100,000
- When
- After 90 days following last furnishing and no later than 1 year after final settlement of the prime contract
- Served on or filed with
- Filed in the name of the state or political subdivision for the claimant's use
- Notarization
- Not required
- Final settlement is an administrative determination on completion and final payment. Obtain the public owner's records rather than counting from the claimant's own last invoice.
AS 36.25.010, 36.25.020
Frequently Asked Questions
Is there a statutory mechanics lien form in Alaska?
Alaska prescribes the content of its lien documents rather than templates. AS 34.35.064 lists what the Notice of Right to Lien must contain, including a warning in specified type size, and AS 34.35.070 lists the contents of the Claim of Lien.
Does an Alaska Claim of Lien have to be notarized?
The Claim of Lien must be verified by the oath of the claimant or another person with knowledge of the facts (AS 34.35.070). In practice the oath is taken before a notary. The owner's Notice of Completion must also be verified (AS 34.35.071).
Where do I file a mechanics lien in Alaska?
The Claim of Lien is recorded in the recording district where the property is located, within 120 days after completing the contract or ceasing to furnish (AS 34.35.068). The recorded document must also meet Alaska's general recording requirements.
How does a Notice of Completion affect my Alaska lien deadline?
After a valid Notice of Completion is recorded, a claimant that received the owner's advance notice, or that has not given a Notice of Right to Lien, must record a Claim of Lien or a Notice of Right to Lien within 15 days (AS 34.35.068). Recording a Notice of Right to Lien preserves the 120-day period.
What form releases a mechanics lien in Alaska?
Alaska has no prescribed release template. A claimant must promptly remove a recorded lien after full payment (AS 34.35.074). An owner or contractor may also record a bond for 150 percent of the claim, which substitutes for the lien (AS 34.35.072).
What form do I use for an Alaska public project bond claim?
A claimant that contracted with a subcontractor serves written notice on the prime contractor within 90 days after last furnishing, stating the amount and for whom the work was done. Suit is filed after 90 days and within 1 year after final settlement (AS 36.25.020).
Related Alaska Resources
Alaska Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Alaska Notice Requirements
Who must give notice, when, and how.
Alaska Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Alaska Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Alaska law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.