Your Guide to The Miller Act Vs. The Little Miller Act
If you are somehow related to construction and you have a specialization in dealing with government contracts then you must have probably heard about the miller act. We will discuss the miller act vs. the Little Miller Act, both versions which can make an impact on your work.
Also, read for The Building Blocks of Modular Construction: Contractual & Lien Considerations
What is the Miller Act?
The miller act is a protector of construction parties from the first and second-tier who are looking to recover the outstanding debts. In the miller act, the commanding contractor will have to obtain the two surety bonds; one of them is a payment bond and the other is the performance bond. Under the performance bond, the satisfactory completion of the project is agreed on a duly sign contract. Now under the payment bond, all the suppliers and sub contractors are assured of their due payment. This miller act was passed in the year 1935. States over the years though started to bring upon the changes. All those state-wise changes were known as the little miller acts.
The Miller Act vs. the Little Miller Act
Under the miller act, contractors are expected to secure payment bonds for contracts that are more than $100,000. For other protection of payments, a contract between $30k to $100k is provided. If the payment is not made to suppliers or sub contractors, they can straightaway sue the contractor in district US court.
Under the little miller act, there are different statutes under different states. They all have their own set of rules and guidelines. So it comes down to the fact that if the construction project is being implemented under the federal government, the miller guidelines are followed and if the project is state-sponsored, the little miller act is put in place.
Little Miller Act Differences among States
It is very clear that the little miller act will vary from state to state and one is advised to study the specific guidelines laid by the state under the act before the project is commenced. Also, one should make sure that the entire legal obligations under the act are rightfully met. Things to look upon are-
- Contract amount requirement
The amount of payment bond that has to be secured by the contractor under the federal miller act can be different in each state. For example, that bond payment in Missouri can be around $25000 and in states like Tennessee, the amount could exceed almost $100,000.
- Bond claim filing/notice requirements
The deadline to file a bond claim is another variation that differs with each state. Let us consider an example of it. in Illinois, one is expected to file bond claims within the period of 180 days when the last work or furnishing is completed. But in contrast, the claimant in Florida will not have to file any notice in this regard. In Louisiana, the deadline for filing is of 45 days.
- Bond claim statute of limitation
This means the deadline to file the lawsuit for the bond claim. Each state has its time frame within which one is expected to file the bond claim. The little miller act will have all the details concerning each state.
How to File Little Miller Act Bond Claims
One should have a clear understanding of the eligibility to file the bond claim. Few states allow only the construction parties of a first and second tier to file the claim. Hiring an attorney will be much more advisable as he will have all the experience to share in construction disputes.
We at the National Lien and Bond Claim System will be happy to help you in such cases. We also have a great team to deal with cases related to a lien in Texas and Florida. We would be glad to help you in every way.
Also, read for
- Questions about the Impact of Sloan v. Liberty Mutual
- What Are Liens and How Can They Impact Your Property?
Related Articles

The Little Miller Act: What is it and How is it Relevant to Your Projects?
Public projects require prime contractors to post performance and payment bonds, but Little Miller Act rules vary by state. This post explains bond thresholds, coverage percentages, notice requirements, and filing deadlines for subs and suppliers.
Read Article
The Miller Act Deadlines That Decide Whether You Get Paid on a Federal Project
You cannot lien a federal courthouse, an Army base, or a VA hospital. On a federal construction project the payment bond is your security, and two Miller Act deadlines decide whether you collect: a 90-day notice and a one-year suit window.
Read Article
Enforcing Little Miller Act Claims in Arizona
An overview of Arizona Little Miller Act bond claims on public contracts of $100,000 or more, covering the performance and payment bond requirements, the 90-day preliminary notice, and the rule that suit be filed after 90 days but within one year.