HomeCaliforniaMechanics Lien Forms
California Mechanics Lien Forms

California Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on California construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A California subcontractor or supplier needs, in order, a Preliminary 20-Day Notice within 20 days after first furnishing, a verified Claim of Mechanics Lien recorded with the county recorder, and a foreclosure action within 90 days after recording (Cal. Civ. Code §§ 8204, 8414, 8460).

A direct contractor records before the earlier of 90 days after completion or 60 days after a recorded Notice of Completion or Cessation. Every other claimant records before the earlier of 90 days after completion or 30 days after either notice (§§ 8412, 8414).

The Claim of Mechanics Lien must include the Notice of Mechanics Lien and a proof of service affidavit, and it must be served on the owner. A lien not served as the statute prescribes is unenforceable (§ 8416). A lis pendens is recorded within 20 days after suit is filed.

On public works, a claimant serves a preliminary notice on the public entity and direct contractor, may serve a stop payment notice on the public entity, and may sue on the payment bond within 6 months after the stop payment notice period expires (§§ 9300, 9356, 9558).

California's lien law, Civil Code §§ 8000 to 9566, gives claimants three remedies on private work: the mechanics lien, the stop payment notice, and a claim on any payment bond. Each depends on a timely Preliminary 20-Day Notice, which has prescribed content and a boldface warning.

The Claim of Mechanics Lien is verified, includes the Notice of Mechanics Lien and a proof of service affidavit, and is recorded with the county recorder. On public works, the remedies are the public stop payment notice and the payment bond, since public property cannot be liened.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

California Preliminary Notices

Preliminary 20-Day Notice

Statutory Form
Required When It Applies
Who uses it
Subcontractors, suppliers, equipment lessors and design professionals; laborers are exempt
When
Within 20 days after first furnishing; a late notice protects work furnished within the 20 days before it and afterward
Served on or filed with
The owner or reputed owner, direct contractor and construction lender; a claimant contracting directly with the owner serves only the lender
Notarization
Not required
  • The notice carries general project information and a prescribed boldface warning. It is a prerequisite to the lien, stop payment notice and private bond remedies.
  • A claimant may also file the notice with the county recorder to receive notification of a recorded Notice of Completion or Cessation; this is optional.

Cal. Civ. Code §§ 8102, 8200, 8202, 8204, 8214

Proof of Notice Declaration

Required When It Applies
Who uses it
Claimants proving service of any statutory notice
When
Completed after service; used when proof is needed
Served on or filed with
Retained as evidence; not normally recorded
Notarization
Not required (declaration under penalty of perjury)

Cal. Civ. Code § 8118

California Lien Claim and Service

Claim of Mechanics Lien with Notice of Mechanics Lien

Statutory Form
Required When It Applies
Who uses it
All lien claimants
When
Direct contractors: before the earlier of 90 days after completion or 60 days after a recorded Notice of Completion or Cessation. Others: before the earlier of 90 days after completion or 30 days after either notice
Served on or filed with
Recorded with the county recorder; a copy with the Notice of Mechanics Lien is served on the owner or reputed owner
Notarization
Verification required; acknowledgment is not required for recording
  • The proof of service affidavit is part of the recorded claim. Failure to serve as the statute prescribes makes the lien unenforceable.
  • Completion is a statutory event, including specified cessation periods, not the claimant's own last day of work.

Cal. Civ. Code §§ 8412, 8414, 8416

California Enforcing the Lien

Complaint to Enforce Lien and Notice of Pendency of Action

Required When It Applies
Who uses it
Lien claimants
When
Suit within 90 days after recording the lien; lis pendens within 20 days after filing suit
Served on or filed with
Complaint filed in superior court; lis pendens recorded in the county where the property is located
Notarization
Not required

Cal. Civ. Code §§ 8460, 8461

Notice of Extension of Credit

Optional
Who uses it
Claimants and owners who agree to extend credit
When
Recorded within the original 90-day enforcement period; suit then within 90 days after the credit expires, never later than 1 year after completion
Served on or filed with
Recorded with the county recorder
Notarization
Not required

Cal. Civ. Code § 8460

Stop Payment Notice (Private Works)

Optional
Who uses it
Lien claimants; a direct contractor may serve a lender but not the owner
When
Before the lien recording deadline expires; suit after 10 days and within 90 days after that deadline
Served on or filed with
The owner or its architect, or the responsible person at the lender's branch administering the construction funds
Notarization
Verification required
  • A lender stop payment notice may be unbonded, but a claimant bond of 125 percent generally obliges the lender to withhold, subject to the recorded payment bond exception. Notice of commencement of suit goes to recipients within 5 days.

Cal. Civ. Code §§ 8502, 8520, 8530, 8532, 8550

California Releasing or Bonding Off a Lien

Mechanics Lien Release Bond

Optional
Who uses it
Owners, interested owners, direct contractors or subcontractors
When
Before or after the foreclosure suit is filed
Served on or filed with
Recorded with the county recorder; notice and a copy go to the claimant
Notarization
Not required; surety execution rules apply
  • The admitted surety bond equals 125 percent of the lien. The claimant must sue on the bond within 6 months after notice of it.

Cal. Civ. Code § 8424

Petition for Release Order

Optional
Who uses it
Owners, after the time to enforce the lien has expired
When
After demanding a release at least 10 days earlier; serve the petition and hearing notice at least 15 days before the hearing
Served on or filed with
Filed in superior court with a certified copy of the lien; the resulting order is recorded
Notarization
Verification required for the petition

Cal. Civ. Code §§ 8480, 8482, 8484, 8486, 8490

Release of Mechanics Lien

Required When It Applies
Who uses it
Lien claimants
When
On payment or settlement
Served on or filed with
Recorded with the county recorder
Notarization
Not prescribed by the lien statutes; check county recording requirements
  • A recorded release clears the encumbrance. It is different from the four statutory waiver forms, which waive lien, stop payment notice and bond rights in exchange for payment.

Cal. Civ. Code §§ 8482, 8490

California Owner Notices and Forms

Notice of Completion and Notice of Cessation

Optional
Who uses it
Owners
When
Notice of Completion on or within 15 days after completion; Notice of Cessation after 30 continuous days without labor; copies within 10 days after recording
Served on or filed with
Recorded with the county recorder; copies to the direct contractor and preliminary notice claimants
Notarization
Verification required; acknowledgment not required
  • Failure to send a copy keeps the full 90-day period for that claimant. Owner-occupied residences of four or fewer units are exempt from the copy requirement. California has no general notice of commencement.

Cal. Civ. Code §§ 8182, 8184, 8188, 8190

Notice of Nonresponsibility

Optional
Who uses it
Owners or interested persons who did not contract for the work
When
Posted and recorded within 10 days after learning of the work
Served on or filed with
Posted on the site and recorded with the county recorder
Notarization
Verification required

Cal. Civ. Code § 8444

California Public Works and Payment Bond Claims

Private Payment Bond Claim

Optional
Who uses it
Claimants on private projects with a payment bond
When
Preliminary notice, or substitute notice within 15 days after a recorded Notice of Completion or 75 days after completion; suit within 6 months after completion if the bond was recorded before completion
Served on or filed with
The surety and principal; suit filed in superior court
Notarization
Not required

Cal. Civ. Code §§ 8609, 8610, 8612

Preliminary 20-Day Notice (Public Works)

Required When It Applies
Who uses it
Claimants without a direct contract with the direct contractor; laborers are exempt
When
Within 20 days after first furnishing; a later notice reaches back 20 days
Served on or filed with
The public entity and the direct contractor
Notarization
Not required

Cal. Civ. Code §§ 9300, 9302, 9304

Stop Payment Notice (Public Works)

Required When It Applies
Who uses it
Claimants other than the direct contractor
When
Within 30 days after a recorded Notice of Completion, acceptance or cessation, or 90 days after completion or cessation if none; suit after 10 days and within 90 days after the notice period expires
Served on or filed with
The awarding department's director on state work, or the disbursing officer or awarding body on local work
Notarization
Verification required
  • No claimant bond is required. Paying $10 with the notice entitles the claimant to notice of the enforcement deadline, and the entity must be told within 5 days after suit is filed.

Cal. Civ. Code §§ 9352, 9354, 9356, 9362, 9502, 9504

Public Works Payment Bond Claim

Required When It Applies
Who uses it
Claimants other than the direct contractor on public contracts over $25,000
When
Preliminary notice, or substitute notice within 15 days after a recorded Notice of Completion or 75 days after completion; suit within 6 months after the stop payment notice period expires
Served on or filed with
The surety and principal; suit filed in superior court
Notarization
Not required
  • Serving a stop payment notice is not required for bond recovery.

Cal. Civ. Code §§ 9550, 9558, 9560, 9564

Frequently Asked Questions

Is there a statutory mechanics lien form in California?

California prescribes the content of the Claim of Mechanics Lien and the Notice of Mechanics Lien, including a statutory warning to the owner (Cal. Civ. Code § 8416), and the content and boldface warning of the Preliminary 20-Day Notice (§ 8202). Lien waivers must follow four statutory forms (§§ 8132 to 8138).

Does a California mechanics lien have to be notarized?

The Claim of Mechanics Lien must be verified, but it may be recorded without an acknowledgment (Cal. Civ. Code § 8416). A verification under penalty of perjury satisfies the requirement, so notarization is not required.

Where do I file a mechanics lien in California?

Record the Claim of Mechanics Lien with the county recorder where the property is located and serve the owner with a copy and the Notice of Mechanics Lien (Cal. Civ. Code § 8416). Deadlines depend on completion and any recorded Notice of Completion or Cessation (§§ 8412, 8414).

What happens if I miss the 20-day preliminary notice deadline in California?

A late Preliminary 20-Day Notice still protects labor and materials furnished within the 20 days before it was given and afterward (Cal. Civ. Code § 8204). Earlier work is not covered.

What form releases a mechanics lien in California?

A paid claimant records a release of the lien. An owner may record a lien release bond for 125 percent of the claim (Cal. Civ. Code § 8424), or, once the time to enforce has expired, petition the court for a release order (§ 8480).

What form do I use for a California public project bond claim?

Serve a Preliminary 20-Day Notice on the public entity and direct contractor, or a timely substitute notice on the surety and principal. Suit on the payment bond must be filed within 6 months after the stop payment notice period expires (Cal. Civ. Code §§ 9560, 9558).

Is a California stop payment notice the same as a lien?

No. A stop payment notice reaches construction funds held by the owner, lender or public entity rather than the property. It must be verified and served before the applicable deadline, and enforced by suit within 90 days after that deadline (Cal. Civ. Code §§ 8502, 8550, 9502).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us