California Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on California construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A California subcontractor or supplier needs, in order, a Preliminary 20-Day Notice within 20 days after first furnishing, a verified Claim of Mechanics Lien recorded with the county recorder, and a foreclosure action within 90 days after recording (Cal. Civ. Code §§ 8204, 8414, 8460).
A direct contractor records before the earlier of 90 days after completion or 60 days after a recorded Notice of Completion or Cessation. Every other claimant records before the earlier of 90 days after completion or 30 days after either notice (§§ 8412, 8414).
The Claim of Mechanics Lien must include the Notice of Mechanics Lien and a proof of service affidavit, and it must be served on the owner. A lien not served as the statute prescribes is unenforceable (§ 8416). A lis pendens is recorded within 20 days after suit is filed.
On public works, a claimant serves a preliminary notice on the public entity and direct contractor, may serve a stop payment notice on the public entity, and may sue on the payment bond within 6 months after the stop payment notice period expires (§§ 9300, 9356, 9558).
California's lien law, Civil Code §§ 8000 to 9566, gives claimants three remedies on private work: the mechanics lien, the stop payment notice, and a claim on any payment bond. Each depends on a timely Preliminary 20-Day Notice, which has prescribed content and a boldface warning.
The Claim of Mechanics Lien is verified, includes the Notice of Mechanics Lien and a proof of service affidavit, and is recorded with the county recorder. On public works, the remedies are the public stop payment notice and the payment bond, since public property cannot be liened.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
California Preliminary Notices
Preliminary 20-Day Notice
- Who uses it
- Subcontractors, suppliers, equipment lessors and design professionals; laborers are exempt
- When
- Within 20 days after first furnishing; a late notice protects work furnished within the 20 days before it and afterward
- Served on or filed with
- The owner or reputed owner, direct contractor and construction lender; a claimant contracting directly with the owner serves only the lender
- Notarization
- Not required
- The notice carries general project information and a prescribed boldface warning. It is a prerequisite to the lien, stop payment notice and private bond remedies.
- A claimant may also file the notice with the county recorder to receive notification of a recorded Notice of Completion or Cessation; this is optional.
Cal. Civ. Code §§ 8102, 8200, 8202, 8204, 8214
Proof of Notice Declaration
- Who uses it
- Claimants proving service of any statutory notice
- When
- Completed after service; used when proof is needed
- Served on or filed with
- Retained as evidence; not normally recorded
- Notarization
- Not required (declaration under penalty of perjury)
Cal. Civ. Code § 8118
California Lien Claim and Service
Claim of Mechanics Lien with Notice of Mechanics Lien
- Who uses it
- All lien claimants
- When
- Direct contractors: before the earlier of 90 days after completion or 60 days after a recorded Notice of Completion or Cessation. Others: before the earlier of 90 days after completion or 30 days after either notice
- Served on or filed with
- Recorded with the county recorder; a copy with the Notice of Mechanics Lien is served on the owner or reputed owner
- Notarization
- Verification required; acknowledgment is not required for recording
- The proof of service affidavit is part of the recorded claim. Failure to serve as the statute prescribes makes the lien unenforceable.
- Completion is a statutory event, including specified cessation periods, not the claimant's own last day of work.
Cal. Civ. Code §§ 8412, 8414, 8416
California Enforcing the Lien
Complaint to Enforce Lien and Notice of Pendency of Action
- Who uses it
- Lien claimants
- When
- Suit within 90 days after recording the lien; lis pendens within 20 days after filing suit
- Served on or filed with
- Complaint filed in superior court; lis pendens recorded in the county where the property is located
- Notarization
- Not required
Cal. Civ. Code §§ 8460, 8461
Notice of Extension of Credit
- Who uses it
- Claimants and owners who agree to extend credit
- When
- Recorded within the original 90-day enforcement period; suit then within 90 days after the credit expires, never later than 1 year after completion
- Served on or filed with
- Recorded with the county recorder
- Notarization
- Not required
Cal. Civ. Code § 8460
Stop Payment Notice (Private Works)
- Who uses it
- Lien claimants; a direct contractor may serve a lender but not the owner
- When
- Before the lien recording deadline expires; suit after 10 days and within 90 days after that deadline
- Served on or filed with
- The owner or its architect, or the responsible person at the lender's branch administering the construction funds
- Notarization
- Verification required
- A lender stop payment notice may be unbonded, but a claimant bond of 125 percent generally obliges the lender to withhold, subject to the recorded payment bond exception. Notice of commencement of suit goes to recipients within 5 days.
Cal. Civ. Code §§ 8502, 8520, 8530, 8532, 8550
California Releasing or Bonding Off a Lien
Mechanics Lien Release Bond
- Who uses it
- Owners, interested owners, direct contractors or subcontractors
- When
- Before or after the foreclosure suit is filed
- Served on or filed with
- Recorded with the county recorder; notice and a copy go to the claimant
- Notarization
- Not required; surety execution rules apply
- The admitted surety bond equals 125 percent of the lien. The claimant must sue on the bond within 6 months after notice of it.
Cal. Civ. Code § 8424
Petition for Release Order
- Who uses it
- Owners, after the time to enforce the lien has expired
- When
- After demanding a release at least 10 days earlier; serve the petition and hearing notice at least 15 days before the hearing
- Served on or filed with
- Filed in superior court with a certified copy of the lien; the resulting order is recorded
- Notarization
- Verification required for the petition
Cal. Civ. Code §§ 8480, 8482, 8484, 8486, 8490
Release of Mechanics Lien
- Who uses it
- Lien claimants
- When
- On payment or settlement
- Served on or filed with
- Recorded with the county recorder
- Notarization
- Not prescribed by the lien statutes; check county recording requirements
- A recorded release clears the encumbrance. It is different from the four statutory waiver forms, which waive lien, stop payment notice and bond rights in exchange for payment.
Cal. Civ. Code §§ 8482, 8490
California Owner Notices and Forms
Notice of Completion and Notice of Cessation
- Who uses it
- Owners
- When
- Notice of Completion on or within 15 days after completion; Notice of Cessation after 30 continuous days without labor; copies within 10 days after recording
- Served on or filed with
- Recorded with the county recorder; copies to the direct contractor and preliminary notice claimants
- Notarization
- Verification required; acknowledgment not required
- Failure to send a copy keeps the full 90-day period for that claimant. Owner-occupied residences of four or fewer units are exempt from the copy requirement. California has no general notice of commencement.
Cal. Civ. Code §§ 8182, 8184, 8188, 8190
Notice of Nonresponsibility
- Who uses it
- Owners or interested persons who did not contract for the work
- When
- Posted and recorded within 10 days after learning of the work
- Served on or filed with
- Posted on the site and recorded with the county recorder
- Notarization
- Verification required
Cal. Civ. Code § 8444
California Public Works and Payment Bond Claims
Private Payment Bond Claim
- Who uses it
- Claimants on private projects with a payment bond
- When
- Preliminary notice, or substitute notice within 15 days after a recorded Notice of Completion or 75 days after completion; suit within 6 months after completion if the bond was recorded before completion
- Served on or filed with
- The surety and principal; suit filed in superior court
- Notarization
- Not required
Cal. Civ. Code §§ 8609, 8610, 8612
Preliminary 20-Day Notice (Public Works)
- Who uses it
- Claimants without a direct contract with the direct contractor; laborers are exempt
- When
- Within 20 days after first furnishing; a later notice reaches back 20 days
- Served on or filed with
- The public entity and the direct contractor
- Notarization
- Not required
Cal. Civ. Code §§ 9300, 9302, 9304
Stop Payment Notice (Public Works)
- Who uses it
- Claimants other than the direct contractor
- When
- Within 30 days after a recorded Notice of Completion, acceptance or cessation, or 90 days after completion or cessation if none; suit after 10 days and within 90 days after the notice period expires
- Served on or filed with
- The awarding department's director on state work, or the disbursing officer or awarding body on local work
- Notarization
- Verification required
- No claimant bond is required. Paying $10 with the notice entitles the claimant to notice of the enforcement deadline, and the entity must be told within 5 days after suit is filed.
Cal. Civ. Code §§ 9352, 9354, 9356, 9362, 9502, 9504
Public Works Payment Bond Claim
- Who uses it
- Claimants other than the direct contractor on public contracts over $25,000
- When
- Preliminary notice, or substitute notice within 15 days after a recorded Notice of Completion or 75 days after completion; suit within 6 months after the stop payment notice period expires
- Served on or filed with
- The surety and principal; suit filed in superior court
- Notarization
- Not required
- Serving a stop payment notice is not required for bond recovery.
Cal. Civ. Code §§ 9550, 9558, 9560, 9564
Frequently Asked Questions
Is there a statutory mechanics lien form in California?
California prescribes the content of the Claim of Mechanics Lien and the Notice of Mechanics Lien, including a statutory warning to the owner (Cal. Civ. Code § 8416), and the content and boldface warning of the Preliminary 20-Day Notice (§ 8202). Lien waivers must follow four statutory forms (§§ 8132 to 8138).
Does a California mechanics lien have to be notarized?
The Claim of Mechanics Lien must be verified, but it may be recorded without an acknowledgment (Cal. Civ. Code § 8416). A verification under penalty of perjury satisfies the requirement, so notarization is not required.
Where do I file a mechanics lien in California?
Record the Claim of Mechanics Lien with the county recorder where the property is located and serve the owner with a copy and the Notice of Mechanics Lien (Cal. Civ. Code § 8416). Deadlines depend on completion and any recorded Notice of Completion or Cessation (§§ 8412, 8414).
What happens if I miss the 20-day preliminary notice deadline in California?
A late Preliminary 20-Day Notice still protects labor and materials furnished within the 20 days before it was given and afterward (Cal. Civ. Code § 8204). Earlier work is not covered.
What form releases a mechanics lien in California?
A paid claimant records a release of the lien. An owner may record a lien release bond for 125 percent of the claim (Cal. Civ. Code § 8424), or, once the time to enforce has expired, petition the court for a release order (§ 8480).
What form do I use for a California public project bond claim?
Serve a Preliminary 20-Day Notice on the public entity and direct contractor, or a timely substitute notice on the surety and principal. Suit on the payment bond must be filed within 6 months after the stop payment notice period expires (Cal. Civ. Code §§ 9560, 9558).
Is a California stop payment notice the same as a lien?
No. A stop payment notice reaches construction funds held by the owner, lender or public entity rather than the property. It must be verified and served before the applicable deadline, and enforced by suit within 90 days after that deadline (Cal. Civ. Code §§ 8502, 8550, 9502).
Related California Resources
California Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
California Notice Requirements
Who must give notice, when, and how.
California Lien Waivers
Statutory forms, waiver types, and enforceability rules.
California Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about California law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.