Every notice, lien, enforcement, release, and bond claim document used on Colorado construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Colorado claimant needs, in order, a Notice of Intent to File a Lien Statement served at least 10 days before recording, a sworn lien statement recorded within 4 months after last furnishing, and a foreclosure action with a recorded lis pendens within 6 months (C.R.S. §§ 38-22-109, 38-22-110).

The notice of intent goes to the owner or reputed owner and the principal contractor, by personal service or registered or certified mail, return receipt requested. An affidavit of service is recorded with the lien statement (§ 38-22-109(3)).

Laborers paid by the day or piece who furnish no laborers or materials must record within 2 months after completion of the improvement. Colorado has no owner's notice of completion; completion is a fact, and 3 months' discontinuance counts as completion (§ 38-22-109).

On public works, a claimant may file a verified statement of claim with the public body up to final settlement and must then sue within 90 days after the published settlement date. A direct suit on the payment bond must be filed within 6 months after completion (C.R.S. §§ 38-26-105, 38-26-107).

Colorado has no preliminary notice requirement. A claimant serves a Notice of Intent to File a Lien Statement at least 10 days before recording, records a sworn lien statement within 4 months after last furnishing, and must sue and record a lis pendens within 6 months.

Colorado also offers optional notices that protect funds during the job, including a notice to withhold construction funds and a notice to the disburser to pay the claimant directly. Public works claims run against withheld contract funds or the payment bond under C.R.S. §§ 38-26-105 to 38-26-107.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Colorado Preliminary Notices

Notice to Withhold Construction Funds

Optional
Who uses it
Claimants other than the principal contractor
When
At any time, best before funds are disbursed
Served on or filed with
The owner or reputed owner, its agent or architect, or the financing institution or disburser
Notarization
Not required
  • It states the work or materials, the contracting party, and the approximate value completed and agreed. It requires the recipient to withhold enough money due or to become due.

C.R.S. § 38-22-102(4)

Notice to Disburse Direct

Optional
Who uses it
Lien claimants on projects with a disburser
When
Before the relevant disbursement
Served on or filed with
The disburser, by certified mail, personal delivery, or leaving it with the person in charge at its residence or business
Notarization
Not required
  • It identifies the property, the claimant, its contracting party and the contract, and requires direct payment from funds due that party. It does not replace the lien statement.

C.R.S. § 38-22-126(4)

Colorado Notices Before Filing a Lien

Notice of Intent to File a Lien Statement

Required When It Applies
Who uses it
All lien claimants
When
At least 10 days before the lien statement is recorded
Served on or filed with
The owner or reputed owner and the principal contractor, or their agents, by personal service or registered or certified mail, return receipt requested
Notarization
Not required for the notice; the affidavit of service must be sworn
  • Record the affidavit of service or mailing with the lien statement.

C.R.S. § 38-22-109(3)

Colorado Lien Claim and Service

Lien Statement

Notarized
Required When It Applies
Who uses it
All lien claimants
When
Within 4 months after last furnishing; day or piece laborers within 2 months after completion of the improvement
Served on or filed with
Recorded with the county clerk and recorder where the property is located
Notarization
Required (signed and sworn by the claimant or its representative)
  • The statement names the owner or reputed owner, the claimant and contractor, describes the property, and states the amount due. A new or amended statement may be recorded within the same period to correct mistakes.

C.R.S. § 38-22-109

Notice of Extension

Optional
Who uses it
Claimants on ongoing projects
When
Recorded within the original lien filing period; renew before it expires if work is unfinished
Served on or filed with
Recorded with the county clerk and recorder
Notarization
Not required
  • It extends the filing period to the earlier of 4 months after completion or 6 months after the notice. Owners may demand termination once the supply agreement ends.

C.R.S. § 38-22-109(10), (11), (12)

Colorado Enforcing the Lien

Annual Affidavit of Noncompletion

Notarized
Required When It Applies
Who uses it
Claimants whose lien remains alive while improvements are incomplete
When
Within 30 days after each anniversary of recording, if enforcement has not begun
Served on or filed with
Recorded with the county clerk and recorder
Notarization
Required (affidavit)
  • It does not revive a lien that has already expired under § 38-22-110.

C.R.S. § 38-22-109(8), (9)

Foreclosure Action and Notice of Lis Pendens

Required When It Applies
Who uses it
Lien claimants
When
Both within 6 months after the last work or furnishing or completion of the improvement, as the statute measures it
Served on or filed with
Action filed in district court; lis pendens recorded in the county where the property is located
Notarization
Not required
  • The 6 months do not run from recording the lien. Calendar completion as well as the claimant's own last date.

C.R.S. § 38-22-110

Colorado Releasing or Bonding Off a Lien

Substitution of Bond for Lien

Optional
Who uses it
Owners of an interest in the property
When
After the lien is recorded
Served on or filed with
Filed with the district court in the county of the property; the clerk's certificate is recorded where the lien was recorded
Notarization
Not required
  • The undertaking equals 1.5 times the lien plus allowed costs and requires court approval. Recording the certificate releases the property and any lis pendens. The claimant must sue on the bond within the foreclosure period.

C.R.S. §§ 38-22-131, 38-22-132, 38-22-133

Satisfaction and Release of Lien

Notarized
Required When It Applies
Who uses it
Lien claimants who have been paid or validly tendered payment
When
Within 10 days after a written request following payment or tender
Served on or filed with
Entered of record with the county clerk and recorder
Notarization
Required (acknowledgment of satisfaction)
  • A claimant that fails to release owes $10 per day afterward. Liens for more than is due are addressed separately under the excessive lien statute, amended in 2026.

C.R.S. §§ 38-22-118, 38-22-128

Colorado Owner Notices and Forms

Notice of Nonliability

Optional
Who uses it
Owners or interest holders who did not order the work
When
Within 5 days after learning of the work
Served on or filed with
Personally served on all providers, or posted and kept posted conspicuously on the property
Notarization
Not required

C.R.S. § 38-22-105

Disburser's Recorded Information Notice

Required When It Applies
Who uses it
Construction disbursers
When
Before the first disbursement
Served on or filed with
Recorded with the county clerk and recorder
Notarization
Not required
  • It lists the owner, contractor and disburser with addresses and phone numbers and the property description. Suppliers may also demand this information from the party that ordered their work.

C.R.S. § 38-22-126(2), (3)

Colorado Public Works and Payment Bond Claims

Verified Statement of Claim on Withheld Public Funds

Notarized
Required When It Applies
Who uses it
Unpaid subcontractors and suppliers on public works
When
Up to and including the time of final settlement; suit and a lis pendens filed with the public body within 90 days after the published settlement date
Served on or filed with
Filed with the public body that awarded the contract
Notarization
Required (verified statement of the amount due and unpaid)
  • On contracts over $150,000, the public body publishes notice of final settlement at least twice, no later than 10 days before settlement. A contractor may substitute a bond for 1.5 times the claim to release the funds.

C.R.S. §§ 38-26-107, 38-26-108

Suit on Public Works Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works
When
Within 6 months after completion of the work
Served on or filed with
Filed in district court against the contractor and surety
Notarization
Not required
  • A verified claim on withheld funds is not a prerequisite to this route, and a late bond suit cannot be relabeled as a contract claim (Pat's Construction Service v. Insurance Co. of the West, 141 P.3d 885 (Colo. App. 2005)).

C.R.S. §§ 38-26-105, 38-26-106

Frequently Asked Questions

Is there a statutory mechanics lien form in Colorado?

No. Colorado prescribes the contents of the lien statement but no template (C.R.S. § 38-22-109). The statement must identify the owner, the claimant and contractor, the property and the amount due, and it must be sworn.

Does a Colorado lien statement have to be notarized?

Yes. The lien statement must be signed and sworn to by the claimant or its representative, which requires an oath before a notary or other authorized officer (C.R.S. § 38-22-109). The affidavit of service of the notice of intent is also sworn.

Where do I file a mechanics lien in Colorado?

Record the lien statement with the county clerk and recorder where the property is located, within 4 months after last furnishing, after serving the notice of intent at least 10 days earlier (C.R.S. § 38-22-109).

Does Colorado have a notice of completion or preliminary notice?

No. Colorado has no owner's notice of completion and no mandatory preliminary notice. Completion is determined from the facts, and 3 months' discontinuance of work counts as completion (C.R.S. § 38-22-109(7)).

What form releases a mechanics lien in Colorado?

After payment or valid tender and a written request, the claimant must enter satisfaction of record within 10 days or owe $10 per day (C.R.S. § 38-22-118). An owner may also substitute a court-approved bond for 1.5 times the lien (§§ 38-22-131, 38-22-132).

What form do I use for a Colorado public project bond claim?

Colorado has two routes. File a verified statement of claim with the public body up to final settlement and sue within 90 days after the published settlement date (C.R.S. § 38-26-107), or sue directly on the payment bond within 6 months after completion (§ 38-26-105).

How long do I have to foreclose a Colorado mechanics lien?

The action must be commenced and a lis pendens recorded within 6 months after the last work or furnishing or completion of the improvement, as C.R.S. § 38-22-110 measures it. The period does not run from recording the lien.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.