Connecticut Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on Connecticut construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A Connecticut subcontractor or supplier needs, in order, a notice of intent to the owner, a sworn certificate of lien recorded with the town clerk within 90 days after ceasing work, and service of a true and attested copy on the owner within 30 days after recording (Conn. Gen. Stat. §§ 49-34, 49-35).
The notice of intent is not limited to residential work. Claimants other than original contractors serve it on each owner, and on each original contractor that recorded the required affidavit, no later than 90 days after ceasing to furnish (§ 49-35).
Foreclosure and a lis pendens must both be started within 1 year after recording, or within 60 days after final disposition of an application to discharge or reduce the lien, whichever is later (§ 49-39). An unforeclosed lien expires automatically.
On public works, an unpaid claimant serves a notice of claim on the surety, with a copy to the prime contractor, within 180 days after last furnishing. Suit follows within 1 year after last furnishing, with separate timing for retainage (§ 49-42).
A Connecticut mechanic's lien runs on a tight sequence: a notice of intent from claimants who did not contract with the owner, a sworn certificate of lien recorded with the town clerk within 90 days, service of a true and attested copy on the owner within 30 days, and foreclosure with a lis pendens within 1 year.
Connecticut also supplies a statutory form for releasing a recorded lien, an expedited owner application to discharge or reduce a lien, and a bond substitution procedure. Public works claims run against the payment bond under Conn. Gen. Stat. § 49-42.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
Connecticut Notices Before Filing a Lien
Notice of Intent to Claim a Lien
- Who uses it
- Subcontractors, suppliers and other claimants without a direct contract with the owner
- When
- After starting work and no later than 90 days after ceasing to furnish
- Served on or filed with
- Each owner, and each original contractor that recorded the statutory affidavit, by a proper officer or indifferent person
- Notarization
- Not required
- The notice states that the claimant has furnished or commenced work and intends to claim a lien. Service rules differ for local residents, nonresidents with local agents, and other nonresidents.
- A subcontractor whose written contract carries the owner's written assent is exempt.
Conn. Gen. Stat. § 49-35
Connecticut Lien Claim and Service
Certificate of Mechanic's Lien
- Who uses it
- All lien claimants
- When
- Within 90 days after ceasing to perform services or furnish materials
- Served on or filed with
- Lodged for recording with the town clerk of the town where the property is located
- Notarization
- Required (subscribed and sworn to by the claimant; an acknowledgment alone is not enough)
- The certificate describes the premises, the amount claimed, the persons against whom it is filed, the date work commenced, and that the amount is justly due as nearly as can be ascertained.
Conn. Gen. Stat. § 49-34
Service of True and Attested Copy of Certificate on Owner
- Who uses it
- All lien claimants
- When
- No later than 30 days after lodging the certificate
- Served on or filed with
- Each owner, using the service methods of § 49-35; the serving officer's endorsed return goes back to the claimant
- Notarization
- Not required for the service copy
Conn. Gen. Stat. §§ 49-34, 49-35
Connecticut Enforcing the Lien
Foreclosure Complaint and Notice of Lis Pendens
- Who uses it
- Lienholders
- When
- Within 1 year after recording, or within 60 days after final disposition of an application to discharge or reduce, whichever is later
- Served on or filed with
- Complaint filed in Superior Court; lis pendens recorded in the land records where the lien is recorded
- Notarization
- Not required
- A lien not foreclosed in time is extinguished automatically, and the unreleased record no longer affects title.
Conn. Gen. Stat. §§ 49-39, 49-40a, 52-325
Connecticut Releasing or Bonding Off a Lien
Release of Mechanic's Lien
- Who uses it
- Lienholders
- When
- On payment or settlement; no fixed statutory deadline
- Served on or filed with
- Recorded in the land records of the town where the lien is recorded
- Notarization
- Required (executed, attested and acknowledged like a deed)
- The statute supplies a substantially sufficient release form, not exclusive wording.
Conn. Gen. Stat. § 49-9
Application to Dissolve Lien by Substitution of Bond
- Who uses it
- Owners or other interested persons who intend in good faith to contest the lien
- When
- At any time; the certified order must be recorded within 10 days after the papers are returned to the court clerk
- Served on or filed with
- Filed in Superior Court with notice to the lienor; the certified order is recorded with the town clerk
- Notarization
- Not required
- The claimant must sue on the substitute bond within 1 year after the original certificate was recorded, not after the substitution.
Conn. Gen. Stat. § 49-37
Demand to Discharge Invalid Lien
- Who uses it
- Any person with an interest in the affected property
- When
- At any time; the lienor has 30 days after notice to release
- Served on or filed with
- The lienor at its last known address, by registered or certified mail, return receipt requested
- Notarization
- Not required for the demand
- A lienor that fails to release a lien filed without just cause may owe up to $100 per week after the 30 days, capped at $5,000, or actual loss including attorney's fees, whichever is greater.
Conn. Gen. Stat. § 49-51
Connecticut Owner Notices and Forms
Application to Discharge or Reduce Mechanic's Lien
- Who uses it
- Owners, before foreclosure is pending; parties to a foreclosure may move before trial
- When
- At any time before foreclosure, with at least 4 days' notice of hearing; an appeal must be taken within 7 days
- Served on or filed with
- Filed in Superior Court with a proposed order and summons served on the lienor
- Notarization
- Not required
- The lienor must first show probable cause; the owner may then prove invalidity or excessiveness by clear and convincing evidence. A certified order takes effect when recorded.
Conn. Gen. Stat. §§ 49-35a, 49-35b, 49-35c
Original Contractor's Affidavit
- Who uses it
- Original contractors that want to receive notices of intent
- When
- Within 15 days after commencing work
- Served on or filed with
- Recorded with the town clerk
- Notarization
- Required (affidavit)
- It states the contractor's business name, business address and the property description. A defective affidavit does not defeat a claimant's lien rights.
Conn. Gen. Stat. § 49-35(a)
Owner's Notice of Intention to Make Advance Payment
- Who uses it
- Owners paying ahead of the contract schedule
- When
- At least 5 days before the advance payment
- Served on or filed with
- Each person known to have furnished services or materials
- Notarization
- Not required
- Without it, an advance payment does not count as a good-faith payment that reduces the fund available to lien claimants.
Conn. Gen. Stat. § 49-36(c)
Connecticut Public Works and Payment Bond Claims
Notice of Claim on Payment Bond
- Who uses it
- Unpaid subcontractors and suppliers on bonded public works over $100,000
- When
- Within 180 days after last furnishing; for retainage, within 180 days after the applicable retainage payment date; payment must first be 60 days overdue
- Served on or filed with
- The surety, with a copy to the prime contractor, by registered or certified mail to its business office or by civil process
- Notarization
- Not required
- The notice states the amount with substantial accuracy, the party that received the work, and a detailed project description. The surety must respond within 90 days, but its silence is treated as a denial, not an admission.
Conn. Gen. Stat. § 49-42
Suit on Payment Bond
- Who uses it
- Claimants who served the notice of claim
- When
- Within 1 year after last furnishing; a retainage-only suit runs 1 year after retainage was due
- Served on or filed with
- Filed in Superior Court for the judicial district where the contract was performed
- Notarization
- Not required
Conn. Gen. Stat. § 49-42
Frequently Asked Questions
Is there a statutory mechanic's lien form in Connecticut?
Connecticut prescribes the contents of the certificate of mechanic's lien but no exclusive template (Conn. Gen. Stat. § 49-34). It does supply a substantially sufficient form for releasing a recorded lien (§ 49-9) and a form for the owner's application to discharge or reduce (§ 49-35a).
Does a Connecticut mechanic's lien have to be notarized?
Yes. The certificate must be subscribed and sworn to by the claimant (Conn. Gen. Stat. § 49-34). The jurat must show that an oath was administered; a mere acknowledgment does not satisfy the statute.
Where do I file a mechanic's lien in Connecticut?
The certificate is lodged with the town clerk of the town where the property is located, within 90 days after ceasing work (Conn. Gen. Stat. § 49-34). A true and attested copy must then be served on the owner within 30 days (§ 49-35).
Who must send a notice of intent in Connecticut?
Every claimant other than an original contractor, on residential and commercial work alike, unless its written subcontract carries the owner's written assent. It goes to each owner and to each original contractor that recorded the statutory affidavit, no later than 90 days after ceasing work (Conn. Gen. Stat. § 49-35).
What form releases a mechanic's lien in Connecticut?
Conn. Gen. Stat. § 49-9 supplies a release form, executed, attested and acknowledged like a deed and recorded in the land records. An owner may also substitute a bond (§ 49-37) or apply to discharge or reduce the lien (§ 49-35a).
What form do I use for a Connecticut public project bond claim?
Connecticut prescribes no template. The claimant serves a notice of claim stating the amount, the party supplied and the project on the surety, with a copy to the prime contractor, within 180 days after last furnishing. Suit must follow within 1 year after last furnishing (Conn. Gen. Stat. § 49-42).
How long do I have to foreclose a Connecticut mechanic's lien?
Foreclosure must be commenced and a lis pendens recorded within 1 year after the certificate is recorded, or within 60 days after final disposition of an application to discharge or reduce, whichever is later (Conn. Gen. Stat. § 49-39).
Related Connecticut Resources
Connecticut Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Connecticut Notice Requirements
Who must give notice, when, and how.
Connecticut Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Connecticut Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Connecticut law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.