HomeDelawareMechanics Lien Forms
Delaware Mechanics Lien Forms

Delaware Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Delaware construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Delaware claimant needs, in order, a Statement of Claim filed with the Prothonotary of the Superior Court in the county where the structure sits, a writ of scire facias served on the defendant, and a lien judgment (25 Del. C. §§ 2711, 2712, 2714). No preliminary notice or notice of intent is required.

A contractor that contracted directly with the owner and furnished both labor and material files within 180 days after completion or another listed timing event (§ 2711(a)). Every other eligible claimant files within 120 days after its own last labor or delivery, or after final payment events described in § 2711(b).

The Statement of Claim must carry the claimant's affidavit that its facts are true and correct, along with the contract or a bill of particulars and the other contents listed in § 2712. A defendant that contests the lien files a sworn affidavit of defense (§ 2716).

On covered public works, there is no statutory bond claim notice. A claimant sues on the bond in the agency's name within 1 year after the contractor ceased work if the bond so provides, or otherwise within 3 years after last work (29 Del. C. § 6962(d)(9)).

Delaware has no preliminary notice, notice of intent, notice of commencement, or owner's notice of completion. The lien process centers on one court filing: the Statement of Claim filed with the Prothonotary of the Superior Court, which may also serve as the complaint.

After filing, the court issues a writ of scire facias, the defendant answers with a sworn affidavit of defense, and a lien judgment is executed by writ of levari facias. Residential owners have a separate statutory payment certification and release procedure.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Delaware Lien Claim and Service

Statement of Claim

Statutory Form
Notarized
Required When It Applies
Who uses it
Contractors, subcontractors, suppliers and other eligible claimants
When
Within 180 days after completion or another listed event for a direct contractor furnishing labor and material; within 120 days after last labor or delivery, or after the listed final payment events, for all others
Served on or filed with
Filed with the Prothonotary of the Superior Court in the county where the structure is located
Notarization
Required (claimant's affidavit that the facts are true and correct)
  • The statute prescribes the contents, including the parties, amount due, contract or bill of particulars, dates, property description, and the amount due on each structure. It may be denominated a complaint.
  • A claim against two or more structures of the same owner must allocate the amount due on each.

25 Del. C. §§ 2711, 2712, 2713

Delaware Enforcing the Lien

Writ of Scire Facias Sur Mechanics' Lien

Statutory Form
Required When It Applies
Who uses it
Claimants; issued by the court and served by the sheriff
When
After the Statement of Claim is filed
Served on or filed with
The named defendant; a copy is also left with a resident of an occupied residential structure or affixed to the structure's door
Notarization
Not required
  • The Superior Court uses a prescribed writ form. The writ directs the defendant to respond within 20 days after service.

25 Del. C. §§ 2714, 2715

Affidavit Identifying Overlapping Personal and Lien Demands

Notarized
Required When It Applies
Who uses it
Claimants pursuing both a personal action and a lien action for the same debt
When
In whichever action is docketed last
Served on or filed with
Filed in the later-docketed action
Notarization
Required (affidavit)

25 Del. C. § 2725

Writ of Levari Facias

Statutory Form
Required When It Applies
Who uses it
Claimants holding a lien judgment
When
After judgment
Served on or filed with
Issued to the sheriff of the county where the property is located
Notarization
Not required
  • The statute supplies the writ form, which identifies the property, debt, interest and costs.

25 Del. C. § 2719

Delaware Releasing or Bonding Off a Lien

Petition to Discharge Lien on Payment into Court or Entry of Security

Notarized
Optional
Who uses it
Owners and other parties in interest
When
After the Statement of Claim is filed
Served on or filed with
Filed in the pending Superior Court proceeding, with the cash deposit or security
Notarization
Required (supporting affidavit separating disputed and undisputed amounts)
  • The undisputed portion is paid before discharge, and approved security may not be less than the required cash deposit.

25 Del. C. § 2729

Written Release, Subordination or Satisfaction of Filed Lien

Optional
Who uses it
Lien claimants and interested parties
When
After the Statement of Claim has been filed
Served on or filed with
Delivered to the party it benefits; docket relief is handled in the pending case
Notarization
Not required by the statute

25 Del. C. § 2706(b)

Delaware Owner Notices and Forms

Affidavit of Defense

Notarized
Required When It Applies
Who uses it
Owners and other defendants in the lien action
When
By the time to answer; the writ states 20 days after service
Served on or filed with
Filed in the lien action and served on the claimant
Notarization
Required (sworn affidavit)
  • The affidavit states the belief in a legal defense and its nature and character, and, for a partial defense, the sum admitted due. Without it the claimant may seek default judgment.
  • A defendant may also file exceptions to the Statement of Claim within 20 days after service.

25 Del. C. § 2716; Del. Super. Ct. Civ. R. 12

Owner's Demand for List of Persons Furnishing Labor and Material

Optional
Who uses it
Owners; the contractor or subcontractor must respond with a complete written list
When
At any time; consequences follow if the list is not furnished within 10 days after demand
Served on or filed with
The contractor or subcontractor
Notarization
Not required

25 Del. C. § 2705

Residential Contractor's Certification of Payment or Release of Liens

Notarized
Required When It Applies
Who uses it
Contractors paid by an owner who uses the property solely as the owner's residence
When
Before or at the time of full or final payment
Served on or filed with
The residential owner
Notarization
Required (the contractor's certification must be notarized and verified)
  • The contractor either certifies that all labor and materials are paid in full, or delivers a release signed by every eligible claimant with a certification that the signers are complete.
  • An owner who pays in full in good faith holds the property clear of liens in the stated circumstances.

25 Del. C. § 2707

Delaware Public Works and Payment Bond Claims

Suit on Public Works Bond

Required When It Applies
Who uses it
Unpaid firms furnishing labor or material on covered large public works contracts
When
Within 1 year after the contractor ceased work if the bond so provides; otherwise within 3 years after last work on the contract
Served on or filed with
Filed in a court of competent jurisdiction in the name of the contracting agency for the claimant's use
Notarization
Not required
  • The statute imposes no notice of claim, service method or 90-day deadline. Review the bond for its own claim terms, which cannot impose limits the statute does not authorize.

29 Del. C. § 6962(d)(9)

Frequently Asked Questions

Is there a statutory mechanics lien form in Delaware?

Delaware prescribes the contents of the Statement of Claim rather than a single template (25 Del. C. § 2712). The statute does supply the forms of the writs of scire facias and levari facias used in enforcement (§§ 2714, 2719).

Does a Delaware mechanics lien have to be notarized?

Yes. The Statement of Claim must include the claimant's affidavit that the facts stated are true and correct (25 Del. C. § 2712). A defendant's affidavit of defense must also be sworn (§ 2716).

Where do I file a mechanics lien in Delaware?

The Statement of Claim is filed with the Prothonotary of the Superior Court in the county where the structure is located (25 Del. C. § 2711). Direct contractors furnishing labor and material have 180 days after completion or another listed event; all other claimants have 120 days under § 2711(b).

Does Delaware require a preliminary notice or notice of intent to lien?

No. Chapter 27 contains no preliminary notice, notice of furnishing, notice of intent to lien, notice of commencement, or owner's notice of completion. Contract terms may still require notices.

What form releases a mechanics lien in Delaware?

After a claim is filed, the claimant may sign a written agreement releasing, subordinating or satisfying the lien (25 Del. C. § 2706(b)). An owner who disputes the claim may petition to discharge it on payment into court or entry of security under § 2729.

What form do I use for a Delaware public project bond claim?

Delaware's public works statute requires no notice of claim. The claimant sues on the bond in the contracting agency's name for its own use, within 1 year after the contractor ceased work if the bond so provides, or otherwise within 3 years after last work (29 Del. C. § 6962(d)(9)).

How do residential owners protect themselves from Delaware liens?

Before or at final payment, the contractor must give an owner who occupies the home either a notarized certification that all labor and materials are paid, or a release signed by every eligible claimant with a notarized certification (25 Del. C. § 2707).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us