Florida provides optional statutory lien waiver forms
Florida prescribes progress and final lien waiver forms that no one may require a lienor to depart from, but a different waiver voluntarily signed is enforceable according to its terms (Fla. Stat. § 713.20(4)-(8)).
Quick Answer
Florida does not require every waiver to use a statutory form, but it prescribes progress and final waiver forms and forbids anyone from requiring a lienor to sign a different one (Fla. Stat. § 713.20(4)-(6)). A materially different waiver that a lienor voluntarily signs is enforceable according to its terms.
A waiver of the right to claim a lien made in advance of furnishing is unenforceable in Florida. A lienor may waive lien rights only for labor, services, or materials already furnished, and may release those accrued rights by amount, through a stated date, or as to a parcel (§ 713.20(2)-(3)).
Neither statutory lien waiver requires notarization, and neither is recorded. A recorded satisfaction or release of a lien that has already been recorded is a different document: it must identify the original lien, be acknowledged before a notary, and be recorded with the clerk (§ 713.21(2)).
A lienor that receives a check may condition its waiver on payment of the check (§ 713.20(7)). Without that express condition, the waiver is effective according to its terms whether or not funds have cleared.
Florida sets out two statutory lien waiver forms in section 713.20: a Waiver and Release of Lien Upon Progress Payment and a Waiver and Release of Lien Upon Final Payment. No person may require a lienor to furnish a waiver that differs from the statutory form.
The statute does not create four separate conditional and unconditional forms. Instead, a lienor that receives a check may expressly condition its waiver on payment of that check. For public projects, section 255.05 prescribes parallel waivers of the right to claim against the payment bond.
Florida Lien Waiver Types
Waiver and Release of Lien Upon Progress Payment
- When to use it
- Exchanged for a progress payment. It releases lien rights for work furnished through the date stated in the form, and excludes retainage and later work.
- When it takes effect
- Effective according to its terms upon delivery; if expressly conditioned on payment of a check, effective when the check is paid.
Waiver and Release of Lien Upon Final Payment
- When to use it
- Exchanged for final payment. It releases all lien rights for the labor, services, or materials furnished to the property.
- When it takes effect
- Effective according to its terms upon delivery; if expressly conditioned on payment of a check, effective when the check is paid.
Waiver of Right to Claim Against the Payment Bond (Progress Payment)
- When to use it
- Used on public projects bonded under section 255.05 in exchange for a progress payment. It excludes retainage and later furnishing.
- When it takes effect
- Effective according to its terms; it may be conditioned on payment of a check.
Waiver of Right to Claim Against the Payment Bond (Final Payment)
- When to use it
- Used on public projects bonded under section 255.05 in exchange for final payment.
- When it takes effect
- Effective according to its terms; it may be conditioned on payment of a check.
Notarization
The statutory progress and final waivers under section 713.20, and the public bond waivers under section 255.05, do not require notarization.
A satisfaction or release of a lien that has already been recorded must be acknowledged before a notary and recorded (Fla. Stat. § 713.21(2)). A document that does both must meet the recording requirements.
Advance waivers are unenforceable
A waiver of the right to claim a lien made in advance of furnishing is unenforceable (Fla. Stat. § 713.20(2)). A lienor may release rights only for labor, services, or materials already furnished, by amount, through a date, or as to a parcel.
A release of accrued rights given in exchange for payment is not an unlawful advance waiver merely because the payment has not yet cleared. The Florida Supreme Court rejected an advance waiver of public payment bond rights in American Casualty Co. v. Coastal Caisson Drill Co., 542 So. 2d 957 (Fla. 1989).
Conditioning a waiver on a check
A lienor that receives a check may expressly condition its waiver on payment of that check (Fla. Stat. § 713.20(7)). The statute does not make every waiver conditional automatically.
Where no payment bond protects the owner, the owner may withhold the amount of an unpaid check from its payment to the contractor until the condition is satisfied.
Payment bond rights
A lien waiver under section 713.20 also waives the lienor's private payment bond rights under section 713.23 in a like amount (Fla. Stat. § 713.23(5)). A lienor cannot waive in advance its right to sue the surety on a private payment bond.
On public projects, section 255.05 prescribes separate progress and final waivers of the right to claim against the payment bond, and prohibits advance waivers of the right to proceed against the surety.
Read the through date and the release language
A progress waiver releases rights through the date stated in the form, not only the dollar amount printed. Check the through date, excluded retainage, and any pending change orders before signing.
Additional nonstatutory language can release more than lien rights. In Spectrum Interiors, Inc. v. Exterior Walls, Inc., 2 So. 3d 1093 (Fla. 5th DCA 2009), assignment language in a waiver barred recovery of earlier accrued claims.
Exchange Florida lien waivers with your customers and subcontractors, tracked against each payment.
Frequently Asked Questions
Does Florida have a statutory lien waiver form?
Yes. Section 713.20 of the Florida Statutes prescribes a Waiver and Release of Lien Upon Progress Payment and a Waiver and Release of Lien Upon Final Payment. No one may require a lienor to furnish a different form, although a different waiver voluntarily signed is enforceable according to its terms.
Does a Florida lien waiver have to be notarized?
No. The statutory waivers under § 713.20 do not require notarization. Only a satisfaction of a lien that has already been recorded must be acknowledged before a notary (§ 713.21(2)).
Are conditional lien waivers recognized in Florida?
Yes, in a specific way. A lienor that receives a check may expressly condition its statutory waiver on payment of that check (§ 713.20(7)). Florida does not prescribe separate conditional and unconditional forms.
Can a Florida contract waive lien rights in advance?
No. A waiver of the right to claim a lien made in advance is unenforceable (§ 713.20(2)). Lien rights may be waived only for labor, services, or materials already furnished.
Does a Florida lien waiver also waive payment bond rights?
Yes. A § 713.20 lien waiver also waives private payment bond rights under § 713.23 in a like amount (§ 713.23(5)). Public projects use separate statutory waivers of the right to claim against the payment bond under § 255.05.
Does a progress waiver release retainage in Florida?
No. The statutory progress payment waiver excludes retainage and labor, services, or materials furnished after the date stated in the waiver (§ 713.20(4)).
Related Florida Resources
Florida Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Florida Notice Requirements
Who must give notice, when, and how.
Florida Mechanics Lien Forms
Every notice, lien, release, and bond claim form.
Florida Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Florida law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.