Quick Answer
A Hawaii lien claimant files an Application for a Lien and a Notice of Lien in the circuit court where the property lies, no later than 45 days after the date of completion, and serves them on the owner, the general contractor, and other interested parties (HRS § 507-43(a)). The court holds a probable cause hearing.
The date of completion is a statutory event, not the claimant's last day on the job. It occurs when a notice of completion is published twice and the affidavit of publication is filed, or one year after actual completion or abandonment if no valid notice is published (§ 507-43(b), (f)).
If the court enters an Order Directing Lien to Attach, the claimant must sue to foreclose within three months after the order (§ 507-43(e)). On registered land, a certified copy of the order must be filed with the Land Court within seven days.
On public projects, every bond claimant must serve written notice on the contractor and the surety within 90 days after its last furnishing, stating the amount and the party supplied (HRS § 103D-324(d)). Suit may begin after that 90-day period and must be filed within one year.
Hawaii's mechanic's and materialman's lien law, HRS § 507-41 et seq., works differently from most states. A claimant does not record a lien with a county office. It files an Application for a Lien and a Notice of Lien in circuit court, and no lien attaches until the court finds probable cause and enters an order directing the lien to attach.
Hawaii has no general preliminary notice requirement on private projects. On public projects, unpaid claimants proceed against the contractor's payment bond under HRS § 103D-324, which requires written notice to the contractor and the surety within 90 days.
This page describes each document, who uses it, when it is due, and where it goes. Hawaii does not prescribe fill-in forms for most of these documents; the statute prescribes their content.
Hawaii Preliminary Notices
Homeowner Contract with Lien and Bonding Disclosures
- Who uses it
- Licensed contractors contracting with a homeowner
- When
- Oral explanation before contracting or at signing; written contract signed by both parties before work begins
- Served on or filed with
- The homeowner
- Notarization
- Not required
- The statute and administrative rules prescribe the content, including lien rights and bonding information.
- A homeowner cannot waive these protections, and noncompliance can defeat the contractor's lien.
HRS § 444-25.5; HAR §§ 16-77-79, 16-77-80
Hawaii Lien Claim and Service
Application for a Lien and Notice of Lien
- Who uses it
- Contractors, subcontractors, suppliers, and laborers that improved the property
- When
- No later than 45 days after the date of completion of the improvement
- Served on or filed with
- Filed in the circuit court where the property lies; served like a summons on the owner, persons with an interest, the contracting parties, and the general contractor
- Notarization
- Not expressly required by the lien statute
- The application must state the amount, the labor or materials furnished, a property description, the facts of the claim, and the parties.
- The notice sets a return hearing 3 to 10 days after service.
HRS § 507-43(a)-(b)
Order Directing Lien to Attach
- Who uses it
- Entered by the court on the claimant's application
- When
- After the probable cause hearing, if the court finds probable cause
- Served on or filed with
- Entered by the circuit court; on registered land, a certified copy is filed with the Assistant Registrar of the Land Court within 7 days after entry
- Notarization
- Not applicable (court order)
- No lien attaches until the order is entered.
HRS § 507-43(a)-(b)
Hawaii Enforcing the Lien
Demand for Payment
- Who uses it
- Lienors before enforcing the lien
- When
- Before the enforcement action; it may be included in the Application and Notice of Lien
- Served on or filed with
- The party owing the amount due
- Notarization
- Not required
HRS § 507-47
Complaint to Foreclose Mechanic's Lien
- Who uses it
- Lienors holding an Order Directing Lien to Attach
- When
- Within 3 months after entry of the Order Directing Lien to Attach
- Served on or filed with
- Filed in the circuit court where the property lies and served on the defendants
- Notarization
- Not required
- The lien cannot be extended. Failure to sue within three months extinguishes it.
HRS §§ 507-43(e), 507-47
Hawaii Releasing or Bonding Off a Lien
Cash or Bond to Discharge Lien
- Who uses it
- Owners, lessees, principal contractors, or intermediate subcontractors
- When
- Any time
- Served on or filed with
- Deposited or filed with the circuit court clerk, or with the Assistant Registrar where registered land is affected
- Notarization
- Not required
- The cash or bond must equal twice the amount of the lien claim.
HRS § 507-45
Written Notice of Satisfaction
- Who uses it
- Lienors whose lien or lien claim has been satisfied
- When
- Upon satisfaction of the lien or claim, other than expiration
- Served on or filed with
- Filed with the circuit court clerk, and with the Assistant Registrar for registered land
- Notarization
- Not required
- A contractual payment waiver does not necessarily satisfy this filing obligation.
HRS § 507-46
Hawaii Owner Notices and Forms
Written Demand to Publish Notice of Completion
- Who uses it
- General contractors that want the completion clock to start
- When
- Before the contractor publishes; the owner has 5 days to publish
- Served on or filed with
- The owner
- Notarization
- Not required
HRS § 507-43(f)
Notice of Completion or Abandonment
- Who uses it
- Owners, or general contractors after a written demand on the owner
- When
- After substantial completion or actual abandonment; published twice, seven days apart
- Served on or filed with
- Published in a newspaper of general circulation in the county; the newspaper files an affidavit of publication with the circuit court clerk
- Notarization
- Not required for the notice; the affidavit of publication is sworn
- If no valid notice is published, completion is deemed to occur one year after actual completion or abandonment.
HRS § 507-43(f)-(g)
Hawaii Public Works and Payment Bond Claims
Written Payment Bond Claim Notice
- Who uses it
- Every unpaid claimant on a bonded public project, including first-tier subcontractors and suppliers
- When
- Within 90 days after the claimant's last furnishing of labor or materials
- Served on or filed with
- The contractor and the surety, by registered or certified mail or any method allowed for service of a summons
- Notarization
- Not required
- The notice must state with substantial accuracy the amount claimed and the party supplied.
HRS § 103D-324(d); HAR § 3-122-227
Action on Payment Bond
- Who uses it
- Unpaid claimants that served the 90-day notice
- When
- After the 90-day period from last furnishing, and within 1 year
- Served on or filed with
- Filed in the circuit court where the project lies against the contractor and surety
- Notarization
- Not required
HRS § 103D-324(d)-(e)
Open Questions Under Hawaii Law
- Whether the one-year limit for suit on a Hawaii public payment bond runs from the claimant's own last furnishing or from the last labor or materials furnished by anyone under the bonded contract. The conservative practice is to sue within one year after the claimant's own last furnishing. This point is not settled under Hawaii law. National Lien & Bond confirms it with a local Hawaii attorney before relying on it.
Frequently Asked Questions
Is there a statutory mechanics lien form in Hawaii?
No fill-in form. HRS § 507-43 prescribes the content of the Application for a Lien and the Notice of Lien, which are filed together in circuit court. The application must state the amount, the labor or materials furnished, a property description, the facts of the claim, and the contracting parties.
Where do I file a mechanics lien in Hawaii?
In the circuit court for the circuit where the property is located. Hawaii liens are not recorded with a county office. The court holds a probable cause hearing and, if it finds probable cause, enters an Order Directing Lien to Attach (HRS § 507-43(a)).
Does a Hawaii lien application have to be notarized?
The lien statute does not expressly require verification or notarization of the Application for a Lien. Court rules and evidentiary requirements still apply, and the affidavit of publication for a notice of completion is a sworn document.
When does the 45-day lien deadline start in Hawaii?
It runs from the statutory date of completion: when a notice of completion is published twice and the affidavit of publication is filed, or one year after actual completion or abandonment if no valid notice is published (HRS § 507-43(b), (f)). It does not run from the claimant's last day of work.
What form releases a mechanics lien in Hawaii?
When a lien or lien claim is satisfied, a written notice of satisfaction must be filed with the circuit court clerk, and with the Land Court for registered land (HRS § 507-46). An owner or contractor may instead discharge the lien with cash or a bond equal to twice the claim (§ 507-45).
What form do I use for a Hawaii public project bond claim?
A written notice to the contractor and the surety, served within 90 days after your last furnishing, stating the amount claimed and the party supplied (HRS § 103D-324(d)). The notice applies to every claimant, including subcontractors in direct contract with the prime contractor.
Related Hawaii Resources
Hawaii Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Hawaii Notice Requirements
Who must give notice, when, and how.
Hawaii Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Hawaii Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Hawaii law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.