HomeHawaiiMechanics Lien Forms
Hawaii Mechanics Lien Forms

Hawaii Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Hawaii construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Hawaii lien claimant files an Application for a Lien and a Notice of Lien in the circuit court where the property lies, no later than 45 days after the date of completion, and serves them on the owner, the general contractor, and other interested parties (HRS § 507-43(a)). The court holds a probable cause hearing.

The date of completion is a statutory event, not the claimant's last day on the job. It occurs when a notice of completion is published twice and the affidavit of publication is filed, or one year after actual completion or abandonment if no valid notice is published (§ 507-43(b), (f)).

If the court enters an Order Directing Lien to Attach, the claimant must sue to foreclose within three months after the order (§ 507-43(e)). On registered land, a certified copy of the order must be filed with the Land Court within seven days.

On public projects, every bond claimant must serve written notice on the contractor and the surety within 90 days after its last furnishing, stating the amount and the party supplied (HRS § 103D-324(d)). Suit may begin after that 90-day period and must be filed within one year.

Hawaii's mechanic's and materialman's lien law, HRS § 507-41 et seq., works differently from most states. A claimant does not record a lien with a county office. It files an Application for a Lien and a Notice of Lien in circuit court, and no lien attaches until the court finds probable cause and enters an order directing the lien to attach.

Hawaii has no general preliminary notice requirement on private projects. On public projects, unpaid claimants proceed against the contractor's payment bond under HRS § 103D-324, which requires written notice to the contractor and the surety within 90 days.

This page describes each document, who uses it, when it is due, and where it goes. Hawaii does not prescribe fill-in forms for most of these documents; the statute prescribes their content.

Hawaii Preliminary Notices

Homeowner Contract with Lien and Bonding Disclosures

Required When It Applies
Who uses it
Licensed contractors contracting with a homeowner
When
Oral explanation before contracting or at signing; written contract signed by both parties before work begins
Served on or filed with
The homeowner
Notarization
Not required
  • The statute and administrative rules prescribe the content, including lien rights and bonding information.
  • A homeowner cannot waive these protections, and noncompliance can defeat the contractor's lien.

HRS § 444-25.5; HAR §§ 16-77-79, 16-77-80

Hawaii Lien Claim and Service

Application for a Lien and Notice of Lien

Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, and laborers that improved the property
When
No later than 45 days after the date of completion of the improvement
Served on or filed with
Filed in the circuit court where the property lies; served like a summons on the owner, persons with an interest, the contracting parties, and the general contractor
Notarization
Not expressly required by the lien statute
  • The application must state the amount, the labor or materials furnished, a property description, the facts of the claim, and the parties.
  • The notice sets a return hearing 3 to 10 days after service.

HRS § 507-43(a)-(b)

Order Directing Lien to Attach

Required When It Applies
Who uses it
Entered by the court on the claimant's application
When
After the probable cause hearing, if the court finds probable cause
Served on or filed with
Entered by the circuit court; on registered land, a certified copy is filed with the Assistant Registrar of the Land Court within 7 days after entry
Notarization
Not applicable (court order)
  • No lien attaches until the order is entered.

HRS § 507-43(a)-(b)

Hawaii Enforcing the Lien

Demand for Payment

Required When It Applies
Who uses it
Lienors before enforcing the lien
When
Before the enforcement action; it may be included in the Application and Notice of Lien
Served on or filed with
The party owing the amount due
Notarization
Not required

HRS § 507-47

Complaint to Foreclose Mechanic's Lien

Required When It Applies
Who uses it
Lienors holding an Order Directing Lien to Attach
When
Within 3 months after entry of the Order Directing Lien to Attach
Served on or filed with
Filed in the circuit court where the property lies and served on the defendants
Notarization
Not required
  • The lien cannot be extended. Failure to sue within three months extinguishes it.

HRS §§ 507-43(e), 507-47

Hawaii Releasing or Bonding Off a Lien

Cash or Bond to Discharge Lien

Optional
Who uses it
Owners, lessees, principal contractors, or intermediate subcontractors
When
Any time
Served on or filed with
Deposited or filed with the circuit court clerk, or with the Assistant Registrar where registered land is affected
Notarization
Not required
  • The cash or bond must equal twice the amount of the lien claim.

HRS § 507-45

Written Notice of Satisfaction

Required When It Applies
Who uses it
Lienors whose lien or lien claim has been satisfied
When
Upon satisfaction of the lien or claim, other than expiration
Served on or filed with
Filed with the circuit court clerk, and with the Assistant Registrar for registered land
Notarization
Not required
  • A contractual payment waiver does not necessarily satisfy this filing obligation.

HRS § 507-46

Hawaii Owner Notices and Forms

Written Demand to Publish Notice of Completion

Optional
Who uses it
General contractors that want the completion clock to start
When
Before the contractor publishes; the owner has 5 days to publish
Served on or filed with
The owner
Notarization
Not required

HRS § 507-43(f)

Notice of Completion or Abandonment

Optional
Who uses it
Owners, or general contractors after a written demand on the owner
When
After substantial completion or actual abandonment; published twice, seven days apart
Served on or filed with
Published in a newspaper of general circulation in the county; the newspaper files an affidavit of publication with the circuit court clerk
Notarization
Not required for the notice; the affidavit of publication is sworn
  • If no valid notice is published, completion is deemed to occur one year after actual completion or abandonment.

HRS § 507-43(f)-(g)

Hawaii Public Works and Payment Bond Claims

Written Payment Bond Claim Notice

Required When It Applies
Who uses it
Every unpaid claimant on a bonded public project, including first-tier subcontractors and suppliers
When
Within 90 days after the claimant's last furnishing of labor or materials
Served on or filed with
The contractor and the surety, by registered or certified mail or any method allowed for service of a summons
Notarization
Not required
  • The notice must state with substantial accuracy the amount claimed and the party supplied.

HRS § 103D-324(d); HAR § 3-122-227

Action on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants that served the 90-day notice
When
After the 90-day period from last furnishing, and within 1 year
Served on or filed with
Filed in the circuit court where the project lies against the contractor and surety
Notarization
Not required

HRS § 103D-324(d)-(e)

Open Questions Under Hawaii Law

  • Whether the one-year limit for suit on a Hawaii public payment bond runs from the claimant's own last furnishing or from the last labor or materials furnished by anyone under the bonded contract. The conservative practice is to sue within one year after the claimant's own last furnishing. This point is not settled under Hawaii law. National Lien & Bond confirms it with a local Hawaii attorney before relying on it.

Frequently Asked Questions

Is there a statutory mechanics lien form in Hawaii?

No fill-in form. HRS § 507-43 prescribes the content of the Application for a Lien and the Notice of Lien, which are filed together in circuit court. The application must state the amount, the labor or materials furnished, a property description, the facts of the claim, and the contracting parties.

Where do I file a mechanics lien in Hawaii?

In the circuit court for the circuit where the property is located. Hawaii liens are not recorded with a county office. The court holds a probable cause hearing and, if it finds probable cause, enters an Order Directing Lien to Attach (HRS § 507-43(a)).

Does a Hawaii lien application have to be notarized?

The lien statute does not expressly require verification or notarization of the Application for a Lien. Court rules and evidentiary requirements still apply, and the affidavit of publication for a notice of completion is a sworn document.

When does the 45-day lien deadline start in Hawaii?

It runs from the statutory date of completion: when a notice of completion is published twice and the affidavit of publication is filed, or one year after actual completion or abandonment if no valid notice is published (HRS § 507-43(b), (f)). It does not run from the claimant's last day of work.

What form releases a mechanics lien in Hawaii?

When a lien or lien claim is satisfied, a written notice of satisfaction must be filed with the circuit court clerk, and with the Land Court for registered land (HRS § 507-46). An owner or contractor may instead discharge the lien with cash or a bond equal to twice the claim (§ 507-45).

What form do I use for a Hawaii public project bond claim?

A written notice to the contractor and the surety, served within 90 days after your last furnishing, stating the amount claimed and the party supplied (HRS § 103D-324(d)). The notice applies to every claimant, including subcontractors in direct contract with the prime contractor.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us