Quick Answer
An Idaho lien claimant needs a verified Claim of Lien recorded with the county recorder within 90 days after completing its labor or furnishing materials, a copy served on the owner within five business days after recording, and a foreclosure suit within six months after recording (Idaho Code §§ 45-507, 45-510).
The owner copy must be personally delivered by an officer authorized to serve process or sent by certified mail to the owner's last known address (§ 45-507(5)). Ordinary mail is not the statutory method, and a deed of trust trustee is not an owner for this purpose.
On residential property of one to four units, a general contractor must give the homeowner the § 45-525 disclosure statement and obtain a signed acknowledgment before a contract over $2,000, and must list its subcontractors and suppliers before closing or final payment. Proof of disclosure belongs in the lien claim.
On public works, a claimant that contracted with a subcontractor but not the prime contractor must give the prime written notice by registered or certified mail within 90 days after last furnishing (§ 54-1927). Suit on the bond follows the 90-day period and is generally due within one year.
Idaho's mechanics lien statute, Idaho Code § 45-501 et seq., has no general preliminary notice. Lien rights depend on a verified Claim of Lien recorded within 90 days, a copy served on the owner within five business days, and suit within six months. On residential projects, the general contractor must also give the homeowner statutory disclosures.
Public property in Idaho is not subject to mechanics liens. On public works, unpaid claimants proceed against the payment bond under the Public Contracts Bond Act, Idaho Code § 54-1925 et seq.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
Idaho Preliminary Notices
Disclosure Statement and Acknowledgment of Receipt
- Who uses it
- General contractors on residential property of one to four units
- When
- Before entering a contract exceeding $2,000
- Served on or filed with
- The homeowner or purchaser, who signs an acknowledgment of receipt
- Notarization
- Not required
- The statute prescribes the content: the owner's rights to request lien waivers, insurance proof, title coverage, and a surety bond.
- Failure to give complete disclosures violates the Idaho Consumer Protection Act.
Idaho Code § 45-525(2), (5)
Subcontractor, Materialman, and Rental Equipment Disclosure
- Who uses it
- General contractors on residential property of one to four units
- When
- A reasonable time before closing or final payment
- Served on or filed with
- The homeowner or prospective purchaser
- Notarization
- Not required
- It lists every direct subcontractor, supplier, and equipment provider whose work or materials exceed $500.
Idaho Code § 45-525(3)
Idaho Lien Claim and Service
Claim of Lien
- Who uses it
- Contractors, subcontractors, suppliers, laborers, and equipment providers
- When
- Within 90 days after completion of the claimant's labor or services, or furnishing of materials
- Served on or filed with
- Recorded with the county recorder in a county where the property or part of it lies
- Notarization
- Required (verified under oath by the claimant, its agent, or its attorney)
- The claim states the amount due after credits, the owner, the hiring party, and a property description.
- On residential work, include proof of the required disclosure and receipt.
Idaho Code § 45-507(1)-(4)
Copy of Claim of Lien to Owner
- Who uses it
- Every lien claimant
- When
- No later than 5 business days after recording
- Served on or filed with
- The owner or reputed owner, by personal delivery by an officer authorized to serve process or by certified mail to the last known address
- Notarization
- Not required
Idaho Code § 45-507(5)-(6)
Idaho Enforcing the Lien
Complaint to Foreclose Lien
- Who uses it
- Lien claimants holding a recorded Claim of Lien
- When
- Within 6 months after recording; a payment or credit extension endorsed on the lien record restarts the period
- Served on or filed with
- Filed in district court and served on the defendants
- Notarization
- Not required
Idaho Code § 45-510
Notice of Pendency of Action (Lis Pendens)
- Who uses it
- Lien claimants after filing the foreclosure complaint
- When
- At or after filing the complaint
- Served on or filed with
- Recorded with the county recorder where the property lies
- Notarization
- Not required; general recording requirements apply
Idaho Code § 5-505
Idaho Releasing or Bonding Off a Lien
Release of Recorded Lien
- Who uses it
- Lien claimants whose recorded lien has been paid or settled
- When
- Upon payment or settlement; the lien statute sets no deadline
- Served on or filed with
- Recorded with the county recorder against the property
- Notarization
- Required for recording (acknowledged)
Idaho Code § 55-805
Surety Bond Releasing Property from Mechanic's Lien
- Who uses it
- Debtors or other interested parties, with a corporate surety
- When
- Obtained before the petition to release; the original is filed in court at the hearing
- Served on or filed with
- Filed with the district court in the county where the property lies
- Notarization
- Required (notarial acknowledgments for principal and surety)
- The bond must equal one and one-half times the lien claim.
Idaho Code § 45-519
Petition for Release of Lien and Order Releasing Lien
- Who uses it
- Debtors or interested parties that obtained a lien release bond
- When
- Hearing 5 to 10 days after the order setting it; the claimant is served at least 2 days before the hearing
- Served on or filed with
- Filed in district court; served on the lien claimant as a summons is served
- Notarization
- Not required
- The claimant may except to the surety's sufficiency within 2 days after service.
- Since July 1, 2024, recovery on the bond requires a valid and enforceable lien and is capped at the bond's penal sum.
Idaho Code §§ 45-520, 45-521, 45-524
Idaho Public Works and Payment Bond Claims
Written Notice of Payment Bond Claim
- Who uses it
- Claimants that contracted with a subcontractor but not with the prime contractor
- When
- Within 90 days after last furnishing labor or materials
- Served on or filed with
- The prime contractor, by registered or certified mail
- Notarization
- Not required
- The notice states with substantial accuracy the amount claimed and the party supplied. Claimants in direct contract with the prime need no notice.
Idaho Code § 54-1927
Complaint on Payment Bond
- Who uses it
- Unpaid claimants protected by the public payment bond
- When
- After 90 days from last furnishing; within 1 year after last furnishing, or for a subcontractor of the prime, 1 year after final payment under its subcontract became due
- Served on or filed with
- Filed in the court for the county where the contract was to be performed
- Notarization
- Not required
Idaho Code § 54-1927
Action Against Public Body for Failure to Obtain Payment Bond
- Who uses it
- Unpaid claimants where the public body did not obtain the required bond
- When
- After a demand for payment, and within 1 year after furnishing labor or materials
- Served on or filed with
- Filed in the court for the county where the contract was performed
- Notarization
- Not required
Idaho Code § 54-1928
Frequently Asked Questions
Is there a statutory mechanics lien form in Idaho?
Idaho prescribes the content of the Claim of Lien rather than a fill-in form. It must state the amount due after credits, the owner, the hiring party, and a property description, and on residential work it must include proof of the § 45-525 disclosure (Idaho Code § 45-507).
Does an Idaho mechanics lien have to be notarized?
Yes. The Claim of Lien must be verified by the oath of the claimant, its agent, or its attorney, stating that the affiant believes the claim is just (Idaho Code § 45-507(4)).
Where do I file a mechanics lien in Idaho?
Record the Claim of Lien with the county recorder in a county where the property is located within 90 days after completing your work. Then serve a copy on the owner within five business days, by an officer authorized to serve process or by certified mail (§ 45-507).
Does Idaho require a preliminary notice?
No. Idaho has no general preliminary notice or notice of intent to lien for private projects. On residential property, the general contractor must give the homeowner the § 45-525 disclosures, and on public works a second-tier claimant gives a 90-day notice to the prime contractor.
What form releases a mechanics lien in Idaho?
A paid lien is released by a recorded, acknowledged release. A disputed lien can be released by a surety bond of one and one-half times the claim, a district court petition, and a court order releasing the lien (Idaho Code §§ 45-519 to 45-521).
What form do I use for an Idaho public project bond claim?
A claimant without a direct contract with the prime contractor sends the prime written notice of its claim by registered or certified mail within 90 days after last furnishing (Idaho Code § 54-1927). Suit on the bond is generally due within one year.
Related Idaho Resources
Idaho Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Idaho Notice Requirements
Who must give notice, when, and how.
Idaho Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Idaho Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Idaho law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.