Quick Answer
A Kansas subcontractor or supplier generally needs a verified mechanic's lien statement filed with the clerk of the district court within three months after last furnishing, a copy served on the owner and other required parties, and a foreclosure suit within one year after filing (K.S.A. 60-1103, 60-1105). Direct contractors have four months (K.S.A. 60-1102).
On qualifying residential property, a subcontractor or supplier must mail the statutory warning statement to an owner, or hold the owner's signed acknowledgment, and attach a compliance affidavit to the lien statement (K.S.A. 60-1103a, 60-1103(a)(2)). Claims of $250 or less are exempt.
On new residential property sold to a good-faith purchaser, a claimant must file a notice of intent to perform before the deed is recorded to keep a lien after the transfer (K.S.A. 60-1103b). On nonresidential property, a notice of extension filed within the original period extends the deadline to five months total.
On public works, a claimant sues on the contractor's bond within six months after completion of the public improvement (K.S.A. 60-1111). On Kansas Department of Transportation contracts, a sworn itemized claim is due within six months and suit within one year after contract completion (K.S.A. 68-410).
Kansas mechanics lien law, K.S.A. 60-1101 et seq., requires a verified mechanic's lien statement filed with the clerk of the district court. Direct contractors have four months after last furnishing, and subcontractors and suppliers have three months; both may extend to five months total on qualifying nonresidential property.
Residential projects add two documents: the warning statement that subcontractors and suppliers give an owner, and the notice of intent to perform that protects claims on new residences sold to good-faith purchasers. Public property is not subject to liens; claimants sue on the contractor's statutory bond instead.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory or Judicial Council form text.
Kansas Preliminary Notices
Residential Warning Statement
- Who uses it
- Subcontractors and suppliers on qualifying residential property
- When
- No fixed deadline; the owner's receipt affects the owner's exposure for later payments, so give it early
- Served on or filed with
- Mailed to any one owner; alternatively, the claimant holds a statement signed and dated by an owner acknowledging the warning
- Notarization
- Not required
- The statute supplies the warning language, which must be substantially followed.
- Not required if the total claim does not exceed $250.
K.S.A. 60-1103a
Notice of Intent to Perform
- Who uses it
- Contractors, subcontractors, and suppliers on new one or two family residential structures
- When
- Before the deed transferring the property to a good-faith purchaser for value is recorded
- Served on or filed with
- Filed with the clerk of the district court in the county where the property lies
- Notarization
- Not required
- Substantial compliance with the Judicial Council form is sufficient.
- The notice expires after 18 months unless a lien is filed within that period.
K.S.A. 60-1103b
Kansas Lien Claim and Service
Mechanic's Lien Statement (Contractor)
- Who uses it
- Contractors in direct contract with the owner
- When
- Within 4 months after last furnishing; 5 months if properly extended
- Served on or filed with
- Filed with the clerk of the district court in the county where the property lies
- Notarization
- Required (verified)
- The statement gives the owner, the claimant and its address, a property description, and a reasonably itemized statement and amount.
K.S.A. 60-1102
Mechanic's Lien Statement (Subcontractor or Supplier)
- Who uses it
- Subcontractors and suppliers
- When
- Within 3 months after last furnishing; 5 months if properly extended
- Served on or filed with
- Filed with the clerk of the district court in the county where the property lies
- Notarization
- Required (verified), with a sworn warning statement affidavit on residential work
- It must also name the contractor and show compliance with any required notice of intent to perform.
K.S.A. 60-1103(a)
Copy of Lien Statement to Owner and Interested Parties
- Who uses it
- Subcontractors and suppliers
- When
- After filing; the statute sets no fixed number of days
- Served on or filed with
- Any one owner, any holder of a recorded equitable interest, and any party obligated to pay, by personal service or restricted mail; posting only if no address can be found
- Notarization
- Not required
- Proven actual receipt of the copy satisfies the requirement. Knowledge of the lien from a title report is not receipt.
K.S.A. 60-1103(c)
Kansas Enforcing the Lien
Notice of Extension
- Who uses it
- Contractors, subcontractors, and suppliers on nonresidential property
- When
- Filed within the original 4 month (contractor) or 3 month (subcontractor) period
- Served on or filed with
- Filed with the clerk of the district court; contractors mail it to the owner, and subcontractors to the general contractor or construction manager, by certified and regular mail, with a copy to the owner
- Notarization
- Not required
- The extension runs to five months total, not five additional months.
K.S.A. 60-1102(c), 60-1103(e)
Petition to Foreclose Mechanic's Lien
- Who uses it
- Lien claimants
- When
- Within 1 year after the lien statement is filed; if a promissory note was attached, 1 year after the note matures
- Served on or filed with
- Filed in the district court; a subcontractor's action must include the original contractor
- Notarization
- Not required
K.S.A. 60-1105, 60-1106
Kansas Releasing or Bonding Off a Lien
Release of Notice of Intent to Perform and Waiver of Lien
- Who uses it
- Claimants that filed a notice of intent to perform
- When
- When paid in full or otherwise discharged; the owner may demand it
- Served on or filed with
- Filed in the same office as the notice of intent to perform
- Notarization
- Not expressly required
- Filing extinguishes the claimant's lien right for that property.
K.S.A. 60-1103b(c)-(e)
Release of Mechanic's Lien
- Who uses it
- Lien claimants whose filed lien has been paid or settled
- When
- Upon payment or settlement
- Served on or filed with
- Filed with the clerk of the district court where the lien was filed
- Notarization
- Not prescribed by statute; local court forms may include a jurat
K.S.A. 60-1101 et seq.
Bond to Secure Payment of Claims
- Who uses it
- Owners or contractors
- When
- Before or after liens are filed
- Served on or filed with
- Approved by a district judge and filed with the clerk of the district court
- Notarization
- Not required
- A general bond must be at least the contract price; a bond for a disputed claim equals the claim amount. Approval and filing prevent or discharge covered liens.
K.S.A. 60-1110
Kansas Owner Notices and Forms
Landowner's Petition for Adjudication of Liens
- Who uses it
- Owners, when liens are filed and no foreclosure has begun
- When
- Any time after liens are filed
- Served on or filed with
- Filed in the district court of the county where the property lies, naming the claimants
- Notarization
- Not required
- A lien not enforced within the one-year period is cancelled by law.
K.S.A. 60-1108
Kansas Public Works and Payment Bond Claims
Action on Public Works Bond
- Who uses it
- Unpaid subcontractors and suppliers protected by the statutory bond
- When
- Within 6 months after completion of the public improvement
- Served on or filed with
- Filed in court against the contractor and surety; no preliminary notice or claim filing is required
- Notarization
- Not required
- Suppliers to suppliers and suppliers to second-tier subcontractors are outside the statutory bond's protection unless the bond is broader.
K.S.A. 60-1111
Sworn Itemized Statement (KDOT Highway Bond)
- Who uses it
- Unpaid claimants on Secretary of Transportation contracts
- When
- Within 6 months after the contract completion date in the Secretary's records
- Served on or filed with
- Filed with the Secretary of Transportation
- Notarization
- Required (sworn and acknowledged before a notary or other officer)
- Suit on the highway bond is due within 1 year after contract completion.
K.S.A. 68-410
Frequently Asked Questions
Is there a statutory mechanics lien form in Kansas?
Kansas prescribes the content of the lien statement rather than a fill-in form: the owner, the claimant and its address, a property description, and a reasonably itemized statement and amount (K.S.A. 60-1102). Kansas Judicial Council forms exist for the notice of intent to perform and the notice of extension.
Does a Kansas mechanics lien have to be notarized?
The lien statement must be verified (K.S.A. 60-1102, 60-1103). On residential work, a subcontractor's statement must also attach an affidavit that the warning statement was given (K.S.A. 60-1103(a)(2)).
Where do I file a mechanics lien in Kansas?
With the clerk of the district court in the county where the property is located, not the register of deeds. Direct contractors file within four months after last furnishing; subcontractors and suppliers within three months (K.S.A. 60-1102, 60-1103).
What is the Kansas residential warning statement?
A statutory notice that a subcontractor or supplier mails to an owner of qualifying residential property, warning that it may lien the property. Instead, the claimant may hold the owner's signed acknowledgment. Claims of $250 or less are exempt (K.S.A. 60-1103a).
What form releases a mechanics lien in Kansas?
A paid claimant files a release with the clerk of the district court. A claimant that filed a notice of intent to perform must file the statutory release of that notice when paid (K.S.A. 60-1103b(d)). An owner or contractor may also discharge liens with a court-approved bond (K.S.A. 60-1110).
What form do I use for a Kansas public project bond claim?
For most public works, no claim form: sue on the bond within six months after completion of the improvement (K.S.A. 60-1111). For KDOT contracts, file a sworn itemized statement with the Secretary within six months and sue within one year (K.S.A. 68-410).
Related Kansas Resources
Kansas Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Kansas Notice Requirements
Who must give notice, when, and how.
Kansas Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Kansas Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Kansas law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.