Kansas Mechanics Lien Forms

Kansas Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Kansas construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Kansas subcontractor or supplier generally needs a verified mechanic's lien statement filed with the clerk of the district court within three months after last furnishing, a copy served on the owner and other required parties, and a foreclosure suit within one year after filing (K.S.A. 60-1103, 60-1105). Direct contractors have four months (K.S.A. 60-1102).

On qualifying residential property, a subcontractor or supplier must mail the statutory warning statement to an owner, or hold the owner's signed acknowledgment, and attach a compliance affidavit to the lien statement (K.S.A. 60-1103a, 60-1103(a)(2)). Claims of $250 or less are exempt.

On new residential property sold to a good-faith purchaser, a claimant must file a notice of intent to perform before the deed is recorded to keep a lien after the transfer (K.S.A. 60-1103b). On nonresidential property, a notice of extension filed within the original period extends the deadline to five months total.

On public works, a claimant sues on the contractor's bond within six months after completion of the public improvement (K.S.A. 60-1111). On Kansas Department of Transportation contracts, a sworn itemized claim is due within six months and suit within one year after contract completion (K.S.A. 68-410).

Kansas mechanics lien law, K.S.A. 60-1101 et seq., requires a verified mechanic's lien statement filed with the clerk of the district court. Direct contractors have four months after last furnishing, and subcontractors and suppliers have three months; both may extend to five months total on qualifying nonresidential property.

Residential projects add two documents: the warning statement that subcontractors and suppliers give an owner, and the notice of intent to perform that protects claims on new residences sold to good-faith purchasers. Public property is not subject to liens; claimants sue on the contractor's statutory bond instead.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory or Judicial Council form text.

Kansas Preliminary Notices

Residential Warning Statement

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers on qualifying residential property
When
No fixed deadline; the owner's receipt affects the owner's exposure for later payments, so give it early
Served on or filed with
Mailed to any one owner; alternatively, the claimant holds a statement signed and dated by an owner acknowledging the warning
Notarization
Not required
  • The statute supplies the warning language, which must be substantially followed.
  • Not required if the total claim does not exceed $250.

K.S.A. 60-1103a

Notice of Intent to Perform

Statutory Form
Required When It Applies
Who uses it
Contractors, subcontractors, and suppliers on new one or two family residential structures
When
Before the deed transferring the property to a good-faith purchaser for value is recorded
Served on or filed with
Filed with the clerk of the district court in the county where the property lies
Notarization
Not required
  • Substantial compliance with the Judicial Council form is sufficient.
  • The notice expires after 18 months unless a lien is filed within that period.

K.S.A. 60-1103b

Kansas Lien Claim and Service

Mechanic's Lien Statement (Contractor)

Notarized
Required When It Applies
Who uses it
Contractors in direct contract with the owner
When
Within 4 months after last furnishing; 5 months if properly extended
Served on or filed with
Filed with the clerk of the district court in the county where the property lies
Notarization
Required (verified)
  • The statement gives the owner, the claimant and its address, a property description, and a reasonably itemized statement and amount.

K.S.A. 60-1102

Mechanic's Lien Statement (Subcontractor or Supplier)

Notarized
Required When It Applies
Who uses it
Subcontractors and suppliers
When
Within 3 months after last furnishing; 5 months if properly extended
Served on or filed with
Filed with the clerk of the district court in the county where the property lies
Notarization
Required (verified), with a sworn warning statement affidavit on residential work
  • It must also name the contractor and show compliance with any required notice of intent to perform.

K.S.A. 60-1103(a)

Copy of Lien Statement to Owner and Interested Parties

Required When It Applies
Who uses it
Subcontractors and suppliers
When
After filing; the statute sets no fixed number of days
Served on or filed with
Any one owner, any holder of a recorded equitable interest, and any party obligated to pay, by personal service or restricted mail; posting only if no address can be found
Notarization
Not required
  • Proven actual receipt of the copy satisfies the requirement. Knowledge of the lien from a title report is not receipt.

K.S.A. 60-1103(c)

Kansas Enforcing the Lien

Notice of Extension

Statutory Form
Optional
Who uses it
Contractors, subcontractors, and suppliers on nonresidential property
When
Filed within the original 4 month (contractor) or 3 month (subcontractor) period
Served on or filed with
Filed with the clerk of the district court; contractors mail it to the owner, and subcontractors to the general contractor or construction manager, by certified and regular mail, with a copy to the owner
Notarization
Not required
  • The extension runs to five months total, not five additional months.

K.S.A. 60-1102(c), 60-1103(e)

Petition to Foreclose Mechanic's Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 1 year after the lien statement is filed; if a promissory note was attached, 1 year after the note matures
Served on or filed with
Filed in the district court; a subcontractor's action must include the original contractor
Notarization
Not required

K.S.A. 60-1105, 60-1106

Kansas Releasing or Bonding Off a Lien

Release of Notice of Intent to Perform and Waiver of Lien

Statutory Form
Required When It Applies
Who uses it
Claimants that filed a notice of intent to perform
When
When paid in full or otherwise discharged; the owner may demand it
Served on or filed with
Filed in the same office as the notice of intent to perform
Notarization
Not expressly required
  • Filing extinguishes the claimant's lien right for that property.

K.S.A. 60-1103b(c)-(e)

Release of Mechanic's Lien

Required When It Applies
Who uses it
Lien claimants whose filed lien has been paid or settled
When
Upon payment or settlement
Served on or filed with
Filed with the clerk of the district court where the lien was filed
Notarization
Not prescribed by statute; local court forms may include a jurat

K.S.A. 60-1101 et seq.

Bond to Secure Payment of Claims

Optional
Who uses it
Owners or contractors
When
Before or after liens are filed
Served on or filed with
Approved by a district judge and filed with the clerk of the district court
Notarization
Not required
  • A general bond must be at least the contract price; a bond for a disputed claim equals the claim amount. Approval and filing prevent or discharge covered liens.

K.S.A. 60-1110

Kansas Owner Notices and Forms

Landowner's Petition for Adjudication of Liens

Optional
Who uses it
Owners, when liens are filed and no foreclosure has begun
When
Any time after liens are filed
Served on or filed with
Filed in the district court of the county where the property lies, naming the claimants
Notarization
Not required
  • A lien not enforced within the one-year period is cancelled by law.

K.S.A. 60-1108

Kansas Public Works and Payment Bond Claims

Action on Public Works Bond

Required When It Applies
Who uses it
Unpaid subcontractors and suppliers protected by the statutory bond
When
Within 6 months after completion of the public improvement
Served on or filed with
Filed in court against the contractor and surety; no preliminary notice or claim filing is required
Notarization
Not required
  • Suppliers to suppliers and suppliers to second-tier subcontractors are outside the statutory bond's protection unless the bond is broader.

K.S.A. 60-1111

Sworn Itemized Statement (KDOT Highway Bond)

Notarized
Required When It Applies
Who uses it
Unpaid claimants on Secretary of Transportation contracts
When
Within 6 months after the contract completion date in the Secretary's records
Served on or filed with
Filed with the Secretary of Transportation
Notarization
Required (sworn and acknowledged before a notary or other officer)
  • Suit on the highway bond is due within 1 year after contract completion.

K.S.A. 68-410

Frequently Asked Questions

Is there a statutory mechanics lien form in Kansas?

Kansas prescribes the content of the lien statement rather than a fill-in form: the owner, the claimant and its address, a property description, and a reasonably itemized statement and amount (K.S.A. 60-1102). Kansas Judicial Council forms exist for the notice of intent to perform and the notice of extension.

Does a Kansas mechanics lien have to be notarized?

The lien statement must be verified (K.S.A. 60-1102, 60-1103). On residential work, a subcontractor's statement must also attach an affidavit that the warning statement was given (K.S.A. 60-1103(a)(2)).

Where do I file a mechanics lien in Kansas?

With the clerk of the district court in the county where the property is located, not the register of deeds. Direct contractors file within four months after last furnishing; subcontractors and suppliers within three months (K.S.A. 60-1102, 60-1103).

What is the Kansas residential warning statement?

A statutory notice that a subcontractor or supplier mails to an owner of qualifying residential property, warning that it may lien the property. Instead, the claimant may hold the owner's signed acknowledgment. Claims of $250 or less are exempt (K.S.A. 60-1103a).

What form releases a mechanics lien in Kansas?

A paid claimant files a release with the clerk of the district court. A claimant that filed a notice of intent to perform must file the statutory release of that notice when paid (K.S.A. 60-1103b(d)). An owner or contractor may also discharge liens with a court-approved bond (K.S.A. 60-1110).

What form do I use for a Kansas public project bond claim?

For most public works, no claim form: sue on the bond within six months after completion of the improvement (K.S.A. 60-1111). For KDOT contracts, file a sworn itemized statement with the Secretary within six months and sue within one year (K.S.A. 68-410).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us