Kentucky Mechanics Lien Forms

Kentucky Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Kentucky construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Kentucky subcontractor or supplier generally needs three documents in order: a written notice of intention to hold the property liable, a sworn Statement of Lien filed with the county clerk within 6 months after last furnishing, and a suit to enforce filed within 12 months after the lien is filed (KRS 376.010, 376.080, 376.090).

The notice deadline depends on the claim. For claims less than $1,000, the notice is due within 75 days after last furnishing; for claims exceeding $1,000, within 120 days. On a protected owner-occupied single or two-family dwelling, the notice is due within 75 days regardless of amount (KRS 376.010(4), (5)).

Within 7 days after filing the Statement of Lien, the claimant must mail a copy by regular mail to the owner's last known address. Failure to mail the copy dissolves the lien (KRS 376.080(1)). Once the lien is satisfied, the lienholder must record a release within 30 days (KRS 382.365).

On public improvements, the claimant files a sworn lien on funds due the contractor by the later of 60 days after the month of last furnishing or substantial completion, delivers copies to the authority and contractor, and sues within 6 months, or 30 days after a protest notice (KRS 376.230 to 376.260).

Kentucky mechanics lien law (KRS Chapter 376) uses a short sequence of documents. A claimant without a direct contract with the owner gives written notice of its intention to hold the property liable, every claimant files a sworn Statement of Lien with the county clerk, and the claimant then sues to enforce within 12 months.

Kentucky does not publish a single official lien form. The statutes prescribe what each document must contain, and a document that omits a required element can dissolve the lien. Public improvements follow a separate track: the lien attaches to funds the public authority owes the contractor, not to the public property.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text or offer downloadable forms.

Kentucky Preliminary Notices

Notice of Intention to Hold Property Liable

Required When It Applies
Who uses it
Subcontractors, suppliers, and other claimants without a direct contract with the owner
When
Within 75 days after last furnishing for claims less than $1,000; within 120 days after last furnishing for claims exceeding $1,000
Served on or filed with
The owner, the owner's authorized agent, or the applicable lessee, at the last known address
Notarization
Not required
  • The statute prescribes content, not a template: the notice must state the intention to hold the property liable and the amount claimed.
  • A claim of exactly $1,000 falls between the statute's two categories. Use the 75-day deadline.
  • Serve the notice before filing the Statement of Lien.

KRS 376.010(4)

Notice to Owner of Owner-Occupied Dwelling

Required When It Applies
Who uses it
Claimants without a direct contract with the owner of a protected owner-occupied single or two-family dwelling
When
Within 75 days after last furnishing, regardless of the claim amount
Served on or filed with
The owner or the owner's authorized agent
Notarization
Not required
  • This notice replaces the general notice for protected dwellings.
  • The lien does not reach amounts the owner paid the contractor before receiving the notice.
  • The contractor or subcontractor cannot act as the owner's authorized agent for this notice.

KRS 376.010(5)

Advance Statement of Labor or Materials (Priority Filing)

Optional
Who uses it
Lien claimants who want priority over a later mortgage, contract lien, or conveyance
When
Before the competing mortgage, lien, or conveyance is recorded
Served on or filed with
Filed with the county clerk of the county where the labor or materials are or will be furnished
Notarization
Sworn, in the same manner as the Statement of Lien
  • This filing protects priority only. The claimant must still complete the notice, lien statement, and suit requirements.

KRS 376.010(2)

Kentucky Lien Claim and Service

Statement of Lien

Notarized
Required When It Applies
Who uses it
Every lien claimant, including prime contractors, subcontractors, and suppliers
When
Within 6 months after the claimant last furnished labor or materials
Served on or filed with
Filed with the county clerk of the county where the improvement is located
Notarization
Required. The statement must be subscribed and sworn to by the claimant or its representative
  • The statement must show the amount due after known credits and setoffs, a description sufficient to identify the property, the owner if known, the claimant's contractual tier, the claimant's name and address, and an agent or address for service.

KRS 376.080(1)

Mailed Copy of the Statement of Lien

Required When It Applies
Who uses it
Every lien claimant
When
Within 7 days after filing the Statement of Lien
Served on or filed with
The owner, by regular mail to the owner's last known address
Notarization
Not required
  • Failure to mail the copy within 7 days dissolves the lien.

KRS 376.080(1)

Postjudgment Mechanic's Lien

Optional
Who uses it
Contractors covered by the Kentucky Fairness in Construction Act
When
Within 60 days after a judgment against the contracting entity
Served on or filed with
Filed under the Chapter 376 filing procedure
Notarization
Sworn, as for the Statement of Lien
  • The Act excludes residential construction and certain other contracts, and this lien does not apply to public contracts.

KRS 371.420(2); KRS 371.425

Kentucky Enforcing the Lien

Action to Enforce Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 12 months after the Statement of Lien is filed
Served on or filed with
Filed in court as an equitable proceeding, joining the debtor and other persons holding liens or interests in the property
Notarization
Not required by the lien statute
  • If the debtor dies before the 12 months expire, the period extends to 6 months after a personal representative qualifies.
  • A lis pendens memorandum filed with the county clerk gives notice of the suit to later purchasers and lenders.

KRS 376.090; KRS 376.110; KRS 382.440

Kentucky Releasing or Bonding Off a Lien

Release of Satisfied Lien

Required When It Applies
Who uses it
The lienholder after the lien is paid in full
When
Recorded within 30 days after satisfaction; a copy mailed to the owner within 7 days after the release
Served on or filed with
Recorded with the same county clerk where the lien was filed; copy mailed to the owner's last known address
Notarization
No sworn affidavit is prescribed; follow the clerk's recording requirements
  • After written notice from the owner or an interested party, a lienholder that fails to release without good cause faces statutory daily damages, expenses, and attorney's fees.
  • Failure to mail the copy of the release carries a separate statutory penalty.

KRS 382.365

Bond to Release Property from Lien

Optional
Who uses it
The owner, the contractor, a subcontractor, or another person with an interest in the property
When
At any time before judgment enforcing the lien
Served on or filed with
Executed before the county clerk where the lien was filed
Notarization
Not required; the bond is executed before the clerk
  • The bond must be in double the amount of the lien, with good sureties approved by the clerk, conditioned on satisfying the claimant's judgment.
  • The claimant may join the bond obligors in the enforcement suit.

KRS 376.100

Kentucky Owner Notices and Forms

Contractor's Written Protest

Optional
Who uses it
The contractor whose funds are subject to a public improvement lien
When
Within 30 days after delivery of the attested copy
Served on or filed with
Filed with the public authority, which then notifies the claimant by certified mail
Notarization
Not required
  • A protest shortens the claimant's enforcement deadline to 30 days after the authority mails notice of the protest.

KRS 376.250(2), (3)

Kentucky Public Works and Payment Bond Claims

Statement of Lien on Funds Due Contractor (Public Improvement)

Notarized
Required When It Applies
Who uses it
Subcontractors, suppliers, and laborers on improvements to property of the state, a county, an urban county, a city, or their agencies
When
By the later of 60 days after the last day of the month of last furnishing, or substantial completion of the project
Served on or filed with
Filed with the county clerk of the county where the public owner's seat of government lies
Notarization
Required. Verified by affidavit of the claimant, its agent, or its attorney
  • The statement must state the amount due, the date of last furnishing, and the public improvement.
  • The lien attaches to funds due the contractor, not to the public property.
  • An optional prospective statement of expected furnishing may be filed in advance under KRS 376.210.

KRS 376.210; KRS 376.230

Perfection Package to Public Authority and Contractor

Required When It Applies
Who uses it
Public improvement lien claimants
When
After filing the public lien statement
Served on or filed with
A clerk-attested copy delivered to the public authority; an attested copy sent to the contractor or subcontractor by certified mail, return receipt requested, or registered mail, with the transmittal letter and postal receipt filed with the authority
Notarization
Not required
  • Filing with the county clerk alone does not attach the lien to the funds. Kentucky courts enforce these steps strictly.

KRS 376.240; 3D Enterprises Contracting Corp. v. Louisville & Jefferson County Metropolitan Sewer District, 174 S.W.3d 440 (Ky. 2005)

Suit to Enforce Public Improvement Lien

Required When It Applies
Who uses it
Public improvement lien claimants
When
Within 6 months after filing the lien statement; if the contractor protests, suit filed and summons served on the public authority within 30 days after the authority mails notice of the protest
Served on or filed with
Filed in the Circuit Court of the county where the project lies, with notice to the public owner
Notarization
Not required

KRS 376.250(4); KRS 376.260

Bond to Discharge Public Improvement Lien

Optional
Who uses it
The contractor or a person in privity with it
When
Before judgment enforcing the lien
Served on or filed with
Executed before the clerk where the lien was filed
Notarization
Not required
  • The bond must be in double the claim, secured by cash, a bank letter of credit, or surety insurance from a licensed insurer.

KRS 376.212

Payment Bond Claim on State Construction Contracts

Required When It Applies
Who uses it
Unpaid subcontractors, suppliers, and laborers protected by the contractor's payment bond
When
As stated in the executed bond; no statute sets a uniform notice or suit deadline
Served on or filed with
The recipients named in the executed bond, typically the surety and contractor
Notarization
As stated in the bond
  • Payment bonds are required on covered state construction contracts over $100,000. Obtain a certified copy of the bond from the purchasing agency before calendaring deadlines.

KRS 45A.190; KRS 45A.195; KRS 45A.435; 200 KAR 5:305

Open Questions Under Kentucky Law

  • Kentucky's payment bond statutes do not set a uniform notice period for second-tier claimants or a uniform suit deadline. The claim conditions in the currently incorporated state bond form and in each executed bond control. This point is not settled under Kentucky law. National Lien & Bond confirms it with a local Kentucky attorney before relying on it.
  • Whether every recorded lien release must be notarized depends on recording requirements that Kentucky's lien release statute does not itself address. This point is not settled under Kentucky law. National Lien & Bond confirms it with a local Kentucky attorney before relying on it.

Frequently Asked Questions

Is there a statutory mechanics lien form in Kentucky?

No. Kentucky does not publish an official mechanics lien form. KRS 376.080(1) prescribes the content of the Statement of Lien: the amount due after credits and setoffs, a property description, the owner if known, the claimant's tier, the claimant's name and address, and a service address. The statement must be subscribed and sworn.

Does a Kentucky mechanics lien have to be notarized?

The Statement of Lien must be subscribed and sworn to by the claimant or its representative, which requires an oath before an officer authorized to administer it (KRS 376.080(1)). A public improvement lien statement must be verified by affidavit (KRS 376.230). The notice of intention to hold the property liable does not require an oath.

Where do I file a mechanics lien in Kentucky?

File the Statement of Lien with the county clerk of the county where the improvement is located, within 6 months after last furnishing (KRS 376.080). A lien on public improvement funds is filed with the county clerk of the county where the public owner's seat of government lies (KRS 376.230).

What is the deadline for the Kentucky notice of intent to lien?

A claimant without a direct contract with the owner must give notice within 75 days after last furnishing for claims less than $1,000 and within 120 days for claims exceeding $1,000. On a protected owner-occupied single or two-family dwelling, the deadline is 75 days regardless of amount (KRS 376.010(4), (5)).

What form releases a mechanics lien in Kentucky?

Once paid, the lienholder records a release with the county clerk within 30 days after satisfaction and mails a copy to the owner within 7 days after the release (KRS 382.365). An owner may also release the property before judgment by a bond in double the lien amount executed before the clerk (KRS 376.100).

How long do I have to sue on a Kentucky mechanics lien?

Suit must be filed within 12 months after the Statement of Lien is filed (KRS 376.090). On public improvement liens, suit is due within 6 months after filing, or within 30 days after the public authority mails notice of a contractor protest (KRS 376.250).

What form do I use for a Kentucky public project bond claim?

Kentucky has no statutory bond claim form. Claimants on public improvements may file a lien on funds due the contractor under KRS 376.210 to 376.260. Separately, the payment bond required by KRS 45A.190 sets its own claim conditions, so obtain a certified copy of the executed bond from the agency (KRS 45A.195).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.