Quick Answer
A Louisiana subcontractor or supplier generally needs three documents in order: any required preservation notice, such as a seller's 75-day notice of nonpayment, a signed Statement of Claim or Privilege filed in the parish mortgage records, and a suit with a notice of pendency within 1 year after filing (La. R.S. 9:4804, 9:4822, 9:4823, 9:4833).
The filing deadline depends on the project. With a timely Notice of Contract, a subcontractor or supplier files within 30 days after a Notice of Termination, or 6 months after substantial completion if none is filed. Without one, the deadline is 60 days after the Notice of Termination, substantial completion, or abandonment.
When a statement is extinguished or improperly filed, the owner may demand cancellation, and the claimant must deliver a written cancellation request within 10 days after receiving the demand (La. R.S. 9:4833). An interested party may substitute a bond, cash, or certified funds to cancel the statement (La. R.S. 9:4835).
On public works, the claimant files a sworn statement of claim with the governing authority and records it in the parish mortgage records within 45 days after recordation of acceptance or a notice of default. Suit on the payment bond is due within 1 year from that recordation (La. R.S. 38:2242, 38:2247).
Louisiana calls mechanics liens privileges. On private works, the Private Works Act (La. R.S. 9:4801 et seq.) ties most filing deadlines to the owner's Notice of Termination of the work and to whether a Notice of Contract was timely recorded. On public works, the Public Works Act (La. R.S. 38:2241 et seq.) gives claimants a privilege on unexpended contract funds and a claim on the payment bond.
The Acts prescribe the contents of most documents, but few have fill-in forms. The residential Notice of Lien Rights has a statutory substantial form. The private Statement of Claim or Privilege must be signed but need not be sworn, while the public statement of claim must be sworn.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text or offer downloadable forms.
Louisiana Preliminary Notices
Notice of Lien Rights
- Who uses it
- Contractors on residential home improvement contracts for an owner-occupied, principally single-family dwelling
- When
- Before or when the contract is signed
- Served on or filed with
- The owner or the owner's authorized agent, for signature; copies to the owner and to any potential lien claimant on request
- Notarization
- Not required; signed by the owner or agent
- This is a mandatory, nonwaivable disclosure explaining lien exposure and owner protections. It is not a claimant's preservation notice.
La. R.S. 9:4851 to 9:4854
Professional Consultant or Subconsultant Notice
- Who uses it
- Architects, engineers, surveyors, and other professionals not engaged directly by the owner
- When
- Within 30 days after engagement
- Served on or filed with
- The owner
- Notarization
- Not required
- The notice states the claimant's and the engaging party's names and addresses and the general nature of the work.
La. R.S. 9:4804(A)
Notice of Lease of Movables
- Who uses it
- Lessors of equipment and other movables used on the site
- When
- Within 30 days after the equipment is first placed on the site; a later notice protects only rent accruing afterward
- Served on or filed with
- The contractor, and the owner if a Notice of Contract was timely filed
- Notarization
- Not required
- The notice states the lessor's and lessee's names and addresses and describes the equipment. A lessor must answer an owner's or contractor's request to identify leased equipment within 15 days.
La. R.S. 9:4804(B)
Seller's Notice of Nonpayment
- Who uses it
- Sellers of movables to a subcontractor, on projects with a timely Notice of Contract
- When
- No later than 75 days after the last day of the month in which the movables were delivered
- Served on or filed with
- Both the owner and the contractor
- Notarization
- Not required
- The notice identifies the seller and subcontractor, describes the movables, and states the unpaid balance. Missing it defeats the claim and privilege for that price.
- Since 2024, a separate notice under La. R.S. 9:4812(F), sent no sooner than 45 days after delivery, can trigger a special surety payment duty.
La. R.S. 9:4804(C); La. R.S. 9:4812(F)
Request for Notice of Termination
- Who uses it
- Subcontractors, suppliers, and lessors
- When
- Before the Notice of Termination is filed, or before substantial completion or abandonment if none is filed
- Served on or filed with
- The owner
- Notarization
- Not required
- The request must expressly ask for notice and give the claimant's mailing address. The owner must then notify the claimant within 10 days after the triggering event.
La. R.S. 9:4822(I), (J)
Louisiana Notices Before Filing a Lien
Residential Notice of Nonpayment
- Who uses it
- Eligible claimants on residential work where no Notice of Contract was timely filed
- When
- Before the ordinary 60-day filing period expires and at least 10 days before filing
- Served on or filed with
- The owner
- Notarization
- Not required
- The notice states the amount and nature of the obligation and extends the filing period from 60 to 70 days.
La. R.S. 9:4822(D)
Louisiana Lien Claim and Service
Statement of Claim or Privilege
- Who uses it
- Every claimant seeking a privilege, including general contractors, subcontractors, suppliers, and lessors
- When
- Subcontractors and suppliers with a timely Notice of Contract: 30 days after the Notice of Termination, or 6 months after substantial completion if none. General contractors: 60 days, or 7 months. Without a Notice of Contract: 60 days after the Notice of Termination, substantial completion, or abandonment
- Served on or filed with
- Filed in the mortgage records of the parish where the property is located
- Notarization
- Not required. The statement must be signed by the claimant or its representative
- The statement must reasonably identify the property, state the amount and nature of the obligation with a reasonable itemization, and identify the contracting party and the owner.
- When a Notice of Contract was timely filed and gives the owner's address, the claimant must also deliver a copy to the owner within the same period.
La. R.S. 9:4822(A) to (D), (H)
Louisiana Enforcing the Lien
Lower-Tier Pre-Suit Notice to Contractor
- Who uses it
- Lower-tier subcontractors enforcing a claim against the contractor or its surety
- When
- At least 30 days before filing suit
- Served on or filed with
- The contractor
- Notarization
- Not required
- The notice states substantially accurately the amount claimed and the subcontractor for whom the work was performed.
La. R.S. 9:4804(D)
Suit to Enforce and Notice of Pendency of Action
- Who uses it
- Claimants
- When
- Suit against the owner within 1 year after filing the statement, with a notice of pendency recorded within the same year; claims against the contractor or surety within 1 year after the filing period expires
- Served on or filed with
- Filed in the proper court; the notice of pendency is recorded in the parish mortgage records
- Notarization
- Not required by the Act
- Without a timely notice of pendency, the statement loses its effect against third persons.
La. R.S. 9:4813(E); La. R.S. 9:4823; La. R.S. 9:4833(E)
Louisiana Releasing or Bonding Off a Lien
Demand for Cancellation and Cancellation Request
- Who uses it
- The owner or an interested person makes the demand; the claimant delivers the cancellation request
- When
- The claimant must deliver a written cancellation request within 10 days after receiving a written demand when the statement is extinguished or improperly filed
- Served on or filed with
- Demand to the claimant; cancellation request to the recorder of mortgages
- Notarization
- Follow the recorder's cancellation requirements
- A claimant that unreasonably fails to deliver the request is liable for damages and attorney's fees, and the owner may obtain a judgment ordering cancellation.
La. R.S. 9:4833
Bond, Cash, or Certified Funds to Cancel Statement
- Who uses it
- The owner, contractor, or another interested party
- When
- After a statement of claim or notice of pendency is filed
- Served on or filed with
- Deposited with the recorder of mortgages, with notice to the owner, the privilege holder, and the contractor
- Notarization
- Not required
- The security covers the principal claim and up to 125% of principal. The bond is retained by the recorder, not recorded.
La. R.S. 9:4835
Louisiana Owner Notices and Forms
Notice of Contract and Contract Bond
- Who uses it
- The owner and the general contractor, both of whom sign
- When
- Recorded before the contractor begins work
- Served on or filed with
- Filed in the mortgage records of the parish where the property is located, with the bond attached
- Notarization
- Not required
- A general contractor whose contract exceeds $100,000 loses its privilege without a timely Notice of Contract.
- The attached bond gives the owner protection under La. R.S. 9:4802(C).
La. R.S. 9:4811; La. R.S. 9:4812
Notice of Termination of the Work
- Who uses it
- The owner or its authorized representative
- When
- After substantial completion, abandonment, contractor default, or termination of the contract; within 10 days after a qualifying request by the general contractor
- Served on or filed with
- Filed in the parish mortgage records
- Notarization
- Not required; the owner certifies the triggering event
- A Notice of Termination may cover a specified area of the work. If the owner fails to file after a request, the general contractor may obtain a recorded judgment that operates as the notice.
La. R.S. 9:4822(E) to (G)
Louisiana Public Works and Payment Bond Claims
Sworn Statement of Claim (Public Works)
- Who uses it
- Subcontractors, suppliers, laborers, and lessors on public works
- When
- After the amount is due and within 45 days after recordation of acceptance of the work or of a notice of default
- Served on or filed with
- Filed with the governing authority and recorded in the mortgage records of the parish where the work was done
- Notarization
- Required. The statement must be sworn
- The public claim is a privilege on unexpended contract funds, not a lien on the public property.
- A subcontractor in direct contract with the general contractor may sue the contractor and surety even without filing, if it sues before acceptance is recorded. Pierce Foundations, Inc. v. Jaroy Construction, Inc., 190 So. 3d 298 (La. 2016).
La. R.S. 38:2242(B)
Materialman's Notice of Nonpayment (Public Works)
- Who uses it
- Suppliers unpaid by a subcontractor on a public contract
- When
- Within 75 days after the last day of the month of delivery, or the statutory claim period, whichever comes first
- Served on or filed with
- The general contractor and the owner, by certified mail
- Notarization
- Not required
La. R.S. 38:2242(F)
Lower-Tier Notice to Contractor (Public Works)
- Who uses it
- Claimants that contract with a subcontractor but not with the general contractor
- When
- Within 45 days after recordation of acceptance or of the owner's notice of default
- Served on or filed with
- The contractor, by registered or certified mail to its Louisiana office; send copies to the surety and the owner as well
- Notarization
- Not required
- The notice states substantially accurately the amount claimed and the party supplied.
La. R.S. 38:2247(A), (E)
Suit on Public Payment Bond
- Who uses it
- Claimants protected by the payment bond
- When
- Within 1 year from the recordation of acceptance of the work or of the notice of default
- Served on or filed with
- Filed in the proper court against the contractor and surety
- Notarization
- Not required
- A matured claim may be sued on before acceptance is recorded. Payment bonds are generally required on public contracts over $25,000.
La. R.S. 38:2241; La. R.S. 38:2247(A)
Open Questions Under Louisiana Law
- La. R.S. 38:2247(E), added in 2024, refers to notices to the contractor, surety, and owner, while subsection (A) directs the lower-tier notice to the contractor. No appellate decision resolves whether every subsection (A) notice must now go to all three; send it to all three. This point is not settled under Louisiana law. National Lien & Bond confirms it with a local Louisiana attorney before relying on it.
- The execution formalities for cancellation requests and notices of pendency come from general recordation and procedure law and were not fully confirmed. This point is not settled under Louisiana law. National Lien & Bond confirms it with a local Louisiana attorney before relying on it.
Frequently Asked Questions
Is there a statutory mechanics lien form in Louisiana?
No fill-in form exists for the Statement of Claim or Privilege. La. R.S. 9:4822(H) prescribes its contents: a reasonable identification of the property, the amount and nature of the obligation with a reasonable itemization, the contracting party, and the owner. Only the residential Notice of Lien Rights has a statutory substantial form (La. R.S. 9:4852).
Does a Louisiana lien have to be notarized?
On private works, no. The Statement of Claim or Privilege must be signed by the claimant or its representative, but it need not be sworn or notarized (La. R.S. 9:4822(H)). On public works, the statement of claim must be sworn (La. R.S. 38:2242(B)).
Where do I file a lien in Louisiana?
File the Statement of Claim or Privilege in the mortgage records of the parish where the property is located (La. R.S. 9:4822). On public works, file the sworn statement with the governing authority and record it in the parish mortgage records (La. R.S. 38:2242).
What is the deadline to file a Louisiana Statement of Claim or Privilege?
With a timely Notice of Contract, a subcontractor or supplier files within 30 days after the Notice of Termination, or 6 months after substantial completion if none is filed. Without one, the deadline is 60 days, or 70 days on qualifying residential work after a timely notice of nonpayment (La. R.S. 9:4822).
What form releases a lien in Louisiana?
When a statement is extinguished or improperly filed, the claimant must deliver a written cancellation request to the recorder within 10 days after a written demand (La. R.S. 9:4833). An interested party may also cancel the statement by depositing a bond, cash, or certified funds (La. R.S. 9:4835).
How long do I have to sue on a Louisiana privilege?
Suit against the owner is due within 1 year after the statement is filed, and a notice of pendency must be recorded within that year (La. R.S. 9:4823, 9:4833(E)). Claims against the contractor or surety run 1 year after the filing period expires (La. R.S. 9:4813(E)).
What form do I use for a Louisiana public project bond claim?
File a sworn statement of claim with the governing authority and record it within 45 days after recordation of acceptance or a notice of default (La. R.S. 38:2242). A claimant without a contract with the general contractor also sends the contractor notice within the same 45 days, and suit is due within 1 year (La. R.S. 38:2247).
Related Louisiana Resources
Louisiana Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Louisiana Notice Requirements
Who must give notice, when, and how.
Louisiana Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Louisiana Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Louisiana law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.