HomeMaineMechanics Lien Forms
Maine Mechanics Lien Forms

Maine Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Maine construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Maine subcontractor or supplier generally needs three documents in order: a sworn lien statement recorded in the registry of deeds within 90 days after last furnishing, a copy mailed to the owner within the same 90 days, and a lien complaint filed in Superior or District Court within 120 days (10 M.R.S. §§ 3253, 3255).

A contractor with a direct contract with the owner is exempt from the 90-day recording and mailing requirement but must still file suit within 120 days. Any claimant may record a notice under § 3255(2) to protect the lien against a bona fide purchaser.

Within 60 days after filing the complaint, the claimant records the clerk's certificate, an affidavit, or an attested copy of the complaint in the registry of deeds (§ 3261). An owner may release the property by petitioning the court and filing an approved bond (§ 3263).

On public works bonded under 14 M.R.S. § 871, a claimant with a contract with a subcontractor, but not with the prime, sends written notice to the prime by registered or certified mail within 90 days after last furnishing. Suit follows after 90 days and within 1 year after last furnishing.

Maine mechanics lien law (10 M.R.S. §§ 3251 to 3269) has no mandatory preliminary notice. A claimant without a contract with the owner records a sworn lien statement and mails a copy to the owner within 90 days, and every claimant files a lien complaint within 120 days after last furnishing.

Maine does not publish official lien forms. The statutes prescribe the content of each document, and the Law Court requires an actual oath with an officer's jurat on the lien statement. Several optional notices protect the claimant against purchasers and against an owner paying the contractor in full.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text or offer downloadable forms.

Maine Preliminary Notices

Notice to Owner Preserving the Unpaid Balance

Statutory Form
Optional
Who uses it
Subcontractors and suppliers without a contract with the owner, on residential and other nonbusiness property
When
As early as possible, before the owner pays the contractor; no fixed deadline
Served on or filed with
The owner, or the owner's known local agent if the owner resides elsewhere
Notarization
Not required
  • The statute prescribes a double-payment warning at the top of the notice identifying the claimant and the contractor.
  • The lien is limited to the balance the owner owes the contractor when the notice is received. The limit generally does not apply to business, commercial, or industrial work unless the owner resides on the premises.

10 M.R.S. § 3255(3)

Notice Protecting Lien Against a Bona Fide Purchaser

Optional
Who uses it
Any lien claimant, particularly a contractor with a direct contract with the owner
When
Before a purchaser takes title; the notice operates for 120 days from recording and may be rerecorded
Served on or filed with
Recorded in the registry of deeds where the property is located
Notarization
Not required
  • The notice describes the property, names the owners, and states that the claimant is furnishing labor or materials and may claim a lien. A recorded § 3253 lien statement also satisfies this requirement.

10 M.R.S. § 3255(2)

Maine Lien Claim and Service

Mechanic's Lien Statement

Notarized
Required When It Applies
Who uses it
Subcontractors, suppliers, and other claimants without a contract with the owner
When
Within 90 days after the claimant last furnished labor, materials, or services
Served on or filed with
Recorded with the register of deeds for the county or registry district where the property is located
Notarization
Required. The statement must be subscribed and sworn with a proper jurat; an acknowledgment is not sufficient
  • The statement must show the amount due with all just credits, a property description sufficient to identify it, and the owners' names if known.
  • Contractors with a direct contract with the owner are exempt from this filing but should consider recording to protect against purchasers.

10 M.R.S. § 3253; Pineland Lumber Co. v. Robinson, 382 A.2d 33 (Me. 1978)

Mailed Copy of Lien Statement to Owner

Required When It Applies
Who uses it
Claimants who must record a lien statement
When
Within the same 90 days after last furnishing
Served on or filed with
The owner or owners, by ordinary mail
Notarization
Not required
  • A post office certificate of mailing is conclusive proof of receipt under the statute.

10 M.R.S. § 3253(1)(B)

Maine Enforcing the Lien

Complaint to Enforce Mechanic's Lien

Required When It Applies
Who uses it
Every lien claimant
When
Within 120 days after last furnishing labor, materials, or services
Served on or filed with
Filed with the Superior Court clerk in the proper county or the District Court clerk in the proper division, against the debtor, the owner, and other interested parties
Notarization
Not required
  • The complaint must identify the property and the work, allege the owner's contract or consent, and allege compliance with § 3253 where it applies.
  • A claimant without a contract with the owner may not serve the owner until 30 days after filing.
  • Attachment is not a required part of the complaint.

10 M.R.S. §§ 3255(1), 3257

Notice of Lien Complaint (Clerk's Certificate, Affidavit, or Attested Complaint)

Required When It Applies
Who uses it
Lien claimants who have filed a complaint
When
Within 60 days after filing the complaint, and before a purchaser takes title
Served on or filed with
Recorded in the registry of deeds where the property is located
Notarization
The affidavit option is sworn; the certificate and attested complaint are certified by the clerk
  • Failure to record does not invalidate the lien, but a bona fide purchaser who takes title before recording takes free of it.

10 M.R.S. § 3261

Enforcement by Attachment

Optional
Who uses it
Lien claimants choosing the attachment route
When
Attachment made within 180 days after last furnishing
Served on or filed with
Motion and supporting affidavits filed with the court; attachment perfected against the property and served on the defendant
Notarization
Supporting affidavits required
  • An attested attachment order may be recorded in the registry of deeds to perfect the attachment.

10 M.R.S. § 3262; M.R. Civ. P. 4A; 14 M.R.S. § 4154

Maine Releasing or Bonding Off a Lien

Petition for Release and Release Bond

Optional
Who uses it
The owner while a lien action is pending
When
At any time during the lien action; the lienor receives written notice at least 10 days before the hearing
Served on or filed with
Filed with the court where the lien action is pending; the bond runs to the lienor
Notarization
Not required
  • The court fixes the bond amount and approves the sureties.
  • The lien is vacated when attested copies of the proceedings and the clerk's sealed certificate of the bond are recorded in the registry of deeds.

10 M.R.S. § 3263

Voluntary Lien Release or Discharge

Required When It Applies
Who uses it
Lien claimants after payment or settlement
When
As agreed; no statutory deadline
Served on or filed with
Delivered to the owner; recorded in the registry of deeds when clearing a recorded lien
Notarization
No lien statute requires it; follow registry recording requirements
  • Distinguish a payment release, a lien discharge, and a subordination to a particular mortgage.

A. C. Paradis Co. v. H. W. Maxim Co., 91 A.2d 485 (Me. 1952)

Maine Owner Notices and Forms

Owner's Notice Preventing Lien

Optional
Who uses it
Owners
When
Before the affected labor, materials, or services are furnished; it operates only prospectively
Served on or filed with
The person furnishing without a contract with the owner
Notarization
Not required
  • The owner states in writing that it will not be responsible for the furnishing.

10 M.R.S. § 3252

Home Construction Contract and Attorney General Addendum

Required When It Applies
Who uses it
Contractors on home construction contracts exceeding $3,000
When
Signed by both parties and delivered before work begins
Served on or filed with
The homeowner
Notarization
Not required
  • The contract must include the statutory terms, the Attorney General consumer information addendum, and the conspicuous Attorney General contact notice. It is not a separate lien notice.

10 M.R.S. §§ 1487, 1489

Maine Public Works and Payment Bond Claims

Notice of Claim on Public Works Payment Bond

Required When It Applies
Who uses it
Claimants with a contract with a subcontractor but no contract with the bonded prime contractor
When
Within 90 days after the claimant last furnished labor or materials
Served on or filed with
The prime contractor, by registered or certified mail, at its place of business or residence
Notarization
Not required
  • The notice must state substantially accurately the amount claimed and the party supplied.
  • When the claim cannot be determined until the contracting body sets final quantity estimates, a material supplier's notice runs from that determination.

14 M.R.S. § 871(4)

Suit on Public Works Payment Bond

Required When It Applies
Who uses it
Unpaid subcontractors, suppliers, and laborers protected by the payment bond
When
After 90 days without payment and within 1 year after last furnishing
Served on or filed with
Filed in court in the Maine county where the public work is located
Notarization
Not required
  • Payment bonds are generally required on public contracts exceeding $125,000. A claimant may request certified copies of the bond and contract from the contracting body.

14 M.R.S. § 871(3), (4), (6)

Frequently Asked Questions

Is there a statutory mechanics lien form in Maine?

No. Maine does not publish an official lien form. 10 M.R.S. § 3253 prescribes the content of the lien statement: the amount due with all just credits, a description of the property, and the owners' names if known. The statement must be subscribed and sworn.

Does a Maine mechanics lien have to be notarized?

Yes. The lien statement must be sworn before an officer authorized to administer oaths, with a proper jurat. The Law Court held that an acknowledgment of execution is not sufficient. Pineland Lumber Co. v. Robinson, 382 A.2d 33 (Me. 1978).

Where do I file a mechanics lien in Maine?

Record the lien statement with the register of deeds for the county or registry district where the property is located within 90 days after last furnishing, and mail a copy to the owner within the same period (10 M.R.S. § 3253). The lien complaint is filed in Superior Court or District Court within 120 days (§ 3255).

Does Maine require a preliminary notice?

No preliminary notice is required to preserve a Maine lien. A written notice to the owner under 10 M.R.S. § 3255(3) is optional but important on residential and other nonbusiness property, because the lien is limited to the balance the owner owes the contractor when the notice is received.

What form releases a mechanics lien in Maine?

A paid claimant gives a written release or discharge, recorded in the registry of deeds if the lien was recorded. An owner may also petition the court for release and file an approved bond; recording the attested proceedings and the clerk's certificate vacates the lien (10 M.R.S. § 3263).

What form do I use for a Maine public project bond claim?

Maine has no statutory bond claim form. A claimant with a contract with a subcontractor, but not with the prime, sends written notice to the prime by registered or certified mail within 90 days after last furnishing, then sues after 90 days and within 1 year after last furnishing (14 M.R.S. § 871(4)).

Can I file a mechanics lien on a public project in Maine?

Liens cannot attach to state-owned property, where the payment bond under 14 M.R.S. § 871 is the remedy. Section 3251 expressly includes specified municipal public buildings, so a lien may be available on certain municipal projects.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.