Michigan requires statutory lien waiver forms
MCL 570.1115(9) requires lien waivers to be in substantially the statutory format for the four forms: partial and full, conditional and unconditional.
Quick Answer
Yes. Michigan requires statutory lien waiver forms. MCL 570.1115(9) requires waivers in substantially the statutory format for four forms: partial conditional, partial unconditional, full conditional, and full unconditional. The Act separately recognizes substantial compliance, but an unrestricted proprietary release is not a substitute.
The conditional forms are effective upon actual payment of the stated amount. Every waiver, conditional or not, becomes effective when a person pays in reliance on it unless that payer had written notice, at the time of payment, that the consideration failed (MCL 570.1115(6)).
The claimant must give a full unconditional waiver upon receipt of full contract payment, and a partial unconditional waiver for amounts received when the owner, lessee, or designee requests it. None of the four waivers requires notarization.
Advance waivers in an improvement contract are invalid except to the extent payment was actually made to the person giving the waiver (MCL 570.1115(1)). Taking a promissory note or other evidence of debt does not by itself waive or discharge lien rights.
Michigan is a mandatory statutory waiver state. The Construction Lien Act prescribes four waiver forms, and MCL 570.1115(9) requires waivers substantially in that format. A proprietary release labeled as a lien waiver is not a substitute.
Each statutory waiver releases construction lien rights against the described property. A waiver becomes effective when a person pays in reliance on it, unless the payer had written notice at the time of payment that the consideration failed.
Michigan Lien Waiver Types
Partial Conditional Waiver
- When to use it
- Exchanged for a proposed progress payment, waiving lien rights up to a stated amount for furnishing through a stated date.
- When it takes effect
- Effective upon actual payment of the stated amount, and also when a person pays in reliance on it without written notice that the consideration failed.
Partial Unconditional Waiver
- When to use it
- Given after a progress payment is received, when the owner, lessee, or designee requests it.
- When it takes effect
- Effective on delivery for the stated amount through the stated date, subject to the reliance rule.
Full Conditional Waiver
- When to use it
- Exchanged for final payment, releasing all construction lien rights against the described property.
- When it takes effect
- Effective upon actual payment of the stated consideration, and also when a person pays in reliance on it without written notice that the consideration failed.
Full Unconditional Waiver
- When to use it
- Given upon receipt of full contract payment; it represents that the contract has been fully paid.
- When it takes effect
- Effective on delivery and releases all construction lien rights against the described property, subject to the reliance rule.
Statutory format is mandatory
MCL 570.1115(9) requires waivers substantially in the statutory format. Exact typographic replication is not required, but a waiver that departs from the statutory content should not be relied on as a Michigan lien waiver.
No notarization
The four statutory waivers require the claimant's signature and identifying information, not a notary. Do not confuse them with the Claim of Lien and the sworn statement, which are sworn, or the certificate of discharge, which is witnessed and acknowledged (MCL 570.1111, 570.1110, 570.1127).
Advance waivers are invalid
An improvement contract may not require a waiver of lien rights in advance. Such a waiver is invalid except to the extent payment for the labor or materials was actually made to the person giving it (MCL 570.1115(1)).
A statutory conditional waiver exchanged for payment for work already furnished is not a prohibited advance waiver.
Conditional waivers and the reliance rule
A conditional waiver is conditioned on actual payment, but under MCL 570.1115(6) a waiver becomes effective when someone pays in reliance on it unless that payer had written notice, at the time of payment, that the consideration failed.
If a payment check is stopped or dishonored, give written notice of the failed consideration immediately to everyone who may rely on the waiver.
Residential structures
On a residential structure, the owner, lessee, or designee may not rely on a waiver supplied by someone other than the named claimant without first confirming its authenticity with the claimant (MCL 570.1115(7)). A forged waiver does not extinguish an innocent claimant's lien. Horton v. Verhelle, 231 Mich. App. 667 (1998).
Payment bond rights
The statutory waivers release construction lien rights against property; they do not themselves release payment bond or contract claims. The public works bond act prescribes no waiver forms and contains no advance-waiver prohibition like MCL 570.1115(1).
Exchange Michigan lien waivers with your customers and subcontractors, tracked against each payment.
Open Questions Under Michigan Law
- No controlling published Michigan appellate decision resolves whether a subcontract may waive public payment bond rights before performance. This point is not settled under Michigan law. National Lien & Bond confirms it with a local Michigan attorney before relying on it.
Frequently Asked Questions
Does Michigan require a statutory lien waiver form?
Yes. MCL 570.1115(9) requires waivers substantially in the statutory format. Michigan prescribes four forms: partial conditional, partial unconditional, full conditional, and full unconditional.
Does a Michigan lien waiver have to be notarized?
No. The four statutory waivers do not require notarization. The Claim of Lien and the sworn statement are the documents that must be sworn.
When does a Michigan conditional lien waiver take effect?
Upon actual payment of the stated amount. Under MCL 570.1115(6), it also becomes effective when a person pays in reliance on it unless that payer had written notice, at the time of payment, that the consideration failed.
Are advance lien waivers enforceable in Michigan?
No, except to the extent payment was actually made to the person giving the waiver. An improvement contract may not require an advance waiver (MCL 570.1115(1)).
When must a Michigan claimant give a full unconditional waiver?
Upon receipt of full contract payment. A partial unconditional waiver is owed for amounts received when the owner, lessee, or designee requests it (MCL 570.1115).
Does a Michigan lien waiver waive payment bond rights?
Not by itself. The statutory forms release construction lien rights against the described property. Whether another release reaches bond or contract claims depends on its wording.
Related Michigan Resources
Michigan Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Michigan Notice Requirements
Who must give notice, when, and how.
Michigan Mechanics Lien Forms
Every notice, lien, release, and bond claim form.
Michigan Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Michigan law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.