HomeMinnesotaMechanics Lien Forms
Minnesota Mechanics Lien Forms

Minnesota Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Minnesota construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Minnesota subcontractor or supplier generally needs three documents in order: a Pre-Lien Notice served within 45 days after first furnishing, a verified lien statement recorded and served within 120 days after last furnishing, and a foreclosure action with lis pendens within 1 year after the last date stated in the lien statement (Minn. Stat. §§ 514.011, 514.08, 514.12).

Both recording and service must occur within 120 days. The lien statement is recorded with the county recorder or registrar of titles and served personally or by certified mail on the owner, its authorized agent, or the person who contracted with the contractor (§ 514.08).

Once paid, the claimant must record a satisfaction at its own expense within 10 days after payment, tender, or a qualifying demand (§ 514.76). An interested party may also release the premises during a lien action by applying to the court and depositing money or a surety bond the court fixes (§ 514.10).

On public works, the claimant serves a notice of claim on the contractor and the surety, personally or by certified mail at the bond addresses, within 120 days after last furnishing. Suit follows within 1 year after the last date stated in the notice (Minn. Stat. § 574.31).

Minnesota mechanics lien law (Minn. Stat. ch. 514) starts with a Pre-Lien Notice in statutory language. The prime contractor includes it in the owner contract, and subcontractors and suppliers serve it within 45 days after first furnishing. Every claimant then records and serves a verified lien statement within 120 days and forecloses within 1 year.

The Pre-Lien Notice and the public payment bond notice of claim have statutory forms. The lien statement has nine required content items under § 514.08 and must be verified by oath.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text or offer downloadable forms.

Minnesota Preliminary Notices

Pre-Lien Notice by Prime Contractor

Statutory Form
Required When It Applies
Who uses it
Prime contractors that contract with the owner and use subcontractors or suppliers
When
In the written contract with the owner; if there is no written contract, delivered within 10 days after the work is agreed upon
Served on or filed with
The owner or its authorized agent, with a copy of the contract; a separate notice is delivered personally or by certified mail
Notarization
Not required
  • The statute prescribes the exact notice language and type size: at least 10-point bold if printed, capitals if typewritten.
  • Failure to give a required notice defeats the prime contractor's lien.

Minn. Stat. § 514.011, subd. 1

Pre-Lien Notice by Subcontractor or Supplier

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers without a direct contract with the owner
When
Within 45 days after first furnishing labor, skill, or materials
Served on or filed with
The owner or its authorized agent, personally or by certified mail
Notarization
Not required
  • The notice is not required on exempt projects: owners and contractors under common control; wholly residential projects of more than four units; and nonagricultural, wholly or partly nonresidential property meeting the 5,000 square foot tests in subdivision 4c.
  • Owner occupancy alone is not an exemption. A good-faith effort to comply preserves the lien unless actual damage is proven.

Minn. Stat. § 514.011, subds. 2, 4a to 4c

Request for Owner's Name and Address

Optional
Who uses it
Subcontractors and suppliers
When
At any time; the contractor must respond within 10 days after the request
Served on or filed with
The prime contractor
Notarization
Not required

Minn. Stat. § 514.011, subd. 3

Minnesota Lien Claim and Service

Mechanic's Lien Statement

Notarized
Required When It Applies
Who uses it
Every lien claimant
When
Recorded and served within 120 days after the last date of furnishing labor or materials
Served on or filed with
Recorded with the county recorder or registrar of titles; served personally or by certified mail on the owner, its authorized agent, or the person who contracted with the contractor
Notarization
Required. Verified by the oath of a person with knowledge of the facts
  • The statement must include the amount claimed, the improvement, the claimant and its customer, the first and last dates of furnishing, the property description, the owner, the claimant's mailing address, an acknowledgment of the 120-day service requirement, and a statement that any required Pre-Lien Notice was given.

Minn. Stat. §§ 514.08, 514.09

Itemized and Verified Lien Account

Notarized
Required When It Applies
Who uses it
A lien claimant that receives a written request from the owner
When
On request; the owner's request must be made within 15 days after completion of the contract
Served on or filed with
The requesting owner
Notarization
Required. The account must be verified
  • The claimant may not begin enforcement until 10 days after furnishing the account.

Minn. Stat. § 514.07

Minnesota Enforcing the Lien

Foreclosure Complaint and Summons

Required When It Applies
Who uses it
Lien claimants
When
Within 1 year after the last date of furnishing stated in the lien statement
Served on or filed with
Filed in the district court where the premises lie, with the summons served on each person to be bound
Notarization
Not required
  • Filing alone is not enough: the persons to be bound must be timely made parties. Ryan Contracting, Inc. v. JAG Investments, 634 N.W.2d 176 (Minn. 2001).
  • Other lienholders assert their liens by answer in the same action.

Minn. Stat. §§ 514.10, 514.11, 514.12

Notice of Lis Pendens

Required When It Applies
Who uses it
The foreclosure plaintiff
When
At the beginning of the action
Served on or filed with
Recorded with the county recorder or registrar of titles
Notarization
Not required by statute

Minn. Stat. § 514.12

Minnesota Releasing or Bonding Off a Lien

Application to Release Premises with Deposit or Bond

Optional
Who uses it
The owner or another interested party
When
After a foreclosure or adverse claims action has begun, on 10 days' notice of hearing to the claimant
Served on or filed with
Filed in the district court; the deposit or bond is made with the court administrator, and the release order is recorded where the lien is recorded
Notarization
Not required
  • The court fixes the amount, which must cover the claim, interest at $18 per $100, probable disbursements, and an attorney fee allowance. A surety must be listed on Treasury Circular 570.

Minn. Stat. § 514.10

Satisfaction of Mechanic's Lien

Required When It Applies
Who uses it
The lien claimant
When
Within 10 days after payment, tender, or written demand after the enforcement period expires without suit
Served on or filed with
Recorded in the land records where the lien appears
Notarization
Acknowledgment generally required for recording
  • A claimant that refuses to satisfy the lien owes $25 in liquidated damages plus proven damages.

Minn. Stat. §§ 514.76, 507.24

Minnesota Owner Notices and Forms

Notice of Nonauthorization

Optional
Who uses it
An owner or interest holder who did not authorize the improvement
When
Within 5 days after learning of the improvement
Served on or filed with
Served personally or by certified mail on the contributors, or posted conspicuously on the premises
Notarization
Not required

Minn. Stat. § 514.06

Owner's Request for Itemized and Verified Account

Optional
Who uses it
Owners
When
Within 15 days after completion of the contract
Served on or filed with
The lien claimant
Notarization
Not required for the request
  • Section 514.07 also lets the owner withhold payment for 120 days after completion except to the extent signed lien waivers are furnished.

Minn. Stat. § 514.07

Minnesota Public Works and Payment Bond Claims

Notice of Claim on Public Payment Bond

Statutory Form
Required When It Applies
Who uses it
Subcontractors, suppliers, and laborers on public works
When
Within 120 days after the claimant's last labor or materials
Served on or filed with
Both the contractor and the surety, personally or by certified mail at the addresses stated in the bond
Notarization
The statutory form includes a sworn verification and notary block; retain it
  • The notice states the nature and amount of the claim and the last date of furnishing.
  • Notice is excused only when the contractor failed to file the bond with both required addresses.

Minn. Stat. §§ 574.28, 574.31, subd. 2(a), (b)

Suit on Public Payment Bond

Required When It Applies
Who uses it
Claimants that served a timely notice of claim
When
Within 1 year after the last date of furnishing stated in the notice of claim
Served on or filed with
Filed in court, with service on the surety and other defendants
Notarization
Not required
  • The deadline may be extended by a written stipulation with the surety, or by a certified mail extension notice to the surety at least 90 days before the deadline if the surety does not object within 30 days.

Minn. Stat. § 574.31, subd. 2(c), (d)

Open Questions Under Minnesota Law

  • No controlling case decides whether a public payment bond notice of claim that omits the notarial verification in the statutory form is still effective under Minn. Stat. § 574.31. This point is not settled under Minnesota law. National Lien & Bond confirms it with a local Minnesota attorney before relying on it.

Frequently Asked Questions

Is there a statutory mechanics lien form in Minnesota?

The Pre-Lien Notice has mandatory statutory language and type size (Minn. Stat. § 514.011). The lien statement has no fill-in form, but § 514.08 lists nine items it must contain, and it must be verified by oath.

Does a Minnesota mechanics lien have to be notarized?

The lien statement must be verified by the oath of a person with knowledge of the facts (Minn. Stat. § 514.08). The Pre-Lien Notice does not require notarization.

Where do I file a mechanics lien in Minnesota?

Record the lien statement with the county recorder, or the registrar of titles for registered land, and serve it on the owner personally or by certified mail, both within 120 days after last furnishing (Minn. Stat. § 514.08).

Which projects are exempt from the Minnesota Pre-Lien Notice?

Exemptions cover owners and contractors under common control, wholly residential projects of more than four units, and nonagricultural property that meets one of the 5,000 square foot tests in Minn. Stat. § 514.011, subd. 4c. Owner occupancy alone is not an exemption.

What form releases a mechanics lien in Minnesota?

The claimant records a satisfaction at its own expense within 10 days after payment, tender, or a qualifying demand (Minn. Stat. § 514.76). During a lien action, an interested party may release the premises by court-approved deposit or bond (§ 514.10).

How long do I have to foreclose a Minnesota mechanics lien?

Within 1 year after the last date of furnishing stated in the lien statement, the claimant must file suit, bring in the persons to be bound, and record a notice of lis pendens (Minn. Stat. § 514.12).

What form do I use for a Minnesota public project bond claim?

Minn. Stat. § 574.31 provides a substantially sufficient notice of claim form. Serve it on the contractor and surety at the bond addresses within 120 days after last furnishing, then sue within 1 year after the last date stated in the notice.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us