Quick Answer
A Montana subcontractor or supplier usually needs four documents in order: a Notice of Right to Claim a Lien served on the contracting owner within 20 days after first furnishing, a recorded copy filed within 5 business days, a construction lien filed within 90 days after final furnishing, and a foreclosure complaint within 2 years (MCA 71-3-531, 71-3-535, 71-3-562).
The notice period becomes 45 days when a regulated lender's construction loan funds the improvement and the property is not the owner's own residence. No notice is required from original contractors, laborers, or claimants on commercial work or dwellings for five or more families (MCA 71-3-531).
Before filing the construction lien, serve a copy on each owner of record by personal service or certified mail. The clerk will not accept the lien without a certification of that service (MCA 71-3-534). The current statute does not require the lien to be verified or notarized.
Liens cannot attach to public property. A supplier to a subcontractor must notify the prime contractor within 30 days after first delivery, and every protected claimant must file a notice of claim with the public body within 90 days after completion and acceptance (MCA 18-2-206, 18-2-204).
Montana construction liens are governed by Title 71, Chapter 3, Part 5 of the Montana Code Annotated. Payment security on public works is governed by MCA 18-2-201 to 18-2-208. Construction liens cannot attach to public property, so payment rights on public work run through the contractor's security.
Montana prescribes the content of the Notice of Right to Claim a Lien and supplies a substantial form for the construction lien itself. The current statute does not require the lien to be verified. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
Montana Preliminary Notices
Notice of Right to Claim a Lien
- Who uses it
- Subcontractors, suppliers, and other claimants who did not contract directly with the owner
- When
- Within 20 days after first furnishing, or 45 days when a regulated lender's construction loan funds a property that is not the owner's residence
- Served on or filed with
- The contracting owner, by certified mail, which is effective when mailed, or by personal delivery with a written acknowledgment of receipt
- Notarization
- Not required
- A late notice limits the lien to what was furnished in the 20 days (or 45 days) before it was given, plus everything after.
- Not required from an original contractor, a laborer, or claimants on commercial work or dwellings for five or more families. The original contractor must supply owner and property information within 5 business days after a request.
MCA 71-3-531, 71-3-532
Recorded Copy of Notice of Right to Claim a Lien
- Who uses it
- Every claimant required to give the Notice of Right to Claim a Lien
- When
- No later than 5 business days after the notice is given to the owner; it lasts 1 year unless continued
- Served on or filed with
- Filed with the county clerk and recorder where the improved land lies
- Notarization
- Not required; signed by the claimant or an authorized signer
- The notice must be unexpired when the lien is filed. A signed continuation, recorded before expiration, extends it for another year.
MCA 71-3-531(6)
Montana Lien Claim and Service
Construction Lien
- Who uses it
- Contractors, subcontractors, suppliers, and laborers
- When
- Within 90 days after final furnishing, or within 90 days after the owner files a notice of completion
- Served on or filed with
- Filed with the county clerk and recorder of the county where the improved land lies
- Notarization
- Not required by the current statute
- The lien states the claimant, property, owner, contracting party, services or materials, unpaid amount, first and last furnishing dates, and whether a notice of right to claim a lien was given or why it was not required.
- Final furnishing is measured contract by contract; later work under a separate contract does not extend the deadline.
MCA 71-3-535, 71-3-536
Certification of Service on Owner
- Who uses it
- Every lien claimant
- When
- Before the construction lien is filed
- Served on or filed with
- A copy of the lien goes to each owner of record by personal service or certified mail, return receipt requested; the certification accompanies the lien to the recorder
- Notarization
- Not required
- The clerk cannot file the lien without the certification. Document the service method actually used.
MCA 71-3-534(2)
Montana Enforcing the Lien
Complaint to Foreclose Construction Lien
- Who uses it
- Lien claimants
- When
- Within 2 years after the lien is filed
- Served on or filed with
- Filed in the district court, joining interested persons and other lien claimants
- Notarization
- Not required
- Montana has no owner demand that shortens the 2-year period and no recorded lien extension.
MCA 71-3-561, 71-3-562
Notice of Pendency of Action
- Who uses it
- Foreclosing claimants
- When
- When the complaint is filed or afterward
- Served on or filed with
- Recorded with the county clerk and recorder where the property lies
- Notarization
- Not required
MCA 70-19-102
Montana Releasing or Bonding Off a Lien
Acknowledgment of Satisfaction of Lien
- Who uses it
- Lien claimants who have been paid
- When
- Upon payment and satisfaction of the lien
- Served on or filed with
- Recorded with the county clerk and recorder
- Notarization
- Required; acknowledged or proved for recording like a mortgage satisfaction
MCA 71-3-537, 71-1-211
Release of Notice of Right to Claim a Lien
- Who uses it
- Claimants who recorded a Notice of Right to Claim a Lien and have been paid
- When
- Within 5 business days after the owner's request
- Served on or filed with
- Recorded with the same county clerk and recorder
- Notarization
- Not required; signed by the filer or an authorized signer
- The release identifies the original notice's file number, filing date, and recipient. It is different from satisfying a recorded lien.
MCA 71-3-538
Substitution Bond
- Who uses it
- Contracting owners, original contractors, or subcontractors
- When
- Before foreclosure begins or within 30 days after service of the foreclosure complaint
- Served on or filed with
- Filed with the clerk of the district court of the county where the property lies
- Notarization
- Not required by statute
- The bond is 150 percent of the lien, in cash or with a corporate surety approved by a district judge. Filing it discharges the lien from the property.
- Suit on the bond is due within the same 2 years measured from the lien filing.
MCA 71-3-551, 71-3-552, 71-3-553
Montana Owner Notices and Forms
Notice of Completion
- Who uses it
- Contracting owners
- When
- At any time after completion, meaning written acceptance or 30 days without labor
- Served on or filed with
- Recorded with the county clerk and recorder, published once a week for 3 successive weeks, and copied to every person who gave the owner a Notice of Right to Claim a Lien
- Notarization
- Verified by the owner or agent; an affidavit of publication is filed
MCA 71-3-533
Montana Public Works and Payment Bond Claims
Notice to Contractor of Right of Action on Security
- Who uses it
- Persons furnishing provisions, materials, or supplies to a subcontractor on public works
- When
- Within 30 days after first delivery to the subcontractor
- Served on or filed with
- The prime contractor, by personal delivery or certified mail
- Notarization
- Not required
- The notice states the right of action on the security, that deliveries have begun, the subcontractor supplied, and the intent to hold the contractor and its security liable. Actual knowledge does not substitute for it.
MCA 18-2-206
Notice of Claim Against Security
- Who uses it
- Unpaid subcontractors, suppliers, and laborers on public works
- When
- Within 90 days after the contract is completed and the public body affirmatively accepts the work
- Served on or filed with
- Presented to and filed with the contracting public board or body
- Notarization
- Not required; signed by the claimant
MCA 18-2-204
Action on Public Works Security
- Who uses it
- Claimants who preserved their notices
- When
- No special statutory deadline; the 6-year period for actions on written obligations generally applies to suits filed on or after October 1, 2025
- Served on or filed with
- Filed in court in the claimant's own name
- Notarization
- Not required
- Attorney fees are unavailable if suit is filed within 30 days after the notice of claim is filed. Review the bond for any shorter enforceable term.
MCA 18-2-204, 27-2-202(1)
Open Questions Under Montana Law
- When the 6-year limitation for suit on a public works bond begins to run is not settled; the cautious course is to count it from the earliest unpaid payment default. This point is not settled under Montana law. National Lien & Bond confirms it with a local Montana attorney before relying on it.
Frequently Asked Questions
Is there a statutory construction lien form in Montana?
Yes, in substance. MCA 71-3-536 supplies a form the lien may substantially follow, and MCA 71-3-535 lists its required contents. MCA 71-3-532 prescribes the content of the Notice of Right to Claim a Lien, and MCA 18-2-204 supplies the public bond notice of claim.
Does a Montana construction lien have to be notarized?
No. The current MCA 71-3-535 and 71-3-536 do not require the lien to be verified or notarized. An Acknowledgment of Satisfaction must be acknowledged for recording like a mortgage satisfaction (MCA 71-3-537), and an owner's Notice of Completion must be verified (MCA 71-3-533).
Where do I file a construction lien in Montana?
File with the county clerk and recorder of the county where the improved land lies, within 90 days after final furnishing or after the owner files a notice of completion. Serve a copy on each owner of record first and attach the certification of service (MCA 71-3-534, 71-3-535).
Who must send a Notice of Right to Claim a Lien in Montana?
Claimants who did not contract with the owner, such as subcontractors and suppliers, unless the work is commercial or a dwelling for five or more families. Laborers and original contractors are exempt. Serve it within 20 days, or 45 days on qualifying lender-funded work, and record it within 5 business days (MCA 71-3-531).
What form releases a construction lien in Montana?
A paid claimant records an Acknowledgment of Satisfaction of Lien (MCA 71-3-537). A recorded Notice of Right to Claim a Lien is released separately within 5 business days after the owner's request (MCA 71-3-538). An owner, contractor, or subcontractor may substitute a bond of 150 percent of the lien (MCA 71-3-551).
Can a Montana owner shorten the time to foreclose?
No. A foreclosure action must be commenced within 2 years after the lien is filed, and Part 5 provides no owner demand that shortens that period and no recorded extension of it (MCA 71-3-562). Parties may agree to arbitrate lien disputes (MCA 71-3-564).
What form do I use for a Montana public project bond claim?
File a signed notice of claim, substantially in the statutory form, with the contracting public body within 90 days after completion and acceptance (MCA 18-2-204). A supplier to a subcontractor must also notify the prime contractor within 30 days after first delivery (MCA 18-2-206).
Related Montana Resources
Montana Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Montana Notice Requirements
Who must give notice, when, and how.
Montana Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Montana Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Montana law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.