Every notice, lien, enforcement, release, and bond claim document used on Nebraska construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Nebraska subcontractor or supplier usually needs two documents: a construction lien recorded with the register of deeds within 120 days after final furnishing, and an action to enforce filed within 2 years after recording (Neb. Rev. Stat. 52-137, 52-140). No preliminary notice is required to record a lien.

On residential work for a protected party, meaning an owner occupying or intending to occupy the home, the optional Notice of Right to Assert Lien should be served on the owner as early as possible, and a copy of the recorded lien must be sent to the owner within 10 days (Neb. Rev. Stat. 52-135).

An owner or other interested person may send a written demand to institute proceedings. The lien then lapses 30 days after receipt unless the claimant sues or records an affidavit that the total contract price is not yet due (Neb. Rev. Stat. 52-140, 52-152). The lien must be signed but need not be notarized.

Liens cannot attach to public property. A claimant contracting with a subcontractor, but not the prime contractor, must give the prime written notice within 4 months after last furnishing. Suit may begin 90 days after last furnishing and must be filed within 1 year after final settlement (Neb. Rev. Stat. 52-118.01, 52-118.02).

Nebraska construction liens are governed by the Nebraska Construction Lien Act, Neb. Rev. Stat. 52-125 to 52-159. Payment bonds on public works are governed by Neb. Rev. Stat. 52-118 to 52-118.02. Publicly owned real estate is exempt from construction liens, so payment rights on public work run through the bond.

The Act prescribes the content of each recorded instrument, including the lien, the notice of commencement, and the release, but it does not require the lien to be verified or notarized. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Nebraska Preliminary Notices

Notice of Right to Assert Lien

Statutory Form
Optional
Who uses it
Claimants not in direct contract with a protected-party owner on residential real estate
When
At any time after the claimant enters its contract, as early as possible
Served on or filed with
The contracting owner
Notarization
Not required
  • Against a protected party, the lien is limited to the lesser of the claimant's unpaid amount or the amount unpaid under the prime contract when the owner receives the notice, so early service matters.
  • The notice may also request a copy of any notice terminating a notice of commencement.

Neb. Rev. Stat. 52-135, 52-136

Nebraska Lien Claim and Service

Construction Lien

Required When It Applies
Who uses it
Contractors, subcontractors, and suppliers with lien rights
When
After entering the contract and no later than 120 days after the claimant's final furnishing
Served on or filed with
Recorded with the register of deeds of the county where the land lies
Notarization
Not required; signed by the claimant
  • The lien states the property, the person whose interest is charged, the claimant and contracting party, the services or materials and contract price, the amount unpaid, and the time of last furnishing.
  • Suppliers to mere suppliers have no lien rights.

Neb. Rev. Stat. 52-137, 52-147

Copy of Recorded Lien to Protected-Party Owner

Required When It Applies
Who uses it
Claimants recording a lien against a protected-party owner's residential real estate
When
Within 10 days after recording
Served on or filed with
The contracting owner
Notarization
Not required
  • This requirement applies only when the contracting owner is a protected party. It is a prerequisite to foreclosure in that setting.

Neb. Rev. Stat. 52-135(3)

Nebraska Enforcing the Lien

Action to Enforce Construction Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 2 years after recording, or within 30 days after receiving a demand to institute proceedings
Served on or filed with
Filed in court; other recorded claimants may join or be joined
Notarization
Not required
  • A timely proceeding continues the lien while it is pending.

Neb. Rev. Stat. 52-140, 52-155

Affidavit That Contract Price Is Not Yet Due

Notarized
Optional
Who uses it
Claimants who receive a demand to institute proceedings before the contract price is due
When
Within 30 days after receiving the demand, as an alternative to filing suit
Served on or filed with
Recorded in the same office as the lien
Notarization
Required (sworn affidavit)
  • The affidavit identifies the lien's record location and the owner and claimant. It does not extend the lien beyond the ordinary 2-year period.

Neb. Rev. Stat. 52-140, 52-152(2)

Nebraska Releasing or Bonding Off a Lien

Release of Lien

Required When It Applies
Who uses it
Lien claimants who have been paid or have settled
When
Upon payment or settlement; a partial release is made by recorded amendment
Served on or filed with
Recorded with the register of deeds
Notarization
Not required; signed by the claimant
  • The release states that the lien is released and identifies it by record location. Bad-faith refusal to release can support relief against the claimant.

Neb. Rev. Stat. 52-154, 52-148, 52-157

Surety Bond and Notice of Surety Bond

Optional
Who uses it
Owners or prime contractors who want to keep liens from attaching
When
Before liens attach; the notice of surety bond is recorded to obtain protection
Served on or filed with
The notice is recorded with the register of deeds; a true copy of the bond is furnished to claimants on request
Notarization
Not required
  • A claimant without a direct contract with the prime must give the prime written notice of the amount due within 90 days after completing its performance, and sue the surety within 1 year after completion.

Neb. Rev. Stat. 52-141, 52-150

Substitute Collateral and Clerk's Certificate

Optional
Who uses it
Any person with an interest in real estate subject to recorded liens
When
At any time after a lien is recorded
Served on or filed with
Deposited with the district court clerk of the recording county; the clerk's certificate is recorded with the register of deeds
Notarization
Not required
  • The deposit or surety bond must cover the claimed liens plus 15 percent. The claimant's rights transfer from the land to the collateral.

Neb. Rev. Stat. 52-142, 52-151

Nebraska Owner Notices and Forms

Notice of Commencement

Optional
Who uses it
Contracting owners; a qualifying claimant may record one if none applies
When
Effective on recording; lasts its stated term of at least 6 months, or 1 year if none is stated, and may be continued
Served on or filed with
Recorded with the register of deeds; a claimant that records one sends the owner a copy by the recording date
Notarization
Not required; signed
  • A recorded notice affects the priority and attachment timing of liens. Claimants should check for one before starting work.

Neb. Rev. Stat. 52-145

Termination of Notice of Commencement

Optional
Who uses it
Contracting owners
When
Recorded with an effective date at least 30 days later; copies to requesting claimants at least 3 weeks before it takes effect
Served on or filed with
Recorded with the register of deeds, mailed to requesting claimants, and published weekly for 3 consecutive weeks
Notarization
Affidavit of mailing and publication required
  • Termination does not change a claimant's 120-day recording deadline.

Neb. Rev. Stat. 52-146

Demand to Institute Judicial Proceedings

Optional
Who uses it
Owners, security interest holders, or other interested persons
When
At any time after a lien is recorded; the claimant has 30 days after receipt to respond
Served on or filed with
The lien claimant; a copy may also be recorded with the register of deeds
Notarization
Not required

Neb. Rev. Stat. 52-140(2), 52-152(1)

Nebraska Public Works and Payment Bond Claims

Notice of Claim on Public Payment Bond

Required When It Applies
Who uses it
Claimants who contracted with a subcontractor but have no contract with the bonded prime contractor
When
Within 4 months after the claimant's last furnishing
Served on or filed with
The prime contractor, by registered or certified mail to its office, place of business, or residence
Notarization
Not required
  • The notice states the amount claimed with substantial accuracy and the party supplied. Claimants more remote than a subcontractor's own subcontractors and suppliers do not gain bond rights by giving it.

Neb. Rev. Stat. 52-118.01

Suit on Public Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works
When
After 90 days from the claimant's last furnishing without full payment, and within 1 year after final settlement of the principal contract
Served on or filed with
Filed in court in the claimant's own name
Notarization
Not required
  • Final settlement is the public body's administrative determination of the amount due, not final payment. A bond is not required on state projects of $15,000 or less or listed local projects of $10,000 or less unless the specifications require it.

Neb. Rev. Stat. 52-118, 52-118.02

Frequently Asked Questions

Is there a statutory construction lien form in Nebraska?

No fixed form. Neb. Rev. Stat. 52-147 lists the contents of the recorded lien: the property, the person whose interest is charged, the claimant and contracting party, the services or materials and contract price, the amount unpaid, and the time of last furnishing. The Notice of Right to Assert Lien has prescribed content (52-135).

Does a Nebraska construction lien have to be notarized?

No. The lien must be signed by the claimant, but Neb. Rev. Stat. 52-147 does not require verification or notarization. A claimant's response to a demand to institute proceedings, if it is not a lawsuit, must be a recorded affidavit (52-140).

Where do I file a construction lien in Nebraska?

Record it with the register of deeds of the county where the land lies, no later than 120 days after your final furnishing (Neb. Rev. Stat. 52-137). If the owner is a protected party, send the owner a copy within 10 days after recording (52-135).

Do I need a preliminary notice to file a Nebraska lien?

No. No preliminary notice is required to record a Nebraska construction lien. On a protected party's residential project, an early Notice of Right to Assert Lien protects the amount a claimant not in direct contract can recover from the owner (Neb. Rev. Stat. 52-135, 52-136).

What form releases a construction lien in Nebraska?

The claimant records a signed statement releasing the lien that identifies it by record location (Neb. Rev. Stat. 52-154). An interested person can also release the property by depositing collateral or a bond of the claimed liens plus 15 percent with the district court clerk (52-142).

Can a Nebraska owner force me to sue sooner?

Yes. An owner or other interested person may give a written demand to institute proceedings. The lien lapses 30 days after you receive it unless you sue or record an affidavit that the total contract price is not yet due (Neb. Rev. Stat. 52-140).

What form do I use for a Nebraska public project bond claim?

Nebraska has no prescribed bond claim form. A claimant without a contract with the prime gives written notice by registered or certified mail within 4 months after last furnishing, stating the amount and party supplied (Neb. Rev. Stat. 52-118.01). Sue within 1 year after final settlement (52-118.02).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.