HomeNevadaLien Waivers
Nevada Lien Waivers

Nevada Lien Waiver Forms and Rules

When Nevada lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Nevada requires statutory lien waiver forms

Nevada requires a waiver or release of lien rights to be signed in the applicable statutory form, with its payment conditions met, to be enforceable (NRS 108.2457).

Quick Answer

Yes. Nevada requires its statutory lien waiver forms. A waiver or release of lien rights is enforceable only if the claimant or its authorized agent signs it in the applicable form under NRS 108.2457 and the payment conditions are met. The four forms are conditional and unconditional waivers upon progress payment and upon final payment.

A contract term that attempts to waive or impair lien rights in advance is void (NRS 108.2457(1), 108.2453). A signed written settlement of a bona fide dispute, or of pending litigation or arbitration, may waive lien rights it specifically identifies (NRS 108.2457(4)).

None of the four forms must be notarized. If the check or other instrument given in exchange for a waiver fails to clear, the waiver is null and void, even an unconditional one (NRS 108.2457(5)(e); Cashman Equipment Co. v. West Edna Associates, Ltd., 380 P.3d 844 (Nev. 2016)).

Nevada is a mandatory statutory form state. Under NRS 108.2457, a waiver or release of a lien claimant's rights is enforceable only if it is signed in the applicable statutory form and the payment requirements are met. The four forms cover conditional and unconditional releases on progress and final payments.

The forms reach more than the recorded lien; they also address bond rights and other payment rights for the work covered. A contract term that tries to waive or impair lien rights in advance is void.

Nevada Lien Waiver Types

Conditional Waiver and Release Upon Progress Payment

Statutory Form
When to use it
Delivered to induce a progress payment, or when the payment is a single or joint-payee check
When it takes effect
Effective when the check is properly endorsed and paid by the bank, and only to the amount actually paid; retention, pending changes, and disputed items are excluded

Unconditional Waiver and Release Upon Progress Payment

Statutory Form
When to use it
Delivered after a progress payment has actually been received
When it takes effect
Limited to the amount received for the invoiced work; the statutory warning must appear in type at least as large as the document's largest type

Conditional Waiver and Release Upon Final Payment

Statutory Form
When to use it
Delivered to induce final payment, or when final payment is a single or joint-payee check
When it takes effect
Effective when the check is properly endorsed and paid by the bank; claims listed as disputed are excluded

Unconditional Waiver and Release Upon Final Payment

Statutory Form
When to use it
Delivered after the final billing has been paid
When it takes effect
Releases all rights except identified disputed claims; it remains subject to the rule that a waiver given for a dishonored instrument is void

The statutory forms are mandatory

A waiver or release is enforceable only if it follows the applicable statutory form and the payment requirements are met (NRS 108.2457). A claimant is not obliged to waive, but a party seeking an enforceable waiver must use the form.

The forms address bond rights, payment claims, and related statutory payment rights for the covered work, not only the recorded lien. Review the scope before signing.

Advance waivers are void

A contract term that attempts to waive or impair lien rights is void except as NRS 108.2457 permits, and NRS 108.2453 reinforces the rule. The Nevada Supreme Court rejected an unpaid-work lien waiver on public policy grounds (Lehrer McGovern Bovis v. Bullock Insulation, 197 P.3d 1032 (Nev. 2008)).

A signed written accord and satisfaction of a bona fide dispute, or settlement of pending court or arbitration proceedings, may remain enforceable if it specifically identifies the lien rights waived (NRS 108.2457(4)).

Dishonored payments and joint checks

If the check or other negotiable instrument given for a waiver fails to clear for any reason, the waiver is null and void, and lien, bond, and contract rights are unaffected (NRS 108.2457(5)(e)). Payment to an intermediary is not payment to the claimant (Cashman Equipment Co. v. West Edna Associates, Ltd., 380 P.3d 844 (Nev. 2016)).

For a qualifying joint check, endorsement and bank clearance count as payment only up to the least of the check amount, the amount intended for the claimant, or the claimant's outstanding balance (NRS 108.2457(3)).

Notarization

All four forms require the signature of the claimant or its authorized agent. None requires notarization or verification under NRS 108.2457.

Public works releases

Chapter 339 does not prescribe the Chapter 108 forms. For public work progress and retainage payments, a required waiver or release is conditional until the money is received and is limited to the invoiced labor, materials, and equipment (NRS 338.490).

A retainage release using final-payment language did not extinguish separate delay claims outside the retainage bill (APCO Construction, Inc. v. Helix Electric of Nevada, LLC, 509 P.3d 49 (Nev. 2022)).

Residential work

NRS 108.2457 has no separate residential forms. Residential projects carry the 15-day Notice of Intent to Lien and contractor disclosures under NRS 624.600.

A 2025 amendment, effective October 1, 2025, extended residential solar disclosure and paid-portion unconditional release requirements to covered photovoltaic work on qualified multifamily affordable housing (2025 Nev. Stat., ch. 254). It did not replace the four waiver forms.

Exchange Nevada lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Frequently Asked Questions

Does Nevada require statutory lien waiver forms?

Yes. A waiver or release of lien rights is enforceable only if it is signed in the applicable statutory form and the payment requirements are met (NRS 108.2457). The forms cover conditional and unconditional releases upon progress payment and upon final payment.

Does a Nevada lien waiver need to be notarized?

No. The statutory forms must be signed by the claimant or its authorized agent, but NRS 108.2457 does not require notarization or verification.

Are advance lien waivers enforceable in Nevada?

No. A contract term that attempts to waive or impair lien rights in advance is void (NRS 108.2457(1), 108.2453). Only a written settlement of a bona fide dispute or pending proceeding that specifically identifies the rights waived is excepted.

What happens if I sign a Nevada unconditional waiver and the check bounces?

The waiver is null and void if the instrument given in exchange fails to clear for any reason, and your lien and bond rights are unaffected (NRS 108.2457(5)(e)). Even so, use the conditional form until payment clears, because the unconditional form's warning says it binds without payment.

Do Nevada lien waiver forms affect my bond rights?

Yes. The NRS 108.2457 forms address bond rights and related payment rights for the covered work, not only the lien. On public works, NRS 338.490 makes progress and retainage releases conditional until money is received and limits them to invoiced work.

Can a Nevada final waiver release my claims for extra work?

The unconditional final form releases everything except claims listed as disputed, so list every open claim. On public works, a retainage release did not extinguish separate delay claims outside the retainage bill (APCO Construction, Inc. v. Helix Electric of Nevada, LLC, 509 P.3d 49 (Nev. 2022)).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us