Every notice, lien, enforcement, release, and bond claim document used on New Mexico construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A New Mexico subcontractor or supplier usually needs four documents in order: a Notice of Right to Claim a Lien within 60 days after first furnishing, a verified claim of lien recorded with the county clerk, a copy sent to the owner within 15 days, and a proceeding to enforce within 2 years (NMSA 48-2-2.1, 48-2-6, 48-2-10).

The Notice of Right to Claim a Lien applies only to claimants that contract with neither the owner nor the original contractor, on liens over $5,000, and not on residential property of four or fewer units. A late notice still reaches work furnished from 30 days before it is given (NMSA 48-2-2.1).

The claim of lien is due within 120 days after completion of the original contractor's own contract, or for everyone else within 90 days after completion of the building or improvement. It must be verified by oath (NMSA 48-2-6). Enforcement may proceed in court or by binding arbitration.

Liens cannot attach to public property. A claimant that contracted with a subcontractor but not the bonded contractor must give the contractor written notice within 90 days after last furnishing. Suit is due within 1 year after final settlement of the prime contract (NMSA 13-4-19).

New Mexico mechanics liens are governed by NMSA 1978, 48-2-1 et seq. The Construction Lien Stop Notice Act, NMSA 1978, 48-2A-1 et seq., adds a claim against construction funds on residential work of four or fewer dwelling units. Payment bonds on public works are governed by NMSA 1978, 13-4-18 to 13-4-20.

No New Mexico statute prescribes a fixed form for the claim of lien; NMSA 48-2-6 lists its contents and requires verification by oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

New Mexico Preliminary Notices

Notice of Right to Claim a Lien

Required When It Applies
Who uses it
Claimants contracting with neither the owner nor the original contractor, such as sub-subcontractors and suppliers to subcontractors, on liens over $5,000
When
Within 60 days after first furnishing; a late notice reaches only work furnished from 30 days before it is given
Served on or filed with
The owner or reputed owner, or the original contractor, by certified mail with return receipt requested, fax with acknowledgment, or personal delivery
Notarization
Not required
  • Not required on residential property of four or fewer dwelling units, from original contractors, or from claimants contracting directly with the original contractor.
  • An owner or contractor that fails to supply project, owner, contractor, and surety information within 5 days after a written request cannot raise the lack of notice as a defense.

NMSA 48-2-2.1

Stop Notice Preliminary Notice (Residential)

Required When It Applies
Who uses it
Subcontractors and materialmen on residential site improvements of four or fewer dwelling units who want stop notice rights
When
Within 20 days after first furnishing; a late notice loses protection for furnishing more than 20 days before it is given
Served on or filed with
The owner and the construction lender, if any, by hand delivery or mail with return receipt requested
Notarization
Not required
  • This notice preserves rights against construction funds only. Recording a lien on residential work does not depend on it.

NMSA 48-2A-3, 48-2A-5, 48-2A-6

New Mexico Lien Claim and Service

Claim of Lien

Required When It Applies
Who uses it
Original contractors, subcontractors, suppliers, and laborers
When
Original contractors: within 120 days after completion of their contract. All others: within 90 days after completion of the building, improvement, alteration, or repair
Served on or filed with
Recorded with the county clerk of the county where the property or part of it lies
Notarization
Verified by oath of the claimant or another person
  • The claim states the net demand after credits, the owner or reputed owner, the party that employed the claimant or received the materials, the contract terms, and a property description.
  • A claim against two or more improvements of the same owner must designate the amount due on each.

NMSA 48-2-6, 48-2-7, 48-2-8

Copy of Claim of Lien to Owner

Required When It Applies
Who uses it
Every claimant that records a claim of lien
When
Within 15 days after filing
Served on or filed with
The owner or reputed owner at the last known address, or the county assessor's address, by mail, email, certified mail, or hand delivery
Notarization
Not required
  • Missing this step does not void the lien, but it can cost interest, attorney fees, and costs.

NMSA 48-2-6(B)

Stop Notice (Residential)

Required When It Applies
Who uses it
Subcontractors and materialmen who gave the stop notice preliminary notice
When
No earlier than 20 days and no later than 30 days after presenting a request for payment to the original contractor
Served on or filed with
The construction lender, or the owner if there is no lender, by the delivery methods the statute specifies
Notarization
Signed and verified
  • The stop notice is not effective without a bond or cash collateral of 125 percent of the claim. It is a claim against construction funds, not the property.

NMSA 48-2A-5, 48-2A-6, 48-2A-7

New Mexico Enforcing the Lien

Proceeding to Enforce Claim of Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 2 years after the claim of lien is filed
Served on or filed with
A court of competent jurisdiction, or binding arbitration
Notarization
Not required
  • A notice of lis pendens may be recorded after suit is filed; it need not be acknowledged (NMSA 38-1-14).

NMSA 48-2-10

Suit to Satisfy Stop Notice

Required When It Applies
Who uses it
Stop notice claimants
When
No earlier than 30 days and no later than 60 days after delivering the stop notice; written notice of the suit is mailed to the recipient within 5 days after filing
Served on or filed with
Filed in court; notice mailed to the stop notice recipient
Notarization
Not required
  • While this suit is pending, the claimant may not file a lien for the same money.

NMSA 48-2A-9

New Mexico Releasing or Bonding Off a Lien

Petition to Cancel Lien and Substitute Security

Optional
Who uses it
Owners, or original contractors that contracted with the owner
When
At any time after the claim of lien is recorded
Served on or filed with
Filed in the district court of the county where the property lies; the judge's cancellation order is recorded by the county clerk
Notarization
Not required
  • The judge sets and approves security sufficient for the claim, damages, costs, and fees, and the lien transfers to the security.

NMSA 48-2-9

Release of Lien

Notarized
Required When It Applies
Who uses it
Lien claimants who have been paid or have settled
When
Upon payment or settlement
Served on or filed with
Recorded with the county clerk
Notarization
Required for recording (acknowledgment)

NMSA 14-8-4

Claim Satisfied Notice

Required When It Applies
Who uses it
Stop notice claimants whose claim has been satisfied
When
Within 10 days after satisfaction
Served on or filed with
Every recipient of the bonded stop notice
Notarization
Not required; signed statement of satisfaction
  • Failure to deliver it on time is a misdemeanor. The original contractor may instead discharge a stop notice with a 125 percent bond.

NMSA 48-2A-10

New Mexico Owner Notices and Forms

Notice of Nonresponsibility

Optional
Who uses it
Owners and other interested persons who did not cause the improvement
When
Within 3 days after learning of the construction, alteration, or repair
Served on or filed with
Posted in a conspicuous place on the land or improvement
Notarization
Not required
  • It does not protect an owner that caused or contracted for the improvement, directly or indirectly (Skidmore v. Eby, 1953-NMSC-098).

NMSA 48-2-11

Residential Completion and Final Payment Affidavit

Notarized
Required When It Applies
Who uses it
Original contractors on residential work of four or fewer dwelling units
When
On completion and acceptance of final payment
Served on or filed with
The owner, its successor, or agent, for the closing process
Notarization
Required (sworn affidavit)
  • The affidavit states that received invoices are paid, or identifies paid claimants, unpaid claimants with signed waivers, and unpaid claimants without waivers. The owner may escrow amounts for unpaid, unwaived invoices.

NMSA 48-2A-12

New Mexico Public Works and Payment Bond Claims

Notice to Bonded Contractor

Required When It Applies
Who uses it
Claimants that contracted with a subcontractor but have no contract with the bonded contractor
When
Within 90 days after last furnishing labor or materials
Served on or filed with
The bonded contractor, by registered mail or by service in the manner of a civil summons
Notarization
Not required
  • The notice states the amount claimed with substantial accuracy and the party supplied. Notice to the surety alone does not satisfy it.

NMSA 13-4-19(B)

Suit on Public Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works over $25,000
When
After 90 days from last furnishing without full payment, and within 1 year after final settlement of the prime contract
Served on or filed with
Filed in district court in the name of the State for the claimant's use; notice of the suit goes to the bond obligee
Notarization
Not required
  • Final settlement is the date the public body sets in the final closing and settlement of payment. Judgment must await 30 days after the obligee receives notice of the suit.

NMSA 13-4-18, 13-4-19

Frequently Asked Questions

Is there a statutory mechanics lien form in New Mexico?

No fixed form. NMSA 48-2-6 lists what the claim of lien must contain: the net demand after credits, the owner or reputed owner, the party that employed the claimant, the contract terms, and a property description. It must be verified by oath.

Does a New Mexico mechanics lien have to be notarized?

Yes, in effect. The claim of lien must be verified by the oath of the claimant or another person (NMSA 48-2-6). The Notice of Right to Claim a Lien need not be sworn, and a recorded release of lien must be acknowledged under the recording statute (NMSA 14-8-4).

Where do I file a mechanics lien in New Mexico?

Record the claim of lien with the county clerk of the county where the property lies, then send the owner a copy within 15 days (NMSA 48-2-6). Original contractors have 120 days after completing their contract; others have 90 days after completion of the improvement.

Who must send a Notice of Right to Claim a Lien in New Mexico?

Claimants that contract with neither the owner nor the original contractor, on liens over $5,000, except on residential property of four or fewer units. Give it within 60 days after first furnishing; a late notice reaches only work from 30 days before it (NMSA 48-2-2.1).

What form releases a mechanics lien in New Mexico?

A paid claimant records a release, acknowledged for recording (NMSA 14-8-4). An owner or original contractor may also petition the district court to cancel the lien by depositing court-approved security (NMSA 48-2-9).

Does New Mexico have a stop notice?

Yes, for residential work of four or fewer dwelling units. A claimant gives a preliminary notice within 20 days after first furnishing, delivers a verified, bonded stop notice to the lender 20 to 30 days after requesting payment, and sues 30 to 60 days after delivery (NMSA 48-2A-5 to 48-2A-9).

What form do I use for a New Mexico public project bond claim?

New Mexico has no prescribed bond claim form. A claimant that contracted with a subcontractor gives the bonded contractor written notice by registered mail within 90 days after last furnishing. Suit is due within 1 year after final settlement of the prime contract (NMSA 13-4-19).