New Mexico Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on New Mexico construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A New Mexico subcontractor or supplier usually needs four documents in order: a Notice of Right to Claim a Lien within 60 days after first furnishing, a verified claim of lien recorded with the county clerk, a copy sent to the owner within 15 days, and a proceeding to enforce within 2 years (NMSA 48-2-2.1, 48-2-6, 48-2-10).
The Notice of Right to Claim a Lien applies only to claimants that contract with neither the owner nor the original contractor, on liens over $5,000, and not on residential property of four or fewer units. A late notice still reaches work furnished from 30 days before it is given (NMSA 48-2-2.1).
The claim of lien is due within 120 days after completion of the original contractor's own contract, or for everyone else within 90 days after completion of the building or improvement. It must be verified by oath (NMSA 48-2-6). Enforcement may proceed in court or by binding arbitration.
Liens cannot attach to public property. A claimant that contracted with a subcontractor but not the bonded contractor must give the contractor written notice within 90 days after last furnishing. Suit is due within 1 year after final settlement of the prime contract (NMSA 13-4-19).
New Mexico mechanics liens are governed by NMSA 1978, 48-2-1 et seq. The Construction Lien Stop Notice Act, NMSA 1978, 48-2A-1 et seq., adds a claim against construction funds on residential work of four or fewer dwelling units. Payment bonds on public works are governed by NMSA 1978, 13-4-18 to 13-4-20.
No New Mexico statute prescribes a fixed form for the claim of lien; NMSA 48-2-6 lists its contents and requires verification by oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
New Mexico Preliminary Notices
Notice of Right to Claim a Lien
- Who uses it
- Claimants contracting with neither the owner nor the original contractor, such as sub-subcontractors and suppliers to subcontractors, on liens over $5,000
- When
- Within 60 days after first furnishing; a late notice reaches only work furnished from 30 days before it is given
- Served on or filed with
- The owner or reputed owner, or the original contractor, by certified mail with return receipt requested, fax with acknowledgment, or personal delivery
- Notarization
- Not required
- Not required on residential property of four or fewer dwelling units, from original contractors, or from claimants contracting directly with the original contractor.
- An owner or contractor that fails to supply project, owner, contractor, and surety information within 5 days after a written request cannot raise the lack of notice as a defense.
NMSA 48-2-2.1
Stop Notice Preliminary Notice (Residential)
- Who uses it
- Subcontractors and materialmen on residential site improvements of four or fewer dwelling units who want stop notice rights
- When
- Within 20 days after first furnishing; a late notice loses protection for furnishing more than 20 days before it is given
- Served on or filed with
- The owner and the construction lender, if any, by hand delivery or mail with return receipt requested
- Notarization
- Not required
- This notice preserves rights against construction funds only. Recording a lien on residential work does not depend on it.
NMSA 48-2A-3, 48-2A-5, 48-2A-6
New Mexico Lien Claim and Service
Claim of Lien
- Who uses it
- Original contractors, subcontractors, suppliers, and laborers
- When
- Original contractors: within 120 days after completion of their contract. All others: within 90 days after completion of the building, improvement, alteration, or repair
- Served on or filed with
- Recorded with the county clerk of the county where the property or part of it lies
- Notarization
- Verified by oath of the claimant or another person
- The claim states the net demand after credits, the owner or reputed owner, the party that employed the claimant or received the materials, the contract terms, and a property description.
- A claim against two or more improvements of the same owner must designate the amount due on each.
NMSA 48-2-6, 48-2-7, 48-2-8
Copy of Claim of Lien to Owner
- Who uses it
- Every claimant that records a claim of lien
- When
- Within 15 days after filing
- Served on or filed with
- The owner or reputed owner at the last known address, or the county assessor's address, by mail, email, certified mail, or hand delivery
- Notarization
- Not required
- Missing this step does not void the lien, but it can cost interest, attorney fees, and costs.
NMSA 48-2-6(B)
Stop Notice (Residential)
- Who uses it
- Subcontractors and materialmen who gave the stop notice preliminary notice
- When
- No earlier than 20 days and no later than 30 days after presenting a request for payment to the original contractor
- Served on or filed with
- The construction lender, or the owner if there is no lender, by the delivery methods the statute specifies
- Notarization
- Signed and verified
- The stop notice is not effective without a bond or cash collateral of 125 percent of the claim. It is a claim against construction funds, not the property.
NMSA 48-2A-5, 48-2A-6, 48-2A-7
New Mexico Enforcing the Lien
Proceeding to Enforce Claim of Lien
- Who uses it
- Lien claimants
- When
- Within 2 years after the claim of lien is filed
- Served on or filed with
- A court of competent jurisdiction, or binding arbitration
- Notarization
- Not required
- A notice of lis pendens may be recorded after suit is filed; it need not be acknowledged (NMSA 38-1-14).
NMSA 48-2-10
Suit to Satisfy Stop Notice
- Who uses it
- Stop notice claimants
- When
- No earlier than 30 days and no later than 60 days after delivering the stop notice; written notice of the suit is mailed to the recipient within 5 days after filing
- Served on or filed with
- Filed in court; notice mailed to the stop notice recipient
- Notarization
- Not required
- While this suit is pending, the claimant may not file a lien for the same money.
NMSA 48-2A-9
New Mexico Releasing or Bonding Off a Lien
Petition to Cancel Lien and Substitute Security
- Who uses it
- Owners, or original contractors that contracted with the owner
- When
- At any time after the claim of lien is recorded
- Served on or filed with
- Filed in the district court of the county where the property lies; the judge's cancellation order is recorded by the county clerk
- Notarization
- Not required
- The judge sets and approves security sufficient for the claim, damages, costs, and fees, and the lien transfers to the security.
NMSA 48-2-9
Release of Lien
- Who uses it
- Lien claimants who have been paid or have settled
- When
- Upon payment or settlement
- Served on or filed with
- Recorded with the county clerk
- Notarization
- Required for recording (acknowledgment)
NMSA 14-8-4
Claim Satisfied Notice
- Who uses it
- Stop notice claimants whose claim has been satisfied
- When
- Within 10 days after satisfaction
- Served on or filed with
- Every recipient of the bonded stop notice
- Notarization
- Not required; signed statement of satisfaction
- Failure to deliver it on time is a misdemeanor. The original contractor may instead discharge a stop notice with a 125 percent bond.
NMSA 48-2A-10
New Mexico Owner Notices and Forms
Notice of Nonresponsibility
- Who uses it
- Owners and other interested persons who did not cause the improvement
- When
- Within 3 days after learning of the construction, alteration, or repair
- Served on or filed with
- Posted in a conspicuous place on the land or improvement
- Notarization
- Not required
- It does not protect an owner that caused or contracted for the improvement, directly or indirectly (Skidmore v. Eby, 1953-NMSC-098).
NMSA 48-2-11
Residential Completion and Final Payment Affidavit
- Who uses it
- Original contractors on residential work of four or fewer dwelling units
- When
- On completion and acceptance of final payment
- Served on or filed with
- The owner, its successor, or agent, for the closing process
- Notarization
- Required (sworn affidavit)
- The affidavit states that received invoices are paid, or identifies paid claimants, unpaid claimants with signed waivers, and unpaid claimants without waivers. The owner may escrow amounts for unpaid, unwaived invoices.
NMSA 48-2A-12
New Mexico Public Works and Payment Bond Claims
Notice to Bonded Contractor
- Who uses it
- Claimants that contracted with a subcontractor but have no contract with the bonded contractor
- When
- Within 90 days after last furnishing labor or materials
- Served on or filed with
- The bonded contractor, by registered mail or by service in the manner of a civil summons
- Notarization
- Not required
- The notice states the amount claimed with substantial accuracy and the party supplied. Notice to the surety alone does not satisfy it.
NMSA 13-4-19(B)
Suit on Public Payment Bond
- Who uses it
- Unpaid claimants on bonded public works over $25,000
- When
- After 90 days from last furnishing without full payment, and within 1 year after final settlement of the prime contract
- Served on or filed with
- Filed in district court in the name of the State for the claimant's use; notice of the suit goes to the bond obligee
- Notarization
- Not required
- Final settlement is the date the public body sets in the final closing and settlement of payment. Judgment must await 30 days after the obligee receives notice of the suit.
NMSA 13-4-18, 13-4-19
Frequently Asked Questions
Is there a statutory mechanics lien form in New Mexico?
No fixed form. NMSA 48-2-6 lists what the claim of lien must contain: the net demand after credits, the owner or reputed owner, the party that employed the claimant, the contract terms, and a property description. It must be verified by oath.
Does a New Mexico mechanics lien have to be notarized?
Yes, in effect. The claim of lien must be verified by the oath of the claimant or another person (NMSA 48-2-6). The Notice of Right to Claim a Lien need not be sworn, and a recorded release of lien must be acknowledged under the recording statute (NMSA 14-8-4).
Where do I file a mechanics lien in New Mexico?
Record the claim of lien with the county clerk of the county where the property lies, then send the owner a copy within 15 days (NMSA 48-2-6). Original contractors have 120 days after completing their contract; others have 90 days after completion of the improvement.
Who must send a Notice of Right to Claim a Lien in New Mexico?
Claimants that contract with neither the owner nor the original contractor, on liens over $5,000, except on residential property of four or fewer units. Give it within 60 days after first furnishing; a late notice reaches only work from 30 days before it (NMSA 48-2-2.1).
What form releases a mechanics lien in New Mexico?
A paid claimant records a release, acknowledged for recording (NMSA 14-8-4). An owner or original contractor may also petition the district court to cancel the lien by depositing court-approved security (NMSA 48-2-9).
Does New Mexico have a stop notice?
Yes, for residential work of four or fewer dwelling units. A claimant gives a preliminary notice within 20 days after first furnishing, delivers a verified, bonded stop notice to the lender 20 to 30 days after requesting payment, and sues 30 to 60 days after delivery (NMSA 48-2A-5 to 48-2A-9).
What form do I use for a New Mexico public project bond claim?
New Mexico has no prescribed bond claim form. A claimant that contracted with a subcontractor gives the bonded contractor written notice by registered mail within 90 days after last furnishing. Suit is due within 1 year after final settlement of the prime contract (NMSA 13-4-19).
Related New Mexico Resources
New Mexico Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
New Mexico Notice Requirements
Who must give notice, when, and how.
New Mexico Lien Waivers
Statutory forms, waiver types, and enforceability rules.
New Mexico Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about New Mexico law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.