HomeNew YorkMechanics Lien Forms
New York Mechanics Lien Forms

New York Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on New York construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A New York subcontractor or supplier usually needs four documents in order: a verified Notice of Mechanic's Lien filed with the county clerk within 8 months after last furnishing, service on the owner and contractor within 30 days after filing, proof of service filed within 35 days, and a foreclosure action within 1 year (Lien Law 10, 11, 11-b, 17).

No preliminary notice is required in New York. The filing window is 4 months for a single-family dwelling, and a lien for retainage alone may be filed within 90 days after the retainage was due (Lien Law 10). Failing to file proof of service within 35 days terminates the lien (Lien Law 11).

A lien lasts 1 year unless the claimant forecloses and files a notice of pendency, or files one extension for another year. A single-family dwelling lien can be extended only by court order (Lien Law 17). An owner may serve a notice requiring suit within at least 30 days (Lien Law 59).

On public improvements, a lien on unpaid public funds is filed with the department head and the paying officer before, or within 30 days after, completion and acceptance (Lien Law 12). Under State Finance Law 137, a claimant hired by a subcontractor notifies the prime within 120 days after last furnishing.

New York mechanics liens are governed by Article 2 of the New York Lien Law, including Lien Law 9 to 21 for filing, service, duration, and discharge. Article 3-A creates trust funds for project money. Payment bonds on state public works are governed by State Finance Law 137, and Lien Law 5 and 12 create a lien on unpaid public funds.

New York prescribes no fixed lien form. Lien Law 9 lists the contents of the notice of lien, which must be verified, and certificates discharging a lien must be acknowledged. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

New York Lien Claim and Service

Notice of Mechanic's Lien

Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, and laborers
When
During the work or within 8 months after completion of the contract or last furnishing; 4 months for a single-family dwelling; 90 days after retainage was due for a retainage-only lien
Served on or filed with
Filed with the county clerk of each county where the property lies
Notarization
Verified by the lienor or its agent
  • The notice states the lienor, the owner, the hiring party, the labor or materials and their value, the amount unpaid, the first and last dates, the property, and whether it is improved or to be improved with a single-family dwelling.
  • A developer's subdivision house that is not its own residence is not a single-family dwelling for the 4-month rule.

N.Y. Lien Law 9, 10

Service on Owner and Proof of Service

Required When It Applies
Who uses it
Every lien claimant
When
Serve within 5 days before or 30 days after filing; file proof of service within 35 days after filing
Served on or filed with
The owner by the personal, substituted, certified-mail, or limited posting methods the statute allows; proof is filed with the county clerk
Notarization
Proof of service ordinarily by affidavit
  • If proof of service is not filed within 35 days, the lien terminates.

N.Y. Lien Law 11

Copy of Notice of Lien to Contractor

Required When It Applies
Who uses it
Subcontractors and lower-tier lienors
When
Within 5 days before or 30 days after filing the lien or an amendment
Served on or filed with
The contractor or subcontractor that hired the lienor by certified mail; qualifying lower-tier lienors also serve the prime contractor
Notarization
Proof of service filed with the county clerk
  • Owner service does not satisfy this separate requirement.

N.Y. Lien Law 11-b

New York Enforcing the Lien

Foreclosure Action and Notice of Pendency

Required When It Applies
Who uses it
Lienors and their assignees
When
Within 1 year after the lien is filed, unless extended
Served on or filed with
Filed in the proper court; the notice of pendency is filed with the county clerk
Notarization
Not required
  • Commencing suit alone does not preserve the lien; the notice of pendency must also be filed. No real-property notice of pendency is filed after the lien has been discharged by deposit or order.

N.Y. Lien Law 17, 41

Extension of Lien

Required When It Applies
Who uses it
Lienors on property other than a single-family dwelling
When
Filed before the original 1 year expires; it lasts 1 year from its filing
Served on or filed with
Filed with the same county clerk
Notarization
Not required
  • Only one extension may be filed. Further extensions, and any extension of a single-family dwelling lien, require a court order.

N.Y. Lien Law 17

Demand for Verified Statement of Trust Assets

Required When It Applies
Who uses it
Trust beneficiaries such as subcontractors and suppliers
When
Beginning 30 days after the trust claim becomes payable, and generally no more than once a month
Served on or filed with
The owner, contractor, or subcontractor trustee, personally or by registered or certified mail
Notarization
Not required for the demand; the trustee's statement is verified
  • The trustee must allow inspection or serve a verified statement generally within 10 days after the request.

N.Y. Lien Law 75, 76

New York Releasing or Bonding Off a Lien

Certificate of Satisfaction or Release of Lien

Notarized
Required When It Applies
Who uses it
Lienors who have been paid or have settled, in whole or in part
When
When agreeing to discharge all or part of the lien
Served on or filed with
Filed in the office where the lien was filed
Notarization
Required (acknowledged or proved)

N.Y. Lien Law 19(1)

Undertaking or Deposit to Discharge Lien

Optional
Who uses it
Owners or contractors
When
Before or after a foreclosure action begins
Served on or filed with
An undertaking is filed with the county clerk and a copy served on the lienor; a deposit is made with the county clerk or as the court orders
Notarization
Executed undertaking with surety papers
  • An undertaking is 110 percent of the lien. Bonding off substitutes security for the property; it does not pay or extinguish the debt.
  • A bond to discharge all liens under a contract is also available (Lien Law 37).

N.Y. Lien Law 19(4), 20, 37

New York Owner Notices and Forms

Notice to Commence Action

Optional
Who uses it
Owners and other interested persons
When
At any time after the lien is filed; it gives the lienor at least 30 days after service to sue
Served on or filed with
The lienor, personally or at its residence as the statute allows
Notarization
Affidavit of service and noncommencement supports the cancellation application
  • If the lienor does not sue in time, the court may order the lien cancelled.

N.Y. Lien Law 59

Demand for Itemized Statement

Optional
Who uses it
Owners and contractors
When
At any time after a lien is filed; the lienor must respond within 5 days
Served on or filed with
The lienor
Notarization
Not required for the demand; the lienor's statement is verified
  • Missing the 5 days does not cancel the lien by itself. The owner must obtain a compliance order, and the lien may be cancelled if the lienor then fails to obey it.

N.Y. Lien Law 38

New York Public Works and Payment Bond Claims

Notice of Lien for Public Improvement

Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, and laborers on public improvements
When
At any time before completion and acceptance of the improvement, or within 30 days after it is completed and accepted
Served on or filed with
Filed with the head of the department or bureau in charge and with the comptroller or financial officer who pays the funds
Notarization
Verified by the lienor or its agent
  • A copy must be served on the contracting party by certified mail within 5 days before or simultaneously with filing, with proof on or accompanying the notice, or the notice is a nullity (Lien Law 11-c).
  • The lien reaches unpaid public funds, not public land. A claimant may demand notice of completion and acceptance, but the agency's failure does not extend the deadline (Lien Law 11-a).

N.Y. Lien Law 5, 11-c, 12

Foreclosure of Public Improvement Lien

Required When It Applies
Who uses it
Public improvement lienors
When
Within 1 year after the lien is filed, unless extended
Served on or filed with
Filed in court, with the notice of pendency filed with the comptroller or financial officer; an extension is filed in the same office
Notarization
Not required
  • The first extension lasts 1 year from its filing; later ones require a court order.

N.Y. Lien Law 18, 42

Notice of Claim on Public Payment Bond

Required When It Applies
Who uses it
Claimants that contracted with a subcontractor but not with the prime contractor on state public works
When
Within 120 days after the last labor or materials for which the claim is made
Served on or filed with
The prime contractor, personally or by registered mail to its business or residence address
Notarization
Not required
  • The notice states the amount claimed with substantial accuracy and the party supplied. A bond cannot impose more onerous notice conditions than the statute.

N.Y. State Fin. Law 137(3)

Action on Public Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded state public works
When
After 90 days from the claimant's last furnishing without full payment, and within 1 year after the public improvement is completed and accepted
Served on or filed with
Filed in the proper court against the surety and other appropriate defendants
Notarization
Not required
  • Bond copies are open to public inspection at the department and comptroller's offices; obtain the bond before calendaring deadlines.

N.Y. State Fin. Law 137(2), (4)

Frequently Asked Questions

Is there a statutory mechanics lien form in New York?

No fixed form. Lien Law 9 lists what the notice of lien must contain, including the lienor, owner, hiring party, labor or materials, amount unpaid, first and last dates, property description, and single-family status. Lien Law 10 requires the notice to be verified.

Does a New York mechanics lien have to be notarized?

The notice of lien must be verified by the lienor or its agent (Lien Law 9, 10), which in practice means a sworn statement before a notary. A certificate satisfying or releasing a lien must be acknowledged or proved (Lien Law 19).

Where do I file a mechanics lien in New York?

File the notice of lien with the county clerk of each county where the property lies, within 8 months after last furnishing, or 4 months for a single-family dwelling (Lien Law 10). Serve the owner and contractor and file proof of service within 35 days (Lien Law 11, 11-b).

How do I extend a New York mechanics lien?

Before the 1-year term expires, file one extension with the county clerk; it lasts 1 year from its filing. Further extensions require a court order, and a single-family dwelling lien can be extended only by court order (Lien Law 17).

What form releases a mechanics lien in New York?

A paid lienor files an acknowledged certificate of satisfaction or release where the lien was filed (Lien Law 19(1)). An owner or contractor can also discharge the lien with an undertaking of 110 percent of the lien or a deposit (Lien Law 19(4), 20).

Can a New York owner force me to foreclose sooner?

Yes. An owner may serve a notice to commence action, giving at least 30 days after service. If you do not sue in time, the court may cancel the lien (Lien Law 59).

What form do I use for a New York public project bond claim?

There is no prescribed form. A claimant hired by a subcontractor serves the prime contractor with written notice within 120 days after last furnishing, stating the amount and party supplied. Suit is due within 1 year after completion and acceptance (State Finance Law 137).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us