HomeNorth CarolinaMechanics Lien Forms
North Carolina Mechanics Lien Forms

North Carolina Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on North Carolina construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A North Carolina subcontractor usually needs three documents in order: a Notice to Lien Agent within 15 days after first furnishing, a Notice of Claim of Lien Upon Funds served on the obligors, and a Claim of Lien on Real Property filed within 120 days after last furnishing (N.C. Gen. Stat. §§ 44A-11.2, 44A-19, 44A-12).

The Claim of Lien on Real Property is filed with the clerk of superior court in each county where the property lies and served on the record owner. The statutory form includes a certificate of service. It does not require notarization or a sworn verification (N.C. Gen. Stat. §§ 44A-11, 44A-12).

The lien must be enforced by a civil action filed within 180 days after last furnishing. A notice of lis pendens is required within the same period in each other county where the property lies (N.C. Gen. Stat. § 44A-13). There is no owner demand procedure that shortens the 180 days.

Liens cannot attach to public property. On public projects, a claimant with no contract with the prime contractor must give the prime contractor a Notice of Claim on Payment Bond within 120 days after last furnishing, and should serve a Notice of Public Subcontract early to protect claims over $20,000 (N.C. Gen. Stat. § 44A-27).

North Carolina mechanics lien practice is governed by Chapter 44A of the General Statutes. Article 2 controls private projects, including the lien agent system, the Claim of Lien on Real Property, and the lien on funds. Article 3 controls payment bonds on public construction.

Several North Carolina documents have statutory forms that must be followed in substance, including the Notice to Lien Agent, the Notice of Claim of Lien Upon Funds, the Notice of Contract, the Notice of Subcontract, and the Claim of Lien on Real Property. The table below describes each document, who uses it, and when it is due. National Lien & Bond does not reproduce the statutory text on this page.

North Carolina Preliminary Notices

Notice to Lien Agent

Statutory Form
Required When It Applies
Who uses it
Contractors, subcontractors, and suppliers on projects where the owner has designated a lien agent
When
Received by the lien agent within 15 days after first furnishing; later notice can still protect the lien in some circumstances
Served on or filed with
The designated lien agent, by an authorized delivery method or through the lien agent website
Notarization
Not required
  • Notice received after 15 days still protects the lien if the lien agent receives it before a conveyance or deed of trust is recorded.
  • The claimant must cancel the notice within a reasonable time after confirmed final payment on a one- or two-family dwelling.

N.C. Gen. Stat. § 44A-11.2

Notice of Subcontract

Statutory Form
Optional
Who uses it
Second- and third-tier subcontractors on projects where a Notice of Contract has been filed and posted
When
Promptly after the Notice of Contract is posted; it protects against payments made after service
Served on or filed with
The contractor, by personal delivery or a method authorized for service of process
Notarization
Not required
  • Once served, the contractor must send a written Notice of Payment within five days after each later payment.

N.C. Gen. Stat. § 44A-23(b)

Notice of Claim of Lien Upon Funds

Statutory Form
Required When It Applies
Who uses it
First-, second-, and third-tier subcontractors and suppliers; a separate form applies to more remote subcontractors
When
No fixed deadline; serve as early as possible, because payments made before service reduce the funds available
Served on or filed with
Each obligor whose funds are targeted, such as the owner and higher-tier contractors, by personal delivery or a method authorized for service of process
Notarization
Not required
  • After service, the obligor must withhold funds up to the amount of the claim from further payment.
  • Ordinary mail is not an authorized service method for this notice.

N.C. Gen. Stat. §§ 44A-18, 44A-19, 44A-20

North Carolina Lien Claim and Service

Claim of Lien on Real Property

Statutory Form
Required When It Applies
Who uses it
Contractors in direct contract with the owner
When
After the obligation is due and no later than 120 days after last furnishing
Served on or filed with
Filed with the clerk of superior court in each county where the property lies and served on the record owner
Notarization
Not required; the form includes a certificate of service
  • A filed claim cannot be amended. To correct it, cancel the claim and file a substitute within the original filing period.

N.C. Gen. Stat. §§ 44A-11, 44A-12

Claim of Lien on Real Property by Subrogation

Statutory Form
Required When It Applies
Who uses it
First-, second-, and third-tier subcontractors asserting the contractor's lien by subrogation
When
Within 120 days after the claimant's last furnishing
Served on or filed with
Filed with the clerk of superior court; served on the record owner and the contractor through whom subrogation is claimed
Notarization
Not required
  • The claim uses the same statutory form and must identify the contractor through whom subrogation is asserted.

N.C. Gen. Stat. §§ 44A-12, 44A-23(a)

North Carolina Enforcing the Lien

Civil Action to Enforce Claim of Lien and Notice of Lis Pendens

Required When It Applies
Who uses it
Any lien claimant
When
Within 180 days after last furnishing
Served on or filed with
Filed in the court of proper venue; a notice of lis pendens is filed in each other county where the property lies
Notarization
Not required by Chapter 44A

N.C. Gen. Stat. § 44A-13

North Carolina Releasing or Bonding Off a Lien

Acknowledgment or Instrument of Satisfaction

Required When It Applies
Who uses it
Lien claimants who have been paid
When
Upon payment of the claim
Served on or filed with
The clerk of superior court where the claim of lien is filed
Notarization
Signed before the clerk, or an instrument signed and acknowledged by the claimant

N.C. Gen. Stat. § 44A-16(a)(1), (a)(2)

Cash Deposit or Surety Bond to Discharge Lien

Required When It Applies
Who uses it
Owners, contractors, or other interested parties seeking to clear a filed lien
When
At any time after the claim of lien is filed
Served on or filed with
Deposited with the clerk of superior court
Notarization
Not required
  • A cash deposit equals the amount of the claim; a corporate surety bond must equal 125 percent of the claim.

N.C. Gen. Stat. § 44A-16(a)(5), (a)(6)

North Carolina Owner Notices and Forms

Designation of Lien Agent

Required When It Applies
Who uses it
Owners of covered projects costing $40,000 or more, with exceptions for improvements to an existing owner-occupied single-family dwelling
When
No later than the owner's first contract for the improvement
Served on or filed with
Written notice to the registered lien agent; the agent's contact information is posted at the site with the building permit
Notarization
Not required

N.C. Gen. Stat. §§ 44A-11.1, 44A-11.2(d)

Notice of Contract

Statutory Form
Optional
Who uses it
Owners or contractors seeking protection against double payment
When
Filed and posted within 30 days after the building permit issues or the contract is awarded, whichever is later
Served on or filed with
Filed with the clerk of superior court in each county where the property lies and posted at the site
Notarization
Not required
  • A Notice of Contract that is filed but not posted does not secure the statutory protection.

N.C. Gen. Stat. § 44A-23(b)

North Carolina Public Works and Payment Bond Claims

Notice of Public Subcontract

Statutory Form
Required When It Applies
Who uses it
Claimants on public projects with no contract with the prime contractor
When
Promptly after first furnishing; for claims over $20,000, the excess cannot include work furnished more than 75 days before service
Served on or filed with
The prime contractor or its designated agent, by certified mail, signature confirmation, or a method authorized for service of process
Notarization
Not required

N.C. Gen. Stat. § 44A-27(b), (e)

Notice of Claim on Payment Bond

Required When It Applies
Who uses it
Claimants on public projects with a contract with a subcontractor but no contract with the prime contractor
When
Within 120 days after the claimant's last furnishing
Served on or filed with
The prime contractor or its designated agent, by certified mail, signature confirmation, or a method authorized for service of process
Notarization
Not required
  • The notice must state with substantial accuracy the amount claimed and the person for whom the work was performed.

N.C. Gen. Stat. § 44A-27(b), (c)

Action on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public projects
When
After 90 days without payment following last furnishing, and within 1 year after the later of last furnishing or final settlement with the contractor
Served on or filed with
Filed in the county where the contract or any part of it was performed
Notarization
Not required
  • A claimant may request a copy of the payment bond from the prime contractor, who must send it within seven calendar days.

N.C. Gen. Stat. §§ 44A-27, 44A-28, 44A-31

Frequently Asked Questions

Is there a statutory mechanics lien form in North Carolina?

Yes. Chapter 44A prescribes the substance of the Claim of Lien on Real Property, the Notice to Lien Agent, the Notice of Claim of Lien Upon Funds, the Notice of Contract, the Notice of Subcontract, and the Notice of Public Subcontract (N.C. Gen. Stat. §§ 44A-11.2, 44A-12, 44A-19, 44A-23, 44A-27). Each must substantially follow its statutory form.

Does a North Carolina mechanics lien have to be notarized?

No. The statutory Claim of Lien on Real Property form includes a certificate of service but does not require notarization or a sworn verification (N.C. Gen. Stat. § 44A-12). An affidavit is required only in special cases, such as a lien claim based on an owner's payment in violation of a lien on funds notice (N.C. Gen. Stat. § 44A-20(d)).

Where do I file a mechanics lien in North Carolina?

File the Claim of Lien on Real Property with the clerk of superior court in each county where the property is located, after the debt is due and within 120 days after last furnishing. The claim must also be served on the record owner (N.C. Gen. Stat. §§ 44A-11, 44A-12).

Who must send a Notice to Lien Agent in North Carolina?

Potential lien claimants on projects where the owner has designated a lien agent should serve a Notice to Lien Agent so it is received within 15 days after first furnishing. Later notice can still protect the lien against a sale or loan if the agent receives it before that conveyance or deed of trust is recorded (N.C. Gen. Stat. § 44A-11.2).

What form releases a mechanics lien in North Carolina?

A paid claimant may acknowledge satisfaction before the clerk of superior court, or sign and acknowledge an instrument of satisfaction that the owner presents to the clerk. A lien can also be discharged by a cash deposit equal to the claim or a surety bond for 125 percent of the claim (N.C. Gen. Stat. § 44A-16).

Can an owner force me to sue on my North Carolina lien early?

No. Article 2 has no owner demand procedure that shortens the 180-day period to enforce a Claim of Lien on Real Property. The 30-day demand procedure in N.C. Gen. Stat. § 44A-24.10 applies only to commercial real estate broker liens, not construction liens (N.C. Gen. Stat. § 44A-13).

What form do I use for a North Carolina public project bond claim?

A claimant with no contract with the prime contractor serves a written Notice of Claim on Payment Bond on the prime contractor within 120 days after last furnishing, stating the amount and the party supplied. A Notice of Public Subcontract served early protects claims over $20,000. Suit follows the waiting period in N.C. Gen. Stat. §§ 44A-27 and 44A-28.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.