Every notice, lien, enforcement, release, and bond claim document used on Ohio construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Ohio subcontractor usually needs three documents in order: a Notice of Furnishing served within 21 days after first furnishing where a Notice of Commencement is recorded, a sworn Affidavit for Mechanic's Lien recorded within 75 days after last furnishing, and a copy of the affidavit served on the owner within 30 days (R.C. 1311.05, 1311.06, 1311.07).

The lien affidavit deadline is 60 days for a one- or two-family dwelling or residential condominium unit and 120 days for qualifying oil and gas work. The affidavit must be sworn; the statutory sample in R.C. 1311.06(C) is permissive, not mandatory (R.C. 1311.06).

The lien continues 6 years after the affidavit is filed (R.C. 1311.13(C)). If the owner or another interested party serves a notice to commence suit, the claimant must sue within 60 days after service is completed. A lien can be discharged by court-approved bond of 200 or 150 percent of the claim (R.C. 1311.11).

Liens cannot attach to public property. On public improvements, a claimant may serve a sworn affidavit on the public authority within 120 days after last furnishing to claim contract funds (R.C. 1311.26), or furnish the surety a statement of the amount due within 90 days after acceptance to preserve bond rights (R.C. 153.56).

Ohio mechanics liens are governed by R.C. Chapter 1311. Liens on public improvement funds are governed by R.C. 1311.25 to 1311.32, and payment bonds on public improvements by R.C. 153.54 to 153.57. R.C. 4113.62 adds important limits on construction contract terms.

Ohio prescribes the substance of the Notice of Commencement, the Notice of Furnishing, and the public bond forms, and supplies a permissive sample Affidavit for Mechanic's Lien. H.B. 96, effective September 30, 2025, changed the Notice of Commencement. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Ohio Preliminary Notices

Notice of Furnishing

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers without a direct contract with the owner, on projects with a recorded Notice of Commencement
When
Within 21 days after first furnishing; late service preserves furnishing from 21 days before service onward
Served on or filed with
The owner's designee, or the owner if none, and the original contractor unless the claimant contracts directly with it
Notarization
Not required
  • Not required of laborers, original contractors, claimants on home construction contracts, or where no compliant Notice of Commencement exists.
  • A claimant may request a copy of the Notice of Commencement, which must be supplied within 10 days.

R.C. 1311.04(D), 1311.05

Ohio Lien Claim and Service

Affidavit for Mechanic's Lien

Statutory Form
Notarized
Required When It Applies
Who uses it
Original contractors, subcontractors, suppliers, and laborers
When
Within 75 days after last furnishing; 60 days for a one- or two-family dwelling or residential condominium unit; 120 days for oil and gas work
Served on or filed with
Recorded with the county recorder of each county where the property lies
Notarization
Required; sworn
  • The affidavit states the amount due net of setoffs, the property, the contracting party, the owner if known, and the first and last dates of furnishing. The statutory sample is permissive.

R.C. 1311.06

Service Copy of Lien Affidavit

Required When It Applies
Who uses it
Every lien claimant
When
Within 30 days after the affidavit is filed; if service cannot be made, post it within the following 10 days
Served on or filed with
The owner, part owner, lessee, or designee; or posted conspicuously on the property
Notarization
Not required

R.C. 1311.07, 1311.19

Ohio Enforcing the Lien

Suit to Foreclose Mechanic's Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 6 years after the affidavit is filed, or within 60 days after completed service of a notice to commence suit
Served on or filed with
Filed in the court of common pleas against the owner and other interested parties
Notarization
Not required by Chapter 1311

R.C. 1311.11, 1311.13(C), 1311.16

Ohio Releasing or Bonding Off a Lien

Release of Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 30 days after the claim is satisfied or the lien is adjudicated invalid
Served on or filed with
Recorded with the county recorder
Notarization
Acknowledgment may be required for recording
  • On residential projects, an owner who has paid in full may demand a release, which is due within 30 days after receipt.

R.C. 1311.20, 1311.011(B)(3)

Application for Substitute Bond or Security

Required When It Applies
Who uses it
Owners or other parties seeking to clear a lien
When
Before or after an enforcement suit is filed
Served on or filed with
Filed in the court of common pleas, with notice of hearing to the lienholder
Notarization
Not required
  • The bond is 200 percent of claims up to $5,000 and 150 percent of claims over $5,000. The court's approval entry discharges the lien.

R.C. 1311.11(C)

Ohio Owner Notices and Forms

Notice of Commencement

Statutory Form
Notarized
Required When It Applies
Who uses it
Owners, part owners, or lessees who contract for the improvement
When
Recorded before work or materials are first furnished; posted at the site during the work
Served on or filed with
Recorded with the county recorder of each county, with a copy to the original contractor
Notarization
Required; affidavit
  • Since September 30, 2025, the notice expires after four years unless it states otherwise, and an owner may record an affidavit of completion.
  • Home construction contracts are generally exempt.

R.C. 1311.04

Notice to Commence Suit

Optional
Who uses it
Owners, lessees, mortgagees, other interest holders, and qualifying bonded contractors
When
At any time after the lien is filed; the claimant must sue within 60 days after service is completed
Served on or filed with
Served on the lienholder through the statutory sheriff-service procedure; a service affidavit is recorded within 30 days
Notarization
Service affidavit required

R.C. 1311.11(A), (B)

Residential Payment Affidavits

Optional
Who uses it
Owners and original contractors on home construction and home purchase contracts
When
The owner's affidavit of full payment is recorded after full payment; the contractor's payment affidavit is given before each lender disbursement
Served on or filed with
The owner's affidavit is recorded with the county recorder; the contractor's affidavit is given to the lender
Notarization
Affidavit required

R.C. 1311.011(B)

Ohio Public Works and Payment Bond Claims

Public Notice of Furnishing

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers on public improvements without a contract with the principal contractor
When
Within 21 days after first furnishing at the site; late notice preserves furnishing from 21 days before service onward
Served on or filed with
The principal contractor
Notarization
Not required
  • For bond rights, the requirement applies to non-privity claimants furnishing more than $30,000.

R.C. 1311.261, 153.56(C)

Affidavit of Claim on Public Improvement Funds

Required When It Applies
Who uses it
Subcontractors, suppliers, and laborers on public improvements
When
During performance and no later than 120 days after last furnishing; record a copy within 30 days after service
Served on or filed with
Served on the public authority's representative named in the public notice of commencement; a copy is recorded with the county recorder and sent to the subcontractor supplied
Notarization
Affidavit required
  • The principal contractor has 20 days after receiving a copy to dispute the claim.

R.C. 1311.26, 1311.29, 1311.31

Statement of Amount Due to Surety

Required When It Applies
Who uses it
Unpaid claimants on bonded public improvements
When
No later than 90 days after completion of the contract and acceptance by the public authority
Served on or filed with
The sureties on the bond
Notarization
Not required

R.C. 153.56(A)

Action on Payment Bond

Required When It Applies
Who uses it
Claimants who furnished a timely statement to the surety
When
No earlier than 60 days after furnishing the statement and no later than 1 year after acceptance of the improvement
Served on or filed with
Filed in a court with jurisdiction against the surety
Notarization
Not required

R.C. 153.56(B)

Frequently Asked Questions

Is there a statutory mechanics lien form in Ohio?

Ohio lists the required contents of the Affidavit for Mechanic's Lien and supplies a permissive sample form (R.C. 1311.06). The Notice of Commencement and Notice of Furnishing must substantially follow statutory forms (R.C. 1311.04, 1311.05).

Does an Ohio mechanics lien have to be notarized?

Yes. The Affidavit for Mechanic's Lien must be sworn (R.C. 1311.06). The Notice of Furnishing does not require an oath. A Notice of Commencement on a private project is also an affidavit (R.C. 1311.04).

Where do I file a mechanics lien in Ohio?

Record the Affidavit for Mechanic's Lien with the county recorder of each county where the property lies, within 75 days after last furnishing, or 60 days for a one- or two-family dwelling or residential condominium unit. Serve a copy on the owner within 30 days after filing (R.C. 1311.06, 1311.07).

Who must serve an Ohio Notice of Furnishing?

Subcontractors and suppliers without a direct contract with the owner, on projects with a recorded Notice of Commencement, within 21 days after first furnishing. Laborers and claimants on home construction contracts are exempt, and a claimant in direct contract with the original contractor need not serve that contractor (R.C. 1311.05).

What form releases a mechanics lien in Ohio?

The lienholder must record a release within 30 days after the claim is satisfied or the lien is adjudicated invalid (R.C. 1311.20). An owner can also clear a lien by court-approved bond of 200 percent of claims up to $5,000 or 150 percent above $5,000 (R.C. 1311.11(C)).

Can an Ohio owner force me to sue on my lien early?

Yes. An owner, lessee, mortgagee, or other interested party may serve a notice to commence suit through the statutory sheriff-service procedure. The claimant must then sue within 60 days after service is completed, or the lien is void (R.C. 1311.11).

What form do I use for an Ohio public project bond claim?

Furnish the surety a statement of the amount due no later than 90 days after the public authority accepts the improvement, then sue no earlier than 60 days after the statement and within 1 year after acceptance (R.C. 153.56). A separate sworn affidavit claims the contract funds (R.C. 1311.26).