Quick Answer
An Oklahoma subcontractor usually needs three documents in order: a Pre-Lien Notice sent within 75 days after last furnishing, a verified Lien Statement filed within 90 days after last furnishing, and a notarized affidavit of Pre-Lien Notice compliance filed with the lien (42 O.S. §§ 142.6, 143).
The Pre-Lien Notice goes to the original contractor and an owner before the lien is filed. It is not required for claims under $10,000 or for non-owner-occupied residential projects of four or fewer units, but it is always required on an owner-occupied dwelling (42 O.S. § 142.6).
An original contractor files a verified Lien Statement with the county clerk within 4 months after last furnishing (42 O.S. § 142). The clerk mails notice of the filed lien to the owner within 5 business days, and the claimant must sue to foreclose within 1 year after filing (42 O.S. §§ 143.1, 172).
Liens cannot attach to public property. On public contracts over $100,000, a claimant with no contract with the bonded contractor gives written notice to the contractor and surety within 90 days after last furnishing. Suit is due within 1 year after last furnishing, or 2 years if a claim was filed within the first year (61 O.S. § 2).
Oklahoma mechanics and materialmen's liens are governed by Title 42 of the Oklahoma Statutes, sections 141 and following. Payment bonds on public works are governed by 61 O.S. §§ 1 and 2.
Oklahoma statutes prescribe the content of the Pre-Lien Notice and the Lien Statement rather than full fill-in forms. One owner document, the affidavit of cancellation of an expired lien, uses a form prescribed by the Administrative Director of the Courts. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
Oklahoma Preliminary Notices
Pre-Lien Notice
- Who uses it
- Subcontractors, suppliers, and other claimants without a direct contract with the owner
- When
- Before the lien is filed and no later than 75 days after last furnishing
- Served on or filed with
- The original contractor and an owner, by certified mail, hand delivery with receipt, or a qualifying automated transaction
- Notarization
- Not required for the notice itself
- The statute lists the required content, and the notice must identify itself as a pre-lien notice.
- Exempt: claims under $10,000 and non-owner-occupied residential projects of four or fewer units. Always required on an owner-occupied dwelling.
- If the original contractor does not answer a written request for the owner's name and address within five days, the owner-notice requirement cannot be enforced.
42 O.S. § 142.6
Oklahoma Lien Claim and Service
Lien Statement (Original Contractor)
- Who uses it
- Contractors in direct contract with the owner
- When
- Within 4 months after last furnishing labor, materials, or equipment
- Served on or filed with
- Filed with the county clerk of the county where the land lies
- Notarization
- Verified by affidavit
- The claimant supplies the owner's last known mailing address, and the county clerk mails notice of the filed lien to the owner within 5 business days.
42 O.S. §§ 142, 143.1
Lien Statement (Subcontractor and Supplier)
- Who uses it
- Subcontractors, suppliers, equipment lessors, and laborers
- When
- Within 90 days after last furnishing under the subcontract
- Served on or filed with
- Filed with the county clerk of the county where the land lies
- Notarization
- Verified by affidavit
42 O.S. §§ 143, 143.1
Affidavit of Pre-Lien Notice Compliance
- Who uses it
- Claimants required to send a Pre-Lien Notice
- When
- Filed with the Lien Statement
- Served on or filed with
- The county clerk
- Notarization
- Required
42 O.S. § 142.6(C)
Due Diligence Affidavit and Substitute Notice
- Who uses it
- Claimants who cannot locate the owner or another person to be notified
- When
- Substitute service or posting within 60 days after the lien is filed
- Served on or filed with
- The affidavit is filed with the county clerk; notice is served on the occupant or posted on unoccupied property
- Notarization
- Affidavit required
42 O.S. § 143.1(B)
Oklahoma Enforcing the Lien
Petition to Foreclose Lien
- Who uses it
- Lien claimants
- When
- Within 1 year after the Lien Statement is filed
- Served on or filed with
- Filed in the district court of the county where the land lies
- Notarization
- Not required
- Filed lienholders and, in a subcontractor's action, the original contractor must be joined.
42 O.S. §§ 172, 173
Oklahoma Releasing or Bonding Off a Lien
Release of Lien
- Who uses it
- Lienholders who have been paid or have settled
- When
- Upon payment or settlement
- Served on or filed with
- Filed with the county clerk where the lien is filed
- Notarization
- Not required for a corporate release signed by an officer or agent
- No fixed statutory deadline to release a paid lien was confirmed.
42 O.S. § 154
Cash Deposit or Surety Bond to Discharge Lien
- Who uses it
- Owners, lenders, contractors, or other interested parties
- When
- At any time after the lien is filed
- Served on or filed with
- Deposited with the county clerk where the lien is filed; the clerk mails notice to the claimant within three business days
- Notarization
- Not required
- The deposit or bond must equal 125 percent of the lien claim.
- The claimant has 10 days after the clerk's notice is mailed to object to the bond.
42 O.S. § 147.1
Oklahoma Owner Notices and Forms
Owner's Petition to Adjudicate Lien
- Who uses it
- Landowners
- When
- After the lien is filed, when no foreclosure has begun
- Served on or filed with
- Filed in the district court where the land lies, naming the lien claimants as defendants
- Notarization
- Not required
42 O.S. § 177
Affidavit of Cancellation of Lien by Limitation
- Who uses it
- Landowners clearing an expired lien
- When
- After 1 year passes with no foreclosure or adjudication action instituted
- Served on or filed with
- Filed with the county clerk and attached to the original lien
- Notarization
- Affidavit required
42 O.S. § 177
Oklahoma Public Works and Payment Bond Claims
Notice to Contractor and Surety on Public Works Bond
- Who uses it
- Claimants with a contract with a subcontractor at any tier but no contract with the bonded contractor
- When
- Within 90 days after the claimant's last furnishing
- Served on or filed with
- The contractor and the surety, by registered or certified mail
- Notarization
- Not required
- Where a construction manager at risk or trade contractor furnishes the bond, only parties in direct contract with that bonded party may sue.
61 O.S. § 2(B)
Claim and Action on Public Works Payment Bond
- Who uses it
- Unpaid claimants on public contracts over $100,000
- When
- Suit within 1 year after last furnishing, or within 2 years after last furnishing if a claim was filed within the first year
- Served on or filed with
- The claim is presented to the contractor and surety; suit is filed in a court of proper venue
- Notarization
- Not required
- The officer holding the bond must furnish a copy on request.
61 O.S. §§ 1, 2(A)
Frequently Asked Questions
Is there a statutory mechanics lien form in Oklahoma?
No full fill-in form exists. Oklahoma statutes list what the Pre-Lien Notice and the Lien Statement must contain, and the Lien Statement must be verified by affidavit (42 O.S. §§ 142, 142.6, 143). The owner's affidavit of cancellation of an expired lien is the one document on a prescribed form (42 O.S. § 177).
Does an Oklahoma mechanics lien have to be notarized?
Yes. The Lien Statement must be verified by affidavit, and a claimant subject to the Pre-Lien Notice requirement must also file a notarized affidavit verifying compliance with the Lien Statement (42 O.S. §§ 142, 143, 142.6(C)).
Where do I file a mechanics lien in Oklahoma?
File the verified Lien Statement with the county clerk of the county where the land lies: within 4 months after last furnishing for an original contractor, or within 90 days for a subcontractor or supplier. The clerk mails notice to the owner within 5 business days (42 O.S. §§ 142, 143, 143.1).
When is an Oklahoma Pre-Lien Notice not required?
It is not required for an aggregate claim under $10,000, for a non-owner-occupied residential project of four or fewer units, or for agreed retainage. It is always required on property occupied as a dwelling by an owner (42 O.S. § 142.6). One notice covers later furnishing on the same project.
What form releases a mechanics lien in Oklahoma?
A paid lienholder files a written release with the county clerk; a corporation may sign through an officer or agent without acknowledgment or seal (42 O.S. § 154). A disputed lien can be discharged by a cash deposit or surety bond equal to 125 percent of the claim (42 O.S. § 147.1).
Can an Oklahoma owner force a claimant to sue sooner?
Oklahoma has no notice that shortens the 1-year foreclosure period. An owner may instead petition the district court to adjudicate the lien, or after 1 year without suit file an affidavit of cancellation on the prescribed form (42 O.S. §§ 172, 177).
What form do I use for an Oklahoma public project bond claim?
A claimant with no contract with the bonded contractor sends written notice to the contractor and surety by registered or certified mail within 90 days after last furnishing, stating the amount and the party supplied. Suit is due within 1 year, or 2 years if a claim was filed within the first year (61 O.S. § 2).
Related Oklahoma Resources
Oklahoma Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Oklahoma Notice Requirements
Who must give notice, when, and how.
Oklahoma Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Oklahoma Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Oklahoma law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.