HomeOklahomaMechanics Lien Forms
Oklahoma Mechanics Lien Forms

Oklahoma Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Oklahoma construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Oklahoma subcontractor usually needs three documents in order: a Pre-Lien Notice sent within 75 days after last furnishing, a verified Lien Statement filed within 90 days after last furnishing, and a notarized affidavit of Pre-Lien Notice compliance filed with the lien (42 O.S. §§ 142.6, 143).

The Pre-Lien Notice goes to the original contractor and an owner before the lien is filed. It is not required for claims under $10,000 or for non-owner-occupied residential projects of four or fewer units, but it is always required on an owner-occupied dwelling (42 O.S. § 142.6).

An original contractor files a verified Lien Statement with the county clerk within 4 months after last furnishing (42 O.S. § 142). The clerk mails notice of the filed lien to the owner within 5 business days, and the claimant must sue to foreclose within 1 year after filing (42 O.S. §§ 143.1, 172).

Liens cannot attach to public property. On public contracts over $100,000, a claimant with no contract with the bonded contractor gives written notice to the contractor and surety within 90 days after last furnishing. Suit is due within 1 year after last furnishing, or 2 years if a claim was filed within the first year (61 O.S. § 2).

Oklahoma mechanics and materialmen's liens are governed by Title 42 of the Oklahoma Statutes, sections 141 and following. Payment bonds on public works are governed by 61 O.S. §§ 1 and 2.

Oklahoma statutes prescribe the content of the Pre-Lien Notice and the Lien Statement rather than full fill-in forms. One owner document, the affidavit of cancellation of an expired lien, uses a form prescribed by the Administrative Director of the Courts. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Oklahoma Preliminary Notices

Pre-Lien Notice

Required When It Applies
Who uses it
Subcontractors, suppliers, and other claimants without a direct contract with the owner
When
Before the lien is filed and no later than 75 days after last furnishing
Served on or filed with
The original contractor and an owner, by certified mail, hand delivery with receipt, or a qualifying automated transaction
Notarization
Not required for the notice itself
  • The statute lists the required content, and the notice must identify itself as a pre-lien notice.
  • Exempt: claims under $10,000 and non-owner-occupied residential projects of four or fewer units. Always required on an owner-occupied dwelling.
  • If the original contractor does not answer a written request for the owner's name and address within five days, the owner-notice requirement cannot be enforced.

42 O.S. § 142.6

Oklahoma Lien Claim and Service

Lien Statement (Original Contractor)

Required When It Applies
Who uses it
Contractors in direct contract with the owner
When
Within 4 months after last furnishing labor, materials, or equipment
Served on or filed with
Filed with the county clerk of the county where the land lies
Notarization
Verified by affidavit
  • The claimant supplies the owner's last known mailing address, and the county clerk mails notice of the filed lien to the owner within 5 business days.

42 O.S. §§ 142, 143.1

Lien Statement (Subcontractor and Supplier)

Required When It Applies
Who uses it
Subcontractors, suppliers, equipment lessors, and laborers
When
Within 90 days after last furnishing under the subcontract
Served on or filed with
Filed with the county clerk of the county where the land lies
Notarization
Verified by affidavit

42 O.S. §§ 143, 143.1

Affidavit of Pre-Lien Notice Compliance

Notarized
Required When It Applies
Who uses it
Claimants required to send a Pre-Lien Notice
When
Filed with the Lien Statement
Served on or filed with
The county clerk
Notarization
Required

42 O.S. § 142.6(C)

Due Diligence Affidavit and Substitute Notice

Optional
Who uses it
Claimants who cannot locate the owner or another person to be notified
When
Substitute service or posting within 60 days after the lien is filed
Served on or filed with
The affidavit is filed with the county clerk; notice is served on the occupant or posted on unoccupied property
Notarization
Affidavit required

42 O.S. § 143.1(B)

Oklahoma Enforcing the Lien

Petition to Foreclose Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 1 year after the Lien Statement is filed
Served on or filed with
Filed in the district court of the county where the land lies
Notarization
Not required
  • Filed lienholders and, in a subcontractor's action, the original contractor must be joined.

42 O.S. §§ 172, 173

Oklahoma Releasing or Bonding Off a Lien

Release of Lien

Required When It Applies
Who uses it
Lienholders who have been paid or have settled
When
Upon payment or settlement
Served on or filed with
Filed with the county clerk where the lien is filed
Notarization
Not required for a corporate release signed by an officer or agent
  • No fixed statutory deadline to release a paid lien was confirmed.

42 O.S. § 154

Cash Deposit or Surety Bond to Discharge Lien

Required When It Applies
Who uses it
Owners, lenders, contractors, or other interested parties
When
At any time after the lien is filed
Served on or filed with
Deposited with the county clerk where the lien is filed; the clerk mails notice to the claimant within three business days
Notarization
Not required
  • The deposit or bond must equal 125 percent of the lien claim.
  • The claimant has 10 days after the clerk's notice is mailed to object to the bond.

42 O.S. § 147.1

Oklahoma Owner Notices and Forms

Owner's Petition to Adjudicate Lien

Optional
Who uses it
Landowners
When
After the lien is filed, when no foreclosure has begun
Served on or filed with
Filed in the district court where the land lies, naming the lien claimants as defendants
Notarization
Not required

42 O.S. § 177

Affidavit of Cancellation of Lien by Limitation

Statutory Form
Optional
Who uses it
Landowners clearing an expired lien
When
After 1 year passes with no foreclosure or adjudication action instituted
Served on or filed with
Filed with the county clerk and attached to the original lien
Notarization
Affidavit required

42 O.S. § 177

Oklahoma Public Works and Payment Bond Claims

Notice to Contractor and Surety on Public Works Bond

Required When It Applies
Who uses it
Claimants with a contract with a subcontractor at any tier but no contract with the bonded contractor
When
Within 90 days after the claimant's last furnishing
Served on or filed with
The contractor and the surety, by registered or certified mail
Notarization
Not required
  • Where a construction manager at risk or trade contractor furnishes the bond, only parties in direct contract with that bonded party may sue.

61 O.S. § 2(B)

Claim and Action on Public Works Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on public contracts over $100,000
When
Suit within 1 year after last furnishing, or within 2 years after last furnishing if a claim was filed within the first year
Served on or filed with
The claim is presented to the contractor and surety; suit is filed in a court of proper venue
Notarization
Not required
  • The officer holding the bond must furnish a copy on request.

61 O.S. §§ 1, 2(A)

Frequently Asked Questions

Is there a statutory mechanics lien form in Oklahoma?

No full fill-in form exists. Oklahoma statutes list what the Pre-Lien Notice and the Lien Statement must contain, and the Lien Statement must be verified by affidavit (42 O.S. §§ 142, 142.6, 143). The owner's affidavit of cancellation of an expired lien is the one document on a prescribed form (42 O.S. § 177).

Does an Oklahoma mechanics lien have to be notarized?

Yes. The Lien Statement must be verified by affidavit, and a claimant subject to the Pre-Lien Notice requirement must also file a notarized affidavit verifying compliance with the Lien Statement (42 O.S. §§ 142, 143, 142.6(C)).

Where do I file a mechanics lien in Oklahoma?

File the verified Lien Statement with the county clerk of the county where the land lies: within 4 months after last furnishing for an original contractor, or within 90 days for a subcontractor or supplier. The clerk mails notice to the owner within 5 business days (42 O.S. §§ 142, 143, 143.1).

When is an Oklahoma Pre-Lien Notice not required?

It is not required for an aggregate claim under $10,000, for a non-owner-occupied residential project of four or fewer units, or for agreed retainage. It is always required on property occupied as a dwelling by an owner (42 O.S. § 142.6). One notice covers later furnishing on the same project.

What form releases a mechanics lien in Oklahoma?

A paid lienholder files a written release with the county clerk; a corporation may sign through an officer or agent without acknowledgment or seal (42 O.S. § 154). A disputed lien can be discharged by a cash deposit or surety bond equal to 125 percent of the claim (42 O.S. § 147.1).

Can an Oklahoma owner force a claimant to sue sooner?

Oklahoma has no notice that shortens the 1-year foreclosure period. An owner may instead petition the district court to adjudicate the lien, or after 1 year without suit file an affidavit of cancellation on the prescribed form (42 O.S. §§ 172, 177).

What form do I use for an Oklahoma public project bond claim?

A claimant with no contract with the bonded contractor sends written notice to the contractor and surety by registered or certified mail within 90 days after last furnishing, stating the amount and the party supplied. Suit is due within 1 year, or 2 years if a claim was filed within the first year (61 O.S. § 2).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us