HomeOregonMechanics Lien Forms
Oregon Mechanics Lien Forms

Oregon Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Oregon construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Oregon subcontractor or supplier usually needs four documents in order: a Notice of Right to a Lien, a verified claim of lien recorded within 75 days, a notice of filing mailed within 20 days after recording, and a notice of intent to foreclose given at least 10 days before suit (ORS 87.021, 87.035, 87.039, 87.057).

The Notice of Right to a Lien goes to the owner and protects work furnished from 8 business days before delivery. It is not required for labor, labor-and-material, or equipment rental claimants on commercial improvements, but material suppliers on commercial improvements must give it (ORS 87.021, 87.023).

On residential contracts over $2,000, the original contractor must deliver the CCB-adopted Information Notice to Owner About Construction Liens at signing; failure bars the contractor's lien (ORS 87.093). Suit to foreclose is due within 120 days after the claim of lien is recorded (ORS 87.055).

Liens cannot attach to public property. On public improvements, a claimant serves a signed Notice of Claim on the contractor and the contracting agency within 180 days after last furnishing, and sues on the bond within 2 years after last furnishing (ORS 279C.600, 279C.605, 279C.610).

Oregon construction liens are governed by ORS Chapter 87, sections 87.001 to 87.093. Claims on public improvement payment bonds are governed by ORS 279C.600 to 279C.625. The Construction Contractors Board adopts several consumer forms by rule.

Oregon prescribes the substance of the Notice of Right to a Lien, the completion and abandonment notices, and the public bond Notice of Claim. The claim of lien must be verified by oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Oregon Preliminary Notices

Information Notice to Owner About Construction Liens

Statutory Form
Required When It Applies
Who uses it
Original contractors on residential contracts over $2,000
When
At signing of the contract, or within five days after the contractor knows the price will exceed $2,000
Served on or filed with
The owner or the owner's agent, by personal delivery, registered or certified mail, or first-class mail with a certificate of mailing
Notarization
Not required
  • The form is adopted by the Construction Contractors Board by rule rather than printed in the statute.
  • Failure to deliver the notice bars the original contractor's lien. It is not required when the owner is a licensed contractor.

ORS 87.093; OAR 812-001-0200

Notice of Right to a Lien

Statutory Form
Required When It Applies
Who uses it
Subcontractors, suppliers, and equipment lessors who do not contract with the owner
When
During the project; it protects work furnished from 8 business days before delivery or mailing
Served on or filed with
The owner, personally or by registered or certified mail
Notarization
Not required
  • Not required for claimants furnishing at the owner's request, or for labor, labor-and-material, and equipment rental claimants on commercial improvements. Material suppliers on commercial improvements must still give it.
  • A material supplier may also notify a recorded mortgagee to protect its priority.

ORS 87.021, 87.023, 87.025

Oregon Lien Claim and Service

Claim of Lien

Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, laborers, and equipment lessors
When
Within 75 days after the claimant stops furnishing or 75 days after completion of construction, whichever is earlier
Served on or filed with
Recorded with the recording officer of each county where the property lies
Notarization
Verified by oath
  • The claim states the demand net of credits and offsets, the owner if known, the party that hired the claimant, and a sufficient property description.

ORS 87.035

Notice of Filing of Claim of Lien

Required When It Applies
Who uses it
Every lien claimant
When
Within 20 days after the claim of lien is recorded
Served on or filed with
The owner and any qualifying mortgagee, with a copy of the claim of lien attached
Notarization
Not required
  • Failure to give this notice forfeits otherwise recoverable costs, disbursements, and attorney fees.

ORS 87.039

Oregon Enforcing the Lien

Notice of Intent to Foreclose

Required When It Applies
Who uses it
Lien claimants preparing to sue
When
At least 10 days before filing suit
Served on or filed with
The owner and any qualifying mortgagee
Notarization
Not required
  • If the owner demands supporting information, the claimant must respond within five days. Noncompliance bars recovery of fees and costs.

ORS 87.057

Suit to Foreclose Construction Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 120 days after the claim of lien is recorded; if the claim states an extension of credit, within 120 days after the credit expires but no later than 2 years after recording
Served on or filed with
Filed in circuit court, joining the persons personally liable and other recorded lien claimants
Notarization
Not required

ORS 87.055, 87.060

Oregon Releasing or Bonding Off a Lien

Written Release of Lien

Required When It Applies
Who uses it
Lien claimants who have been paid or have settled
When
Upon payment or settlement
Served on or filed with
Recorded with the county recording officer, or presented to release substituted security
Notarization
Not required by Chapter 87

ORS 87.088(3)

Bond or Deposit to Release Lien

Required When It Applies
Who uses it
Owners or other interested persons
When
At any time after the claim of lien is filed; notice of the bond or deposit is served on the claimant within 20 days
Served on or filed with
A bond is filed with the county recording officer; money is deposited with the county treasurer
Notarization
Affidavit of service required
  • The security must be at least 150 percent of the lien or $1,000, whichever is greater.
  • Without timely notice to the claimant and the affidavit of service, the substitution is ineffective.

ORS 87.076, 87.078, 87.081

Oregon Owner Notices and Forms

Notice of Completion

Statutory Form
Optional
Who uses it
Owners, original contractors, mortgagees, or their agents, once all original contractors have substantially performed
When
Posted on the property and recorded within five days after posting
Served on or filed with
Posted conspicuously on the property and recorded in the county where it lies
Notarization
Affidavit of posting required
  • Notices of abandonment and nonabandonment follow the same posting and recording procedure.

ORS 87.045

Notice of Nonresponsibility

Optional
Who uses it
Landowners who did not contract for the improvement
When
Within three days after learning of the construction
Served on or filed with
Posted conspicuously on the land or improvement
Notarization
Not required

ORS 87.030

Notice of Compliance with Homebuyer Protection Act

Statutory Form
Required When It Applies
Who uses it
Sellers of covered new or recently improved residential property
When
No later than closing
Served on or filed with
The purchaser
Notarization
Not required

ORS 87.007; OAR 812-012-0140

Oregon Public Works and Payment Bond Claims

Notice of Claim on Public Works Payment Bond

Statutory Form
Required When It Applies
Who uses it
Unpaid claimants who furnished labor or materials on public improvements, and their assignees
When
Within 180 days after last furnishing; 200 days for required employee benefit plan contributions
Served on or filed with
The contractor and the contracting agency, by registered or certified mail or hand delivery
Notarization
Not required; the notice must be signed

ORS 279C.600, 279C.605

Action on Payment Bond or Public Works Bond

Required When It Applies
Who uses it
Claimants who served a timely Notice of Claim
When
Within 2 years after last furnishing
Served on or filed with
Filed in Oregon circuit court or a federal district court with jurisdiction, in the name of the contracting agency
Notarization
Not required

ORS 279C.610

Frequently Asked Questions

Is there a statutory mechanics lien form in Oregon?

Not for the claim of lien itself. ORS 87.035 lists what the claim must contain and requires it to be verified by oath. The Notice of Right to a Lien, the completion notice, and the public bond Notice of Claim must substantially follow statutory forms (ORS 87.023, 87.045, 279C.605).

Does an Oregon construction lien have to be notarized?

Yes, in effect. The claim of lien must be verified by the oath of the claimant or a person with knowledge of the facts (ORS 87.035). The preliminary notices and the notice of filing do not require an oath.

Where do I file a construction lien in Oregon?

Record the claim of lien with the recording officer of each county where the property lies, within 75 days after you stop furnishing or after completion, whichever is earlier. Then mail notice of the filing, with a copy of the lien, to the owner and mortgagee within 20 days (ORS 87.035, 87.039).

Who must send a Notice of Right to a Lien in Oregon?

Subcontractors, suppliers, and equipment lessors who do not contract with the owner. It is not required for claimants furnishing at the owner's request, or for labor, labor-and-material, and equipment rental claimants on commercial improvements. Material suppliers on commercial improvements must still give it (ORS 87.021).

What form releases a construction lien in Oregon?

A claimant may sign a written release of lien (ORS 87.088(3)). An owner can also free the property by filing a surety bond or depositing money of at least 150 percent of the lien or $1,000, whichever is greater, then serving notice and filing an affidavit of service (ORS 87.076 to 87.081).

Can an Oregon owner force me to foreclose sooner?

No. Oregon has no owner demand that shortens the 120-day foreclosure period. An owner may demand that a lien be released and warn that bonding costs may be recovered, but that demand does not change the foreclosure deadline (ORS 87.055, 87.076(4)).

What form do I use for an Oregon public project bond claim?

Serve a signed Notice of Claim, substantially in the statutory form, on the contractor and the contracting agency by registered or certified mail or hand delivery within 180 days after last furnishing. Suit on the bond is due within 2 years after last furnishing (ORS 279C.605, 279C.610).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us