Pennsylvania Mechanics Lien Forms

Pennsylvania Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Pennsylvania construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Pennsylvania subcontractor usually needs four documents in order: a Notice of Furnishing on Directory projects, a formal notice of intention to file a claim served at least 30 days before filing, the mechanics' lien claim filed within 6 months after completing its work, and a notice of filing served on the owner (49 P.S. §§ 1501, 1501.3, 1502).

The Notice of Furnishing applies only on projects of $1.5 million or more where the owner has filed and posted an optional Notice of Commencement in the State Construction Notices Directory. It is due within 45 days after first furnishing, and failure to file it can forfeit lien rights (49 P.S. § 1501.3).

After filing the claim with the prothonotary, serve written notice of the filing on the owner within one month, and file an affidavit or acceptance of service within 20 days after service (49 P.S. § 1502(a)(2)). File a complaint within 2 years and obtain a verdict or judgment within 5 years (49 P.S. § 1701).

Liens cannot attach to public property. On public works, a claimant with no contract with the prime gives it written notice within 90 days after last furnishing. Suit may begin after the 90-day waiting period and is due within 1 year after it expires (8 P.S. § 194; Centre Concrete Co. v. AGI, Inc., 559 A.2d 516 (Pa. 1989)).

Pennsylvania mechanics liens are governed by the Mechanics' Lien Law of 1963, 49 P.S. § 1101 and following, including the State Construction Notices Directory provisions added in 2014. Payment bonds on public works are governed by the Public Works Contractors' Bond Law of 1967, 8 P.S. § 191 and following.

Most Pennsylvania lien documents have required content rather than a verbatim statutory form. The Notice of Furnishing is the main exception. The old preliminary notice for alteration and repair work was repealed effective January 1, 2007. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Pennsylvania Preliminary Notices

Notice of Furnishing

Statutory Form
Required When It Applies
Who uses it
Subcontractors on searchable projects of $1.5 million or more where a Notice of Commencement has been filed and posted
When
Within 45 days after first performing work or furnishing materials at the site
Served on or filed with
Filed in the State Construction Notices Directory
Notarization
Not required; the filer verifies accuracy
  • Failure to file can forfeit lien rights unless the failure resulted from unlawful interference prohibited by statute.

49 P.S. §§ 1501.3(b), (c), 1501.6

Pennsylvania Notices Before Filing a Lien

Formal Notice of Intention to File a Claim

Required When It Applies
Who uses it
Subcontractors; not required of a contractor in direct contract with the owner
When
At least 30 days before filing the claim, and within the 6-month filing period
Served on or filed with
The owner or the owner's agent, by first-class, registered, or certified mail, by personal service, or by posting if service cannot be made
Notarization
Not required
  • The notice states the claimant, the contracting party, the amount, the work, the completion date, and the property.
  • Not required for a claim filed in response to an owner's rule to file claim.

49 P.S. § 1501(b.1), (c), (d)

Pennsylvania Lien Claim and Service

Mechanics' Lien Claim

Required When It Applies
Who uses it
Contractors and subcontractors
When
Within 6 months after the claimant completes its own work
Served on or filed with
Filed with the prothonotary of each county where the improvement is located
Notarization
Not required by the lien statute
  • The statute prescribes the claim's content. A filed claim cannot later be amended to add property, change the contracting party, or increase the amount after the filing period.

49 P.S. §§ 1502, 1503, 1504

Notice of Filing of Claim

Required When It Applies
Who uses it
Every lien claimant
When
Within one month after the claim is filed
Served on or filed with
The owner, by an adult in the manner of service of a writ of summons, or by posting if service cannot be made
Notarization
Not required
  • Ordinary mail is not a permitted method of service for this notice.

49 P.S. § 1502(a)(2), (c)

Affidavit of Service or Acceptance of Service

Required When It Applies
Who uses it
Every lien claimant
When
Within 20 days after service of the notice of filing
Served on or filed with
Filed with the prothonotary in the lien proceeding
Notarization
Oath or unsworn verification under 18 Pa.C.S. § 4904

49 P.S. § 1502(a)(2)

Pennsylvania Enforcing the Lien

Complaint to Obtain Judgment on Claim

Required When It Applies
Who uses it
Lien claimants
When
Within 2 years after the claim is filed, unless the owner extends the time in writing; verdict or judgment within 5 years after filing
Served on or filed with
Filed in the same court and docket as the claim and served under the civil rules
Notarization
Verification required for factual allegations
  • An owner may shorten the time by a rule to file complaint, which requires the complaint within 20 days after service of the rule.

49 P.S. § 1701; Pa.R.C.P. 1024, 1659

Pennsylvania Releasing or Bonding Off a Lien

Satisfaction of Claim

Required When It Applies
Who uses it
Lien claimants who have been paid
When
Upon payment or discharge, with costs paid; failure within 30 days after a written request allows a petition to compel
Served on or filed with
Entered of record with the prothonotary
Notarization
Not required
  • A court may order satisfaction and impose a penalty up to the amount of the claim.

49 P.S. § 1704

Petition to Discharge Lien by Deposit or Security

Required When It Applies
Who uses it
Owners or other parties in interest
When
At any time after the claim is filed
Served on or filed with
Filed with the court in the lien proceeding
Notarization
Verification of facts outside the record
  • Cash equals the amount of the claim. Approved security is ordinarily double the required deposit, which the court may reduce but not below the full deposit.
  • A separate discharge or reduction remedy is available for qualifying residential owners who have paid in full.

49 P.S. § 1510

Pennsylvania Owner Notices and Forms

Notice of Commencement

Optional
Who uses it
Owners of searchable projects costing $1.5 million or more, or an authorized contractor
When
Before work or materials are first furnished; the notice is also posted at the site through completion
Served on or filed with
Filed in the State Construction Notices Directory and posted conspicuously at the site
Notarization
Not required; the filer verifies accuracy

49 P.S. §§ 1201(18), 1501.3(a)

Notice of Completion

Optional
Who uses it
Owners of projects with a Notice of Commencement
When
Within 45 days after actual completion
Served on or filed with
Filed in the State Construction Notices Directory
Notarization
Not required
  • The notice is informational and does not shorten lien deadlines.

49 P.S. § 1501.4(a)

Rule to File Claim

Optional
Who uses it
Owners or contractors seeking to accelerate a subcontractor's claim
When
After the subcontractor completes its work; the claim is due 30 days after notice of the rule
Served on or filed with
Filed with the prothonotary where the claim could be filed, with notice to the subcontractor
Notarization
Not required

49 P.S. § 1506

Pennsylvania Public Works and Payment Bond Claims

Written Notice to Prime Contractor on Payment Bond

Required When It Applies
Who uses it
Claimants with a contract with a subcontractor but no contract with the prime contractor
When
Within 90 days after last furnishing labor or materials
Served on or filed with
The prime contractor at its regular business office, by registered or certified mail or by service in the manner of process
Notarization
Not required
  • Notice to the surety alone does not satisfy the statute.

8 P.S. § 194(b)

Action on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works
When
After the 90-day waiting period following last furnishing, and within 1 year after that period expires
Served on or filed with
Filed in court against the contractor and surety
Notarization
Verification required for factual allegations
  • A claimant may obtain certified copies of the bond and contract from the contracting body by application and affidavit.

8 P.S. §§ 194(a), 196; 42 Pa.C.S. § 5523(3)

Frequently Asked Questions

Is there a statutory mechanics lien form in Pennsylvania?

Not for the claim itself. 49 P.S. § 1503 lists what the mechanics' lien claim must contain, but it does not prescribe verbatim wording. The Notice of Furnishing filed in the State Construction Notices Directory is the main document with a substantially prescribed statutory form (49 P.S. § 1501.3).

Does a Pennsylvania mechanics lien have to be notarized?

The lien statute does not require an oath for the claim itself (49 P.S. § 1503). The affidavit of service requires an oath or an unsworn verification under 18 Pa.C.S. § 4904, and court pleadings require verification under Pa.R.C.P. 1024. Verification does not necessarily require a notary.

Where do I file a mechanics lien in Pennsylvania?

File the claim with the prothonotary of the county where the improvement is located, within 6 months after completing your work. Serve notice of the filing on the owner within one month, then file the affidavit of service within 20 days after service (49 P.S. § 1502).

Does Pennsylvania still have a preliminary notice for alteration and repair work?

No. The former preliminary notice for alteration and repair work under 49 P.S. § 1501(a) was deleted by Act 52 of 2006, effective January 1, 2007. Subcontractors now serve the formal 30-day notice of intention and, on Directory projects, file a Notice of Furnishing.

What form releases a mechanics lien in Pennsylvania?

A paid claimant enters satisfaction of the claim on the record. If the claimant fails to do so within 30 days after a written request, the court may order satisfaction and impose a penalty (49 P.S. § 1704). An owner may also petition to discharge the lien by deposit or security (49 P.S. § 1510).

Can a Pennsylvania owner shorten the time to enforce a lien?

Yes, in two ways. A rule to file claim requires a subcontractor to file its claim within 30 days after notice (49 P.S. § 1506). A rule to file complaint requires the claimant to file its enforcement complaint within 20 days after service (Pa.R.C.P. 1659).

What form do I use for a Pennsylvania public project bond claim?

A claimant with no contract with the prime contractor sends written notice to the prime within 90 days after last furnishing, by registered or certified mail, stating the amount and the party supplied. Suit is due within 1 year after the 90-day waiting period expires (8 P.S. § 194; Centre Concrete Co. v. AGI, Inc., 559 A.2d 516 (Pa. 1989)).