Rhode Island Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on Rhode Island construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A Rhode Island lien claimant usually needs three documents in order: a sworn Notice of Intention mailed to the owner and recorded in the land evidence records, a notice of lis pendens, and a complaint to enforce. A direct contractor also gives a Notice of Possible Mechanic's Lien first (R.I. Gen. Laws §§ 34-28-4, 34-28-4.1, 34-28-10).
The Notice of Intention protects labor and materials furnished within the 200 days before it is recorded and afterward, so record early. Earned but unpaid retainage is protected from the start of the work (R.I. Gen. Laws §§ 34-28-4, 34-28-9).
Enforcement is fast. Within 40 days after recording the Notice of Intention, record a notice of lis pendens and file the complaint to enforce in Superior Court, on the same day as the lis pendens or within 7 days afterward (R.I. Gen. Laws § 34-28-10).
Liens cannot attach to public property. On public works, a claimant with no contract with the bonded contractor gives it written notice by certified mail within 90 days after last furnishing. Suit on the bond is due within 2 years after last furnishing, or any longer period in the bond (R.I. Gen. Laws §§ 37-12-2, 37-12-5).
Rhode Island mechanics liens are governed by Chapter 34-28 of the Rhode Island General Laws. Payment bonds on public works are governed by Chapter 37-12, together with R.I. Gen. Laws § 37-13-14.
Rhode Island prescribes the substance of several documents, including the Notice of Possible Mechanic's Lien, the Notice of Intention, the notice of lis pendens, and the Demand for Direct Payment. The Notice of Intention must be signed under oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
Rhode Island Preliminary Notices
Notice of Possible Mechanic's Lien
- Who uses it
- Contractors in direct contract with the owner, lessee, or tenant, other than material suppliers
- When
- Before starting work or delivering materials
- Served on or filed with
- The owner, lessee, or tenant, either conspicuously in the written contract or by certified mail, return receipt requested
- Notarization
- Not required
- Failure to give the notice defeats the direct contractor's lien, but not the rights of its subcontractors and suppliers.
R.I. Gen. Laws § 34-28-4.1
Rhode Island Lien Claim and Service
Notice of Intention to Do Work or Furnish Materials, or Both
- Who uses it
- Contractors, subcontractors, suppliers, and other lien claimants
- When
- Mailed and recorded before or within 200 days after furnishing; it covers furnishing within the 200 days before recording and afterward
- Served on or filed with
- Mailed by registered or certified mail, return receipt requested, to the record owner, and recorded in the land evidence records of the city or town where the land lies
- Notarization
- Required; executed under oath
- If the mailed notice is returned undelivered, file it with the returned envelope in the land evidence records within 30 days after return.
- Architects and engineers have a separate timing rule tied to visible commencement of construction.
R.I. Gen. Laws §§ 34-28-4, 34-28-7
Rhode Island Enforcing the Lien
Notice of Lis Pendens
- Who uses it
- Lien claimants
- When
- Within 40 days after recording the Notice of Intention
- Served on or filed with
- Recorded in the land evidence records of the city or town where the land lies
- Notarization
- Not required
R.I. Gen. Laws §§ 34-28-10, 34-28-11
Complaint to Enforce Lien
- Who uses it
- Lien claimants
- When
- Within 40 days after recording the Notice of Intention, on the same day as the lis pendens or within 7 days afterward
- Served on or filed with
- Filed in the Superior Court for the county where the land lies, naming the record owner
- Notarization
- Not required
- The statute lists the required contents, including a detailed account, payments, dates of performance, and the perfection steps taken.
- Other claimants who recorded a Notice of Intention must enter an appearance and file their claim, generally within 20 days after the citation return day.
R.I. Gen. Laws §§ 34-28-10, 34-28-13, 34-28-16
Rhode Island Releasing or Bonding Off a Lien
Release or Subordination of Lien
- Who uses it
- Lien claimants or their authorized signatories
- When
- No fixed deadline
- Served on or filed with
- Delivered to the relying party and recorded when clearing title
- Notarization
- Not required by the statute; recording requirements may apply
- A signed release is enforceable by a person who relies on it, even without consideration.
R.I. Gen. Laws § 34-28-26
Demand for Direct Payment
- Who uses it
- Lien claimants seeking direct payment from the owner, with the approval of each party in the line of privity
- When
- No fixed deadline
- Served on or filed with
- The owner, lessee, tenant, or other person obligated to pay
- Notarization
- Not required
- The form incorporates a lien release, written approvals from intervening parties, and a payment receipt.
R.I. Gen. Laws §§ 34-28-27, 34-28-29
Motion to Discharge Lien by Deposit or Bond
- Who uses it
- Owners, lessees, or tenants
- When
- At any time after the Notice of Intention is recorded
- Served on or filed with
- Filed in the Superior Court for the county where the land lies, with cash paid into the registry or a licensed surety bond
- Notarization
- Not required
- The security must cover the lien demand plus costs, statutory interest, and reasonable attorney fees.
- A claimant must then sue the surety, or amend a pending complaint within 60 days after notice of the substitution order.
R.I. Gen. Laws § 34-28-17
Rhode Island Owner Notices and Forms
Verified Complaint for Order to Show Cause
- Who uses it
- Owners, contractors, or other interested persons challenging a lien
- When
- At any time; the show cause notice is served at least one week before the hearing
- Served on or filed with
- Filed in the Superior Court for the county where the land lies; served on necessary parties
- Notarization
- Verification required
R.I. Gen. Laws § 34-28-17.1
Landlord's Written Consent to Tenant Improvements
- Who uses it
- Landlords
- When
- Before the improvements are made
- Served on or filed with
- Given to the tenant or contractor; no filing required
- Notarization
- Not required
- Written consent subjects the landlord's interest, not only the tenant's interest, to the lien.
R.I. Gen. Laws § 34-28-2
Rhode Island Public Works and Payment Bond Claims
Written Notice of Payment Bond Claim
- Who uses it
- Claimants with a contract with a subcontractor but no contract with the bonded contractor
- When
- Within 90 days after the claimant's last furnishing
- Served on or filed with
- The bonded contractor, by certified mail at its office, place of business, or residence
- Notarization
- Not required
- The notice must state with substantial accuracy the amount claimed and the party supplied.
R.I. Gen. Laws § 37-12-2
Action on Payment Bond
- Who uses it
- Unpaid claimants on bonded public works
- When
- After 90 days without payment, and within 2 years after last furnishing or any longer period stated in the bond
- Served on or filed with
- Filed in the Superior Court for Providence and Bristol Counties
- Notarization
- Not required
R.I. Gen. Laws §§ 37-12-2, 37-12-3, 37-12-5
Frequently Asked Questions
Is there a statutory mechanics lien form in Rhode Island?
Yes. The Notice of Intention to Do Work or Furnish Materials, or Both, must substantially follow the statutory form and contain the required particulars (R.I. Gen. Laws § 34-28-4). The Notice of Possible Mechanic's Lien, the lis pendens, and the Demand for Direct Payment also have statutory forms.
Does a Rhode Island mechanics lien have to be notarized?
Yes. The Notice of Intention must be executed under oath, and the statutory form includes a notarization clause (R.I. Gen. Laws § 34-28-4). The lis pendens and the enforcement complaint do not require an oath.
Where do I file a mechanics lien in Rhode Island?
Mail the Notice of Intention to the record owner by registered or certified mail, return receipt requested, and record it in the land evidence records of the city or town where the land lies. It protects work furnished within the 200 days before recording and afterward (R.I. Gen. Laws § 34-28-4).
How fast must I enforce a Rhode Island mechanics lien?
Within 40 days after recording the Notice of Intention, record a notice of lis pendens and file the complaint to enforce in Superior Court. The complaint must be filed on the same day as the lis pendens or within 7 days afterward (R.I. Gen. Laws § 34-28-10).
What form releases a mechanics lien in Rhode Island?
A claimant may sign a release or subordination, which is enforceable by anyone who relies on it (R.I. Gen. Laws § 34-28-26). An owner may also discharge the lien by depositing cash or a surety bond covering the claim, costs, interest, and attorney fees (R.I. Gen. Laws § 34-28-17).
Can a Rhode Island owner challenge a lien quickly?
Yes. Any interested person may file a verified complaint for an order to show cause, with at least one week's notice of the hearing, asking the court to discharge an invalid lien or one without probable merit (R.I. Gen. Laws § 34-28-17.1). Rhode Island has no owner demand that shortens the 40-day period.
What form do I use for a Rhode Island public project bond claim?
A claimant with no contract with the bonded contractor sends it written notice by certified mail within 90 days after last furnishing, stating the amount and the party supplied. Suit is filed in Superior Court within 2 years after last furnishing, or any longer period in the bond (R.I. Gen. Laws §§ 37-12-2, 37-12-5).
Related Rhode Island Resources
Rhode Island Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Rhode Island Notice Requirements
Who must give notice, when, and how.
Rhode Island Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Rhode Island Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Rhode Island law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.