Quick Answer

A Rhode Island lien claimant usually needs three documents in order: a sworn Notice of Intention mailed to the owner and recorded in the land evidence records, a notice of lis pendens, and a complaint to enforce. A direct contractor also gives a Notice of Possible Mechanic's Lien first (R.I. Gen. Laws §§ 34-28-4, 34-28-4.1, 34-28-10).

The Notice of Intention protects labor and materials furnished within the 200 days before it is recorded and afterward, so record early. Earned but unpaid retainage is protected from the start of the work (R.I. Gen. Laws §§ 34-28-4, 34-28-9).

Enforcement is fast. Within 40 days after recording the Notice of Intention, record a notice of lis pendens and file the complaint to enforce in Superior Court, on the same day as the lis pendens or within 7 days afterward (R.I. Gen. Laws § 34-28-10).

Liens cannot attach to public property. On public works, a claimant with no contract with the bonded contractor gives it written notice by certified mail within 90 days after last furnishing. Suit on the bond is due within 2 years after last furnishing, or any longer period in the bond (R.I. Gen. Laws §§ 37-12-2, 37-12-5).

Rhode Island mechanics liens are governed by Chapter 34-28 of the Rhode Island General Laws. Payment bonds on public works are governed by Chapter 37-12, together with R.I. Gen. Laws § 37-13-14.

Rhode Island prescribes the substance of several documents, including the Notice of Possible Mechanic's Lien, the Notice of Intention, the notice of lis pendens, and the Demand for Direct Payment. The Notice of Intention must be signed under oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.

Rhode Island Preliminary Notices

Notice of Possible Mechanic's Lien

Statutory Form
Required When It Applies
Who uses it
Contractors in direct contract with the owner, lessee, or tenant, other than material suppliers
When
Before starting work or delivering materials
Served on or filed with
The owner, lessee, or tenant, either conspicuously in the written contract or by certified mail, return receipt requested
Notarization
Not required
  • Failure to give the notice defeats the direct contractor's lien, but not the rights of its subcontractors and suppliers.

R.I. Gen. Laws § 34-28-4.1

Rhode Island Lien Claim and Service

Notice of Intention to Do Work or Furnish Materials, or Both

Statutory Form
Notarized
Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, and other lien claimants
When
Mailed and recorded before or within 200 days after furnishing; it covers furnishing within the 200 days before recording and afterward
Served on or filed with
Mailed by registered or certified mail, return receipt requested, to the record owner, and recorded in the land evidence records of the city or town where the land lies
Notarization
Required; executed under oath
  • If the mailed notice is returned undelivered, file it with the returned envelope in the land evidence records within 30 days after return.
  • Architects and engineers have a separate timing rule tied to visible commencement of construction.

R.I. Gen. Laws §§ 34-28-4, 34-28-7

Rhode Island Enforcing the Lien

Notice of Lis Pendens

Statutory Form
Required When It Applies
Who uses it
Lien claimants
When
Within 40 days after recording the Notice of Intention
Served on or filed with
Recorded in the land evidence records of the city or town where the land lies
Notarization
Not required

R.I. Gen. Laws §§ 34-28-10, 34-28-11

Complaint to Enforce Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 40 days after recording the Notice of Intention, on the same day as the lis pendens or within 7 days afterward
Served on or filed with
Filed in the Superior Court for the county where the land lies, naming the record owner
Notarization
Not required
  • The statute lists the required contents, including a detailed account, payments, dates of performance, and the perfection steps taken.
  • Other claimants who recorded a Notice of Intention must enter an appearance and file their claim, generally within 20 days after the citation return day.

R.I. Gen. Laws §§ 34-28-10, 34-28-13, 34-28-16

Rhode Island Releasing or Bonding Off a Lien

Release or Subordination of Lien

Required When It Applies
Who uses it
Lien claimants or their authorized signatories
When
No fixed deadline
Served on or filed with
Delivered to the relying party and recorded when clearing title
Notarization
Not required by the statute; recording requirements may apply
  • A signed release is enforceable by a person who relies on it, even without consideration.

R.I. Gen. Laws § 34-28-26

Demand for Direct Payment

Statutory Form
Optional
Who uses it
Lien claimants seeking direct payment from the owner, with the approval of each party in the line of privity
When
No fixed deadline
Served on or filed with
The owner, lessee, tenant, or other person obligated to pay
Notarization
Not required
  • The form incorporates a lien release, written approvals from intervening parties, and a payment receipt.

R.I. Gen. Laws §§ 34-28-27, 34-28-29

Motion to Discharge Lien by Deposit or Bond

Required When It Applies
Who uses it
Owners, lessees, or tenants
When
At any time after the Notice of Intention is recorded
Served on or filed with
Filed in the Superior Court for the county where the land lies, with cash paid into the registry or a licensed surety bond
Notarization
Not required
  • The security must cover the lien demand plus costs, statutory interest, and reasonable attorney fees.
  • A claimant must then sue the surety, or amend a pending complaint within 60 days after notice of the substitution order.

R.I. Gen. Laws § 34-28-17

Rhode Island Owner Notices and Forms

Verified Complaint for Order to Show Cause

Optional
Who uses it
Owners, contractors, or other interested persons challenging a lien
When
At any time; the show cause notice is served at least one week before the hearing
Served on or filed with
Filed in the Superior Court for the county where the land lies; served on necessary parties
Notarization
Verification required

R.I. Gen. Laws § 34-28-17.1

Landlord's Written Consent to Tenant Improvements

Optional
Who uses it
Landlords
When
Before the improvements are made
Served on or filed with
Given to the tenant or contractor; no filing required
Notarization
Not required
  • Written consent subjects the landlord's interest, not only the tenant's interest, to the lien.

R.I. Gen. Laws § 34-28-2

Rhode Island Public Works and Payment Bond Claims

Written Notice of Payment Bond Claim

Required When It Applies
Who uses it
Claimants with a contract with a subcontractor but no contract with the bonded contractor
When
Within 90 days after the claimant's last furnishing
Served on or filed with
The bonded contractor, by certified mail at its office, place of business, or residence
Notarization
Not required
  • The notice must state with substantial accuracy the amount claimed and the party supplied.

R.I. Gen. Laws § 37-12-2

Action on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works
When
After 90 days without payment, and within 2 years after last furnishing or any longer period stated in the bond
Served on or filed with
Filed in the Superior Court for Providence and Bristol Counties
Notarization
Not required

R.I. Gen. Laws §§ 37-12-2, 37-12-3, 37-12-5

Frequently Asked Questions

Is there a statutory mechanics lien form in Rhode Island?

Yes. The Notice of Intention to Do Work or Furnish Materials, or Both, must substantially follow the statutory form and contain the required particulars (R.I. Gen. Laws § 34-28-4). The Notice of Possible Mechanic's Lien, the lis pendens, and the Demand for Direct Payment also have statutory forms.

Does a Rhode Island mechanics lien have to be notarized?

Yes. The Notice of Intention must be executed under oath, and the statutory form includes a notarization clause (R.I. Gen. Laws § 34-28-4). The lis pendens and the enforcement complaint do not require an oath.

Where do I file a mechanics lien in Rhode Island?

Mail the Notice of Intention to the record owner by registered or certified mail, return receipt requested, and record it in the land evidence records of the city or town where the land lies. It protects work furnished within the 200 days before recording and afterward (R.I. Gen. Laws § 34-28-4).

How fast must I enforce a Rhode Island mechanics lien?

Within 40 days after recording the Notice of Intention, record a notice of lis pendens and file the complaint to enforce in Superior Court. The complaint must be filed on the same day as the lis pendens or within 7 days afterward (R.I. Gen. Laws § 34-28-10).

What form releases a mechanics lien in Rhode Island?

A claimant may sign a release or subordination, which is enforceable by anyone who relies on it (R.I. Gen. Laws § 34-28-26). An owner may also discharge the lien by depositing cash or a surety bond covering the claim, costs, interest, and attorney fees (R.I. Gen. Laws § 34-28-17).

Can a Rhode Island owner challenge a lien quickly?

Yes. Any interested person may file a verified complaint for an order to show cause, with at least one week's notice of the hearing, asking the court to discharge an invalid lien or one without probable merit (R.I. Gen. Laws § 34-28-17.1). Rhode Island has no owner demand that shortens the 40-day period.

What form do I use for a Rhode Island public project bond claim?

A claimant with no contract with the bonded contractor sends it written notice by certified mail within 90 days after last furnishing, stating the amount and the party supplied. Suit is filed in Superior Court within 2 years after last furnishing, or any longer period in the bond (R.I. Gen. Laws §§ 37-12-2, 37-12-5).

Deadlines Are Unforgiving