HomeTennesseeMechanics Lien Forms
Tennessee Mechanics Lien Forms

Tennessee Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Tennessee construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Tennessee subcontractor or supplier needs three core documents in order: a Notice of Nonpayment for each unpaid month, a Notice of Lien served on the owner within 90 days after completion or abandonment, and a sworn complaint seeking attachment within 90 days after serving that notice (Tenn. Code Ann. §§ 66-11-145, 66-11-115, 66-11-126).

The Notice of Nonpayment is due within 90 days after the last day of each month in which work went unpaid, served on the owner and the prime contractor. It does not apply to one-to-four family residential units, and amounts retained to guarantee performance are exempt (Tenn. Code Ann. § 66-11-145).

Recording the sworn statement with the county register within 90 days preserves priority against later purchasers and lenders (Tenn. Code Ann. § 66-11-112). A prime contractor's lien lasts 1 year after completion without recording, but an owner's written demand for enforcement shortens the time to sue to 60 days (Tenn. Code Ann. §§ 66-11-106, 66-11-130).

On public works over $100,000, serve a written notice of claim on the bonded contractor or the awarding official within 90 days after completion of the public work, and sue on the bond within 6 months (Tenn. Code Ann. §§ 12-4-205, 12-4-206).

Tennessee mechanic lien law, Tenn. Code Ann. § 66-11-101 and following, separates three documents that are often confused: the monthly Notice of Nonpayment, the Notice of Lien a remote contractor serves on the owner, and the sworn statement recorded with the county register to protect priority. Tennessee has no general notice of commencement for private projects.

This page describes each Tennessee document a contractor, remote claimant, owner, or public works claimant uses, who uses it, when it is due, and where it is served or recorded. Public works are governed by the Little Miller Act, Tenn. Code Ann. § 12-4-201 and following.

Tennessee Preliminary Notices

Notice to Owner (Residential Contractor's Notice)

Statutory Form
Required When It Applies
Who uses it
Contractors contracting directly with the owner of residential real property
When
Before making the contract or commencing the improvement
Served on or filed with
The owner, by registered mail or otherwise as the statute provides
Notarization
Not required
  • Noncompliance is a statutory violation but does not by itself eliminate the contractor's lien. The owner may reject the contract by registered mail within 3 days after receiving the notice (Tenn. Code Ann. § 66-11-204).

Tenn. Code Ann. §§ 66-11-203, 66-11-206

Notice of Nonpayment

Statutory Form
Required When It Applies
Who uses it
Remote contractors (subcontractors and suppliers) on improvements other than one-to-four family residential units
When
Within 90 days after the last day of each month in which labor or materials were furnished and remain unpaid
Served on or filed with
The owner and the prime contractor, by registered or certified mail, notarized hand delivery, or commercial delivery with written confirmation
Notarization
Not required; hand delivery must be proved by a notarized sworn statement
  • The notice states the claimant, the work or materials, the amount owed, the last date of furnishing, and the property. Failure to serve it forfeits the lien for that month's unpaid work.
  • Amounts retained to guarantee performance are exempt.

Tenn. Code Ann. §§ 66-11-145, 66-11-149

Tennessee Lien Claim and Service

Notice of Lien (Remote Contractor)

Statutory Form
Required When It Applies
Who uses it
Remote contractors: subcontractors and suppliers without a direct contract with the owner
When
Within 90 days after completion or abandonment of the improvement, or earlier if a Notice of Completion cuts off the period
Served on or filed with
The owner
Notarization
The statutory model form is sworn; using it is the safe practice
  • Serving this notice is what preserves the remote contractor's lien against the owner. It is separate from the monthly Notice of Nonpayment.

Tenn. Code Ann. §§ 66-11-115, 66-11-112(d)

Sworn Statement of Amount Due (Recorded Notice of Lien)

Statutory Form
Notarized
Required When It Applies
Who uses it
Prime contractors and remote contractors
When
Within 90 days after completion or abandonment of the improvement
Served on or filed with
Recorded with the county register of deeds in the county where the property is located
Notarization
Required; the amount must be sworn
  • Recording preserves the lien's priority against later purchasers and lenders; it is not required against the original owner.
  • A recorded contract containing the price and property description is an alternative way to give notice (Tenn. Code Ann. § 66-11-111).

Tenn. Code Ann. § 66-11-112

Tennessee Enforcing the Lien

Sworn Complaint Seeking Writ of Attachment

Notarized
Required When It Applies
Who uses it
Prime contractors and remote contractors
When
Prime contractors: within 1 year after completion or abandonment. Remote contractors: within 90 days after serving the Notice of Lien
Served on or filed with
Filed in a court with jurisdiction and served on the persons whose interests are to be attached
Notarization
Required; the pleading must be under oath
  • The timely suit must seek attachment, but the writ need not issue or be served within the period. An attachment bond is filed before the clerk issues the writ.
  • An owner's written demand for enforcement shortens the time to 60 days after service of the demand.

Tenn. Code Ann. §§ 66-11-106, 66-11-115, 66-11-126

Tennessee Releasing or Bonding Off a Lien

Release of Lien

Required When It Applies
Who uses it
A lienor whose lien is forfeited, expired, satisfied, or adjudged invalid
When
Within 30 days after service of the owner's written demand for release
Served on or filed with
Recorded where the lien was recorded
Notarization
Must meet recording authentication requirements
  • A lienor that fails to release after demand is liable for resulting damages, costs, and reasonable attorney fees. The release is effective when recorded.

Tenn. Code Ann. § 66-11-135

Bond to Indemnify Against Recorded Lien

Optional
Who uses it
Owners, contractors, and any other person
When
Any time after the lien is recorded
Served on or filed with
Recorded in the county where the lien is recorded
Notarization
Not separately required
  • The bond equals the lien amount with a corporate surety and discharges the property. A qualifying existing payment bond may be recorded instead.

Tenn. Code Ann. § 66-11-142

Tennessee Owner Notices and Forms

Notice of Completion

Statutory Form
Notarized
Optional
Who uses it
Owners, purchasers, and their agents
When
Upon actual completion of the improvement; a premature notice is void
Served on or filed with
Recorded in the county where the property is located, with copies served at the same time on prime and remote contractors entitled to them
Notarization
Required; acknowledgment
  • Claimants must then serve a written claim within 10 days after recording on one-to-four family residential units, or 30 days otherwise, or lose unrecorded lien rights.

Tenn. Code Ann. § 66-11-143

Demand for Enforcement of Lien

Optional
Who uses it
Owners, owner's agents, and prime contractors
When
At any time after a lien is asserted
Served on or filed with
The lienor
Notarization
Not required
  • The lienor must commence enforcement within 60 days after service of the demand or the lien is forfeited.

Tenn. Code Ann. § 66-11-130

Contractor's Sworn Statement and Receipt (Notice That All Liens Have Been Paid)

Statutory Form
Notarized
Required When It Applies
Who uses it
Prime contractors
When
Upon completion and receipt of the contract price
Served on or filed with
The owner
Notarization
Required; notarized oath
  • The statement confirms payment of subcontractors and suppliers and includes a hold-harmless guarantee to the owner.

Tenn. Code Ann. § 66-11-205

Tennessee Public Works and Payment Bond Claims

Notice of Claim (Little Miller Act)

Required When It Applies
Who uses it
Laborers, subcontractors, and suppliers on public works over $100,000
When
Within 90 days after completion of the public work
Served on or filed with
The bonded contractor or the awarding public official, by certified mail, return receipt requested, or personal delivery
Notarization
Not required
  • The notice must include an itemized account, the balance due, and a description of the property.
  • Mechanic liens cannot attach to public property in Tennessee.

Tenn. Code Ann. § 12-4-205

Action on the Payment Bond

Required When It Applies
Who uses it
Claimants that served a timely notice of claim
When
Within 6 months after completion of the public work or furnishing of the labor or materials
Served on or filed with
Filed in a court of competent jurisdiction against the bond obligors
Notarization
Not required
  • Calendar from the earlier date; serving notice does not restart the period. A bond broader than the statute may be a common-law bond enforceable on its own terms (Koch v. Construction Technology, Inc., 924 S.W.2d 68 (Tenn. 1996)).

Tenn. Code Ann. § 12-4-206

Frequently Asked Questions

Is there a statutory mechanics lien form in Tennessee?

Yes, for several documents. The statute supplies substantial-form models for the Notice of Nonpayment, the Notice of Lien, the Notice of Completion, the residential Notice to Owner, and the contractor's final sworn statement (Tenn. Code Ann. §§ 66-11-145, 66-11-112, 66-11-143, 66-11-203, 66-11-205).

Does a Tennessee mechanics lien have to be notarized?

The sworn statement recorded with the county register must be sworn, and recorded documents must be acknowledged. The Notice of Nonpayment need not be notarized, but proof of hand delivery requires a notarized sworn statement (Tenn. Code Ann. §§ 66-11-112, 66-11-149).

Does Tennessee have a preliminary notice?

Tennessee's equivalent is the monthly Notice of Nonpayment, due within 90 days after the last day of each unpaid month on projects other than one-to-four family residential units (Tenn. Code Ann. § 66-11-145). Prime contractors on residential work give a separate Notice to Owner before contracting (Tenn. Code Ann. § 66-11-203).

Where do I file a mechanics lien in Tennessee?

A remote contractor serves its Notice of Lien on the owner within 90 days after completion or abandonment, and records the sworn statement with the county register in the county where the property is located within the same 90 days (Tenn. Code Ann. §§ 66-11-115, 66-11-112).

Can subcontractors lien an owner-occupied home in Tennessee?

Generally no. On residential property the owner occupies or intends to occupy as a principal residence, only the prime contractor has lien rights, unless the owner and general contractor are the same or commonly controlled (Tenn. Code Ann. § 66-11-146).

What form releases a mechanics lien in Tennessee?

A release of lien recorded where the lien was recorded. After a lien is forfeited, expired, satisfied, or adjudged invalid, the owner may demand release, and the lienor must release within 30 days (Tenn. Code Ann. § 66-11-135). An owner may also record a bond to indemnify against the lien (Tenn. Code Ann. § 66-11-142).

What form do I use for a Tennessee public project bond claim?

A written notice of claim with an itemized account, served on the bonded contractor or the awarding official within 90 days after completion of the public work, followed by suit within 6 months (Tenn. Code Ann. §§ 12-4-205, 12-4-206).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us