HomeTexasMechanics Lien Forms
Texas Mechanics Lien Forms

Texas Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Texas construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Texas subcontractor or supplier needs three core forms in order: a Notice of Claim for Unpaid Labor or Materials for each unpaid month, an Affidavit Claiming a Mechanic's Lien filed with the county clerk, and a copy of the filed affidavit sent within 5 days (Tex. Prop. Code §§ 53.056, 53.052, 53.055).

The Notice of Claim is due by the 15th day of the 3rd month after each month of unpaid work on commercial projects, and by the 15th day of the 2nd month on residential projects. It goes to the owner and the original contractor and must substantially follow the statutory form (Tex. Prop. Code § 53.056).

The lien affidavit is sworn and must be filed by the 15th day of the 4th month after the claimant's last month of work on commercial projects, or the 3rd month on residential projects. Suit to foreclose is due 1 year after the last day the affidavit could have been filed (Tex. Prop. Code §§ 53.052, 53.158).

On public works, claimants mail a notice with a sworn account to the prime contractor and surety by the 15th day of the 3rd month after each unpaid month; lower-tier claimants also notify the prime by the 2nd month. Suit may follow from the 61st day (Tex. Gov't Code §§ 2253.041, 2253.047, 2253.078).

Texas mechanics lien law, Chapter 53 of the Texas Property Code, was rewritten by House Bill 2237 for original contracts entered into on or after January 1, 2022. The current scheme uses a statutory Notice of Claim for each month of unpaid work, a separate retainage notice, a sworn lien affidavit, and a short follow-up notice after filing. Projects under older contracts follow the prior law.

This page describes each Texas form a claimant or owner uses, who uses it, when it is due, and where it is served or filed. Public works are governed by the McGregor Act, Chapter 2253 of the Texas Government Code, which uses its own sworn claim notices to the prime contractor and surety.

Texas Preliminary Notices

Notice of Claim for Unpaid Labor or Materials

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers without a direct contract with the owner
When
By the 15th day of the 3rd month after each month of unpaid work (commercial); by the 15th day of the 2nd month (residential)
Served on or filed with
The owner or reputed owner and the original contractor
Notarization
Not required
  • The notice must substantially comply with the statutory form, including its statutory warning.
  • Certified mail is accepted, as are personal delivery and traceable private delivery services that confirm receipt.
  • For specially fabricated materials not delivered, the month the materials would normally have been delivered controls.

Tex. Prop. Code §§ 53.003, 53.056

Notice of Claim for Unpaid Retainage

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers whose contracts provide for retainage
When
By the earlier of 30 days after the claimant's contract is completed, terminated, or abandoned, or 30 days after the original contract is terminated or abandoned
Served on or filed with
The owner or reputed owner and the original contractor
Notarization
Not required
  • Required only to the extent the retainage was not already included in a monthly Notice of Claim.
  • This notice replaced the former early notice of a contractual retainage arrangement.

Tex. Prop. Code § 53.057

Texas Lien Claim and Service

Affidavit Claiming a Mechanic's Lien

Notarized
Required When It Applies
Who uses it
Original contractors, subcontractors, and suppliers
When
Commercial: by the 15th day of the 4th month after the month of completion, termination, or abandonment (original contractors) or of last furnishing (others); residential: by the 15th day of the 3rd month
Served on or filed with
Filed with the county clerk of the county where the property is located
Notarization
Required; the affidavit must contain a sworn statement of the amount claimed
  • The statute prescribes the affidavit's contents, not verbatim wording. Derivative claimants must list the months furnished and the dates and method of their notices.
  • A claim for retainage only is due by the 15th day of the 3rd month after the month the original contract was completed, terminated, or abandoned.
  • On a homestead, the affidavit must carry the statutory legend at the top in at least 10-point bold type, and the contract must have been signed by both spouses and filed before work began (Tex. Prop. Code § 53.254).

Tex. Prop. Code §§ 53.052, 53.054

Notice of Filed Affidavit

Required When It Applies
Who uses it
Every claimant that files a lien affidavit
When
Within 5 days after filing the affidavit
Served on or filed with
The owner or reputed owner, and also the original contractor if the claimant is a subcontractor or supplier
Notarization
Not required; send a copy of the filed affidavit

Tex. Prop. Code § 53.055

Texas Enforcing the Lien

Suit to Foreclose the Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 1 year after the last day the lien affidavit could have been filed
Served on or filed with
Filed in a court of competent jurisdiction where the property is located
Notarization
Not required by Chapter 53
  • A written extension agreement with the record owner, made before the period expires and recorded with the county clerk, may extend the deadline, but not beyond 2 years after the affidavit was filed.

Tex. Prop. Code § 53.158

Texas Releasing or Bonding Off a Lien

Release of Claim or Lien

Required When It Applies
Who uses it
A claimant that has been paid
When
Within 10 days after receiving a written request, once the debt is paid in collected funds
Served on or filed with
Delivered to the person requesting it and recorded with the county clerk to clear title
Notarization
The release must be in recordable form, which ordinarily requires acknowledgment
  • This recordable release is separate from the statutory progress and final payment waivers.

Tex. Prop. Code § 53.152

Bond to Indemnify Against Lien

Optional
Who uses it
Owners, original contractors, and other interested parties
When
Any time after the lien affidavit is filed
Served on or filed with
Filed with the county clerk where the property is located; the clerk mails notice of the bond to each named obligee
Notarization
Not required by statute
  • The bond must be double the lien amount for liens up to $40,000; above that, the greater of 1.5 times the lien or the lien plus $40,000.
  • The claimant must sue on the bond within 1 year after service of the notice of bond and before the lien itself becomes unenforceable.

Tex. Prop. Code §§ 53.171 to 53.175

Texas Owner Notices and Forms

Affidavit of Completion

Notarized
Optional
Who uses it
Owners
When
Optional; filing more than 10 days after completion changes its effect on the completion date for retainage purposes
Served on or filed with
Filed with the county clerk, with copies to the original contractor and to claimants who gave notice
Notarization
Required; it is a sworn affidavit
  • The statute prescribes the contents, including a conspicuous warning about retained funds.

Tex. Prop. Code § 53.106

Notice Relating to Termination or Abandonment

Required When It Applies
Who uses it
Owners on commercial projects
When
Within 10 days after the original contract is terminated or the original contractor abandons performance
Served on or filed with
Each subcontractor that gave a Notice of Claim or retainage notice or requested the notice in writing
Notarization
Not required
  • Does not apply to residential construction projects. An owner's failure to give it can excuse an affected subcontractor's retainage notice.

Tex. Prop. Code § 53.107

Residential Disclosure Statement and List of Subcontractors and Suppliers

Statutory Form
Required When It Applies
Who uses it
Original contractors on residential construction
When
Disclosure before the owner signs the contract; list before construction begins, with updates within 15 days after any change
Served on or filed with
The owner
Notarization
Not required
  • The owner may waive the list in writing using the statutory language.
  • A missing disclosure statement does not by itself invalidate the contractor's lien.

Tex. Prop. Code §§ 53.255, 53.256

Final Bills-Paid Affidavit

Notarized
Required When It Applies
Who uses it
Original contractors on residential construction
When
When final payment is tendered, as a condition of that payment
Served on or filed with
The owner or the owner's agent
Notarization
Required; it is a sworn affidavit
  • The affidavit states that all bills are paid or lists the unpaid debts.

Tex. Prop. Code § 53.259

Summary Motion to Remove Invalid or Unenforceable Lien

Notarized
Optional
Who uses it
Owners and other parties challenging a lien
When
In a pending foreclosure or declaratory judgment suit, with at least 30 days' notice of the hearing
Served on or filed with
Filed in the pending suit, with notice to the claimant and all parties who have appeared
Notarization
Required; the motion must be verified
  • This is a motion in an existing suit, not a pre-suit demand. A claimant may stay removal by posting a bond or deposit within 30 days after the order.

Tex. Prop. Code §§ 53.160, 53.161

Texas Public Works and Payment Bond Claims

Notice of Claim for Payment with Sworn Statement of Account (McGregor Act)

Notarized
Required When It Applies
Who uses it
Subcontractors and suppliers on public works
When
By the 15th day of the 3rd month after each month of unpaid work
Served on or filed with
The prime contractor and the surety, by certified or registered mail
Notarization
Required; the statement of account must be sworn
  • A claimant without a direct contract with the prime must also notify the prime by the 15th day of the 2nd month after each unpaid month (Tex. Gov't Code § 2253.047).
  • Lower-tier claimants whose contracts provide for retainage must also give the prime a 2nd-month retainage notice.

Tex. Gov't Code §§ 2253.041, 2253.047, 2253.048

Notice of Claim for Retainage (McGregor Act)

Required When It Applies
Who uses it
Claimants on public works whose contracts provide for retainage
When
Within 90 days after final completion of the public work contract
Served on or filed with
The prime contractor and the surety, by certified or registered mail
Notarization
Not required
  • Not required if the retainage was already included in an earlier claim notice.

Tex. Gov't Code § 2253.046

Suit on the Payment Bond

Required When It Applies
Who uses it
Unpaid public works claimants that gave timely notice
When
On or after the 61st day after the claim notice was mailed, and within 1 year after the claim notice was mailed
Served on or filed with
Filed in the county where any part of the public work is located, against the prime contractor and the surety
Notarization
Not required
  • A later demand letter does not restart the 1-year period that runs from the operative statutory notice (Live Systems, LLC v. Hartford Fire Ins. Co., No. 02-23-00238-CV (Tex. App. Fort Worth 2024)).

Tex. Gov't Code §§ 2253.073, 2253.078

Frequently Asked Questions

Is there a statutory mechanics lien form in Texas?

Partly. The monthly Notice of Claim and the retainage notice must substantially follow forms in the statute (Tex. Prop. Code §§ 53.056, 53.057). The lien affidavit is not a verbatim form, but § 53.054 prescribes its contents. The four lien waivers are mandatory statutory forms (Tex. Prop. Code § 53.284).

Does a Texas mechanics lien have to be notarized?

Yes. The Affidavit Claiming a Mechanic's Lien must contain a sworn statement of the amount claimed, which is made before a notary or other officer (Tex. Prop. Code § 53.054). The monthly Notice of Claim does not need to be notarized.

Where do I file a mechanics lien in Texas?

File the lien affidavit with the county clerk of the county where the property is located, then send a copy to the owner, and to the original contractor if you are a subcontractor or supplier, within 5 days (Tex. Prop. Code §§ 53.052, 53.055).

Does Texas still require a 2nd-month notice to the general contractor?

Not on private projects under original contracts entered into on or after January 1, 2022. House Bill 2237 replaced the separate notices with one Notice of Claim to the owner and original contractor. Public works under the McGregor Act still require a 2nd-month notice to the prime from lower-tier claimants (Tex. Gov't Code § 2253.047).

What extra steps apply to a Texas homestead lien?

The contract must be in writing, signed by both spouses if the owner is married, executed before work begins, and filed with the county clerk. The lien affidavit must carry the statutory homestead legend at the top in at least 10-point bold type, and the notices must include the statutory homestead statement (Tex. Prop. Code § 53.254).

What form releases a mechanics lien in Texas?

Once paid in collected funds, the claimant must furnish a recordable release within 10 days after a written request (Tex. Prop. Code § 53.152). An owner can also bond around the lien by filing a bond to indemnify against it (Tex. Prop. Code § 53.171).

What form do I use for a Texas public project bond claim?

Mail a written notice with a sworn statement of account to the prime contractor and the surety by the 15th day of the 3rd month after each unpaid month, and give any required 2nd-month notice to the prime. Retainage claims are due within 90 days after final completion (Tex. Gov't Code §§ 2253.041, 2253.046, 2253.047).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us