Quick Answer
A Texas subcontractor or supplier needs three core forms in order: a Notice of Claim for Unpaid Labor or Materials for each unpaid month, an Affidavit Claiming a Mechanic's Lien filed with the county clerk, and a copy of the filed affidavit sent within 5 days (Tex. Prop. Code §§ 53.056, 53.052, 53.055).
The Notice of Claim is due by the 15th day of the 3rd month after each month of unpaid work on commercial projects, and by the 15th day of the 2nd month on residential projects. It goes to the owner and the original contractor and must substantially follow the statutory form (Tex. Prop. Code § 53.056).
The lien affidavit is sworn and must be filed by the 15th day of the 4th month after the claimant's last month of work on commercial projects, or the 3rd month on residential projects. Suit to foreclose is due 1 year after the last day the affidavit could have been filed (Tex. Prop. Code §§ 53.052, 53.158).
On public works, claimants mail a notice with a sworn account to the prime contractor and surety by the 15th day of the 3rd month after each unpaid month; lower-tier claimants also notify the prime by the 2nd month. Suit may follow from the 61st day (Tex. Gov't Code §§ 2253.041, 2253.047, 2253.078).
Texas mechanics lien law, Chapter 53 of the Texas Property Code, was rewritten by House Bill 2237 for original contracts entered into on or after January 1, 2022. The current scheme uses a statutory Notice of Claim for each month of unpaid work, a separate retainage notice, a sworn lien affidavit, and a short follow-up notice after filing. Projects under older contracts follow the prior law.
This page describes each Texas form a claimant or owner uses, who uses it, when it is due, and where it is served or filed. Public works are governed by the McGregor Act, Chapter 2253 of the Texas Government Code, which uses its own sworn claim notices to the prime contractor and surety.
Texas Preliminary Notices
Notice of Claim for Unpaid Labor or Materials
- Who uses it
- Subcontractors and suppliers without a direct contract with the owner
- When
- By the 15th day of the 3rd month after each month of unpaid work (commercial); by the 15th day of the 2nd month (residential)
- Served on or filed with
- The owner or reputed owner and the original contractor
- Notarization
- Not required
- The notice must substantially comply with the statutory form, including its statutory warning.
- Certified mail is accepted, as are personal delivery and traceable private delivery services that confirm receipt.
- For specially fabricated materials not delivered, the month the materials would normally have been delivered controls.
Tex. Prop. Code §§ 53.003, 53.056
Notice of Claim for Unpaid Retainage
- Who uses it
- Subcontractors and suppliers whose contracts provide for retainage
- When
- By the earlier of 30 days after the claimant's contract is completed, terminated, or abandoned, or 30 days after the original contract is terminated or abandoned
- Served on or filed with
- The owner or reputed owner and the original contractor
- Notarization
- Not required
- Required only to the extent the retainage was not already included in a monthly Notice of Claim.
- This notice replaced the former early notice of a contractual retainage arrangement.
Tex. Prop. Code § 53.057
Texas Lien Claim and Service
Affidavit Claiming a Mechanic's Lien
- Who uses it
- Original contractors, subcontractors, and suppliers
- When
- Commercial: by the 15th day of the 4th month after the month of completion, termination, or abandonment (original contractors) or of last furnishing (others); residential: by the 15th day of the 3rd month
- Served on or filed with
- Filed with the county clerk of the county where the property is located
- Notarization
- Required; the affidavit must contain a sworn statement of the amount claimed
- The statute prescribes the affidavit's contents, not verbatim wording. Derivative claimants must list the months furnished and the dates and method of their notices.
- A claim for retainage only is due by the 15th day of the 3rd month after the month the original contract was completed, terminated, or abandoned.
- On a homestead, the affidavit must carry the statutory legend at the top in at least 10-point bold type, and the contract must have been signed by both spouses and filed before work began (Tex. Prop. Code § 53.254).
Tex. Prop. Code §§ 53.052, 53.054
Notice of Filed Affidavit
- Who uses it
- Every claimant that files a lien affidavit
- When
- Within 5 days after filing the affidavit
- Served on or filed with
- The owner or reputed owner, and also the original contractor if the claimant is a subcontractor or supplier
- Notarization
- Not required; send a copy of the filed affidavit
Tex. Prop. Code § 53.055
Texas Enforcing the Lien
Suit to Foreclose the Lien
- Who uses it
- Lien claimants
- When
- Within 1 year after the last day the lien affidavit could have been filed
- Served on or filed with
- Filed in a court of competent jurisdiction where the property is located
- Notarization
- Not required by Chapter 53
- A written extension agreement with the record owner, made before the period expires and recorded with the county clerk, may extend the deadline, but not beyond 2 years after the affidavit was filed.
Tex. Prop. Code § 53.158
Texas Releasing or Bonding Off a Lien
Release of Claim or Lien
- Who uses it
- A claimant that has been paid
- When
- Within 10 days after receiving a written request, once the debt is paid in collected funds
- Served on or filed with
- Delivered to the person requesting it and recorded with the county clerk to clear title
- Notarization
- The release must be in recordable form, which ordinarily requires acknowledgment
- This recordable release is separate from the statutory progress and final payment waivers.
Tex. Prop. Code § 53.152
Bond to Indemnify Against Lien
- Who uses it
- Owners, original contractors, and other interested parties
- When
- Any time after the lien affidavit is filed
- Served on or filed with
- Filed with the county clerk where the property is located; the clerk mails notice of the bond to each named obligee
- Notarization
- Not required by statute
- The bond must be double the lien amount for liens up to $40,000; above that, the greater of 1.5 times the lien or the lien plus $40,000.
- The claimant must sue on the bond within 1 year after service of the notice of bond and before the lien itself becomes unenforceable.
Tex. Prop. Code §§ 53.171 to 53.175
Texas Owner Notices and Forms
Affidavit of Completion
- Who uses it
- Owners
- When
- Optional; filing more than 10 days after completion changes its effect on the completion date for retainage purposes
- Served on or filed with
- Filed with the county clerk, with copies to the original contractor and to claimants who gave notice
- Notarization
- Required; it is a sworn affidavit
- The statute prescribes the contents, including a conspicuous warning about retained funds.
Tex. Prop. Code § 53.106
Notice Relating to Termination or Abandonment
- Who uses it
- Owners on commercial projects
- When
- Within 10 days after the original contract is terminated or the original contractor abandons performance
- Served on or filed with
- Each subcontractor that gave a Notice of Claim or retainage notice or requested the notice in writing
- Notarization
- Not required
- Does not apply to residential construction projects. An owner's failure to give it can excuse an affected subcontractor's retainage notice.
Tex. Prop. Code § 53.107
Residential Disclosure Statement and List of Subcontractors and Suppliers
- Who uses it
- Original contractors on residential construction
- When
- Disclosure before the owner signs the contract; list before construction begins, with updates within 15 days after any change
- Served on or filed with
- The owner
- Notarization
- Not required
- The owner may waive the list in writing using the statutory language.
- A missing disclosure statement does not by itself invalidate the contractor's lien.
Tex. Prop. Code §§ 53.255, 53.256
Final Bills-Paid Affidavit
- Who uses it
- Original contractors on residential construction
- When
- When final payment is tendered, as a condition of that payment
- Served on or filed with
- The owner or the owner's agent
- Notarization
- Required; it is a sworn affidavit
- The affidavit states that all bills are paid or lists the unpaid debts.
Tex. Prop. Code § 53.259
Summary Motion to Remove Invalid or Unenforceable Lien
- Who uses it
- Owners and other parties challenging a lien
- When
- In a pending foreclosure or declaratory judgment suit, with at least 30 days' notice of the hearing
- Served on or filed with
- Filed in the pending suit, with notice to the claimant and all parties who have appeared
- Notarization
- Required; the motion must be verified
- This is a motion in an existing suit, not a pre-suit demand. A claimant may stay removal by posting a bond or deposit within 30 days after the order.
Tex. Prop. Code §§ 53.160, 53.161
Texas Public Works and Payment Bond Claims
Notice of Claim for Payment with Sworn Statement of Account (McGregor Act)
- Who uses it
- Subcontractors and suppliers on public works
- When
- By the 15th day of the 3rd month after each month of unpaid work
- Served on or filed with
- The prime contractor and the surety, by certified or registered mail
- Notarization
- Required; the statement of account must be sworn
- A claimant without a direct contract with the prime must also notify the prime by the 15th day of the 2nd month after each unpaid month (Tex. Gov't Code § 2253.047).
- Lower-tier claimants whose contracts provide for retainage must also give the prime a 2nd-month retainage notice.
Tex. Gov't Code §§ 2253.041, 2253.047, 2253.048
Notice of Claim for Retainage (McGregor Act)
- Who uses it
- Claimants on public works whose contracts provide for retainage
- When
- Within 90 days after final completion of the public work contract
- Served on or filed with
- The prime contractor and the surety, by certified or registered mail
- Notarization
- Not required
- Not required if the retainage was already included in an earlier claim notice.
Tex. Gov't Code § 2253.046
Suit on the Payment Bond
- Who uses it
- Unpaid public works claimants that gave timely notice
- When
- On or after the 61st day after the claim notice was mailed, and within 1 year after the claim notice was mailed
- Served on or filed with
- Filed in the county where any part of the public work is located, against the prime contractor and the surety
- Notarization
- Not required
- A later demand letter does not restart the 1-year period that runs from the operative statutory notice (Live Systems, LLC v. Hartford Fire Ins. Co., No. 02-23-00238-CV (Tex. App. Fort Worth 2024)).
Tex. Gov't Code §§ 2253.073, 2253.078
Frequently Asked Questions
Is there a statutory mechanics lien form in Texas?
Partly. The monthly Notice of Claim and the retainage notice must substantially follow forms in the statute (Tex. Prop. Code §§ 53.056, 53.057). The lien affidavit is not a verbatim form, but § 53.054 prescribes its contents. The four lien waivers are mandatory statutory forms (Tex. Prop. Code § 53.284).
Does a Texas mechanics lien have to be notarized?
Yes. The Affidavit Claiming a Mechanic's Lien must contain a sworn statement of the amount claimed, which is made before a notary or other officer (Tex. Prop. Code § 53.054). The monthly Notice of Claim does not need to be notarized.
Where do I file a mechanics lien in Texas?
File the lien affidavit with the county clerk of the county where the property is located, then send a copy to the owner, and to the original contractor if you are a subcontractor or supplier, within 5 days (Tex. Prop. Code §§ 53.052, 53.055).
Does Texas still require a 2nd-month notice to the general contractor?
Not on private projects under original contracts entered into on or after January 1, 2022. House Bill 2237 replaced the separate notices with one Notice of Claim to the owner and original contractor. Public works under the McGregor Act still require a 2nd-month notice to the prime from lower-tier claimants (Tex. Gov't Code § 2253.047).
What extra steps apply to a Texas homestead lien?
The contract must be in writing, signed by both spouses if the owner is married, executed before work begins, and filed with the county clerk. The lien affidavit must carry the statutory homestead legend at the top in at least 10-point bold type, and the notices must include the statutory homestead statement (Tex. Prop. Code § 53.254).
What form releases a mechanics lien in Texas?
Once paid in collected funds, the claimant must furnish a recordable release within 10 days after a written request (Tex. Prop. Code § 53.152). An owner can also bond around the lien by filing a bond to indemnify against it (Tex. Prop. Code § 53.171).
What form do I use for a Texas public project bond claim?
Mail a written notice with a sworn statement of account to the prime contractor and the surety by the 15th day of the 3rd month after each unpaid month, and give any required 2nd-month notice to the prime. Retainage claims are due within 90 days after final completion (Tex. Gov't Code §§ 2253.041, 2253.046, 2253.047).
Related Texas Resources
Texas Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Texas Notice Requirements
Who must give notice, when, and how.
Texas Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Texas Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Texas law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.