Quick Answer
A Utah claimant needs three core documents in order: a Preliminary Notice filed on the State Construction Registry within 20 days after first furnishing, a Notice of Construction Lien recorded with the county recorder, and an action to enforce the lien with a recorded lis pendens (Utah Code §§ 38-1a-501, 38-1a-502, 38-1a-701).
The Preliminary Notice requirement applies to every private project lien claimant, including the original contractor. A late notice protects only work furnished beginning 5 days after it is filed, and a notice filed more than 10 days after a Notice of Completion has no effect (Utah Code § 38-1a-501).
Record the Notice of Construction Lien within 180 days after final completion, or within 90 days after a Notice of Completion is filed, whichever is earlier. Deliver or mail a copy to the owner by certified mail within 30 days. Suit and lis pendens are due within 180 days after recording (Utah Code §§ 38-1a-502, 38-1a-701).
On government projects, subcontractors and suppliers file a government-project Preliminary Notice on the SCR, keyed to the Notice of Commencement. Suit on the payment bond may be brought once the claim is unpaid 90 days after last furnishing and within 1 year after last furnishing (Utah Code §§ 38-1b-202, 63G-6a-1103).
Utah runs its construction lien system through the State Construction Registry (SCR). Preliminary notices, notices of completion, and lender notices are filed electronically on the registry; the Notice of Construction Lien itself is recorded with the county recorder. Utah does not use a separate notice of intent to lien.
This page describes each Utah document a claimant, owner, or public works claimant uses, who uses it, when it is due, and where it is filed or served. Owner-occupied residences receive added protection under the Residence Lien Restriction and Lien Recovery Fund Act, and government projects use their own SCR notices and payment bonds.
Utah Preliminary Notices
Preliminary Notice
- Who uses it
- Every private project lien claimant, including original contractors, subcontractors, and suppliers
- When
- Within 20 days after first furnishing labor or materials
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
- The statute prescribes the required contents: claimant, hiring party, owner, original contractor, project location, and parcel or registry identifiers.
- A late notice protects only work furnished beginning 5 days after filing. Failure to file means no lien for work before that date.
Utah Code § 38-1a-501
Notice of Preconstruction Service
- Who uses it
- Architects, engineers, surveyors, and others providing preconstruction services
- When
- Within 20 days after commencing the preconstruction service
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
- A preconstruction lien is then perfected by recording a Notice of Preconstruction Lien within 90 days after completing the service, with a copy to the owner by certified mail within 30 days (Utah Code § 38-1a-402).
Utah Code § 38-1a-401
Utah Lien Claim and Service
Notice of Construction Lien
- Who uses it
- Unpaid claimants that filed a timely Preliminary Notice
- When
- Within 180 days after final completion, or within 90 days after a Notice of Completion is filed if earlier
- Served on or filed with
- Recorded with the county recorder of each county where the property is located; copy to the owner within 30 days
- Notarization
- Required; the notice must be signed and acknowledged for recording
- The statute prescribes the contents. A lien against an owner-occupied residence must include the statutory statement explaining how the owner can obtain removal of the lien.
- Failing to deliver or mail the owner's copy bars costs and attorney fees against that owner but does not void the lien.
- A subcontractor performing substantial work after the certificate of occupancy or final inspection has 180 days after its own final work.
Utah Code § 38-1a-502
Utah Enforcing the Lien
Action to Enforce Lien and Notice of Pendency of Action (Lis Pendens)
- Who uses it
- Lien claimants
- When
- Within 180 days after recording the Notice of Construction Lien; if the owner files bankruptcy first, within 90 days after the stay ends
- Served on or filed with
- Suit filed in court; lis pendens recorded with the county recorder in each county where the lien is recorded
- Notarization
- Not required by the lien statute
- A lien not enforced within the period is automatically void.
- Without a timely lis pendens, the lien is void except against parties joined in the action and persons with actual knowledge of it.
Utah Code § 38-1a-701
Residential Instructions and Homeowner Application Served with the Complaint
- Who uses it
- Claimants enforcing a lien against an owner-occupied residence
- When
- With service of the complaint on the residence owner
- Served on or filed with
- The residence owner
- Notarization
- Not required
- The packet includes the Division of Professional Licensing's Homeowner's Application for Certificate of Compliance. Omitting it bars maintaining or enforcing the lien.
Utah Code § 38-1a-701(6); Utah Admin. Code R156-38a-109
Utah Releasing or Bonding Off a Lien
Cancellation of Lien
- Who uses it
- A claimant that has been paid in full, including costs and cancellation fees
- When
- Within 10 days after receiving a request from an interested person
- Served on or filed with
- Submitted to each county recorder where the lien is recorded
- Notarization
- Must meet county recording requirements
- A claimant that fails to cancel on time is liable for the greater of $100 per day or actual damages.
Utah Code § 38-1a-803
Notice of Release of Lien and Substitution of Alternate Security
- Who uses it
- Owners, original contractors, and subcontractors
- When
- Before 180 days after the first summons is served in the foreclosure action
- Served on or filed with
- Recorded where the lien is recorded; served on the claimant within 30 days after recording
- Notarization
- Required; acknowledgment for recording
- The attached bond or cash deposit must equal 150% of a lien of $25,000 or more, 175% of a lien from $15,000 to under $25,000, and 200% of a lien under $15,000.
Utah Code § 38-1a-804
Utah Owner Notices and Forms
Notice of Completion
- Who uses it
- Owners, original contractors, construction lenders, sureties, and title insurers
- When
- Upon final completion
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
- Filing it shortens the lien recording period to 90 days after filing, never later than 180 days after final completion.
Utah Code § 38-1a-507
Notice of Intent to Obtain Final Completion
- Who uses it
- Owners and original contractors on qualifying nonresidential projects
- When
- At least 45 days before a Notice of Completion is or could be filed
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
- Required when the performance time exceeds 120 days, the original contract price exceeds $500,000, and no payment bond was obtained.
- Claimants covered by a preliminary notice then file a balance statement on the registry within 20 days.
Utah Code § 38-1a-506
Notification of Rights (Protection Against Liens and Civil Action)
- Who uses it
- Original contractors and developers contracting with residential owners
- When
- Included in the written contract with the owner
- Served on or filed with
- The residential owner
- Notarization
- Not required
Utah Code § 38-11-108; Utah Admin. Code R156-38a-108
Petition to Nullify Lien for Failure to File Notice
- Who uses it
- Owners facing a lien filed without a required preliminary notice
- When
- After sending a written request to withdraw by certified mail and waiting 10 business days
- Served on or filed with
- Filed in court and served on the claimant within 3 business days after filing
- Notarization
- Required; the petition must be supported by the owner's sworn affidavit
Utah Code § 38-1a-805
Utah Public Works and Payment Bond Claims
Notice of Commencement for a Government Project
- Who uses it
- Original contractors and government owners
- When
- No later than 15 days after physical construction begins
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
Utah Code § 38-1b-201
Preliminary Notice on Government Project
- Who uses it
- Subcontractors and suppliers on government projects
- When
- By the later of 20 days after first furnishing or 20 days after the Notice of Commencement is filed
- Served on or filed with
- Filed on the State Construction Registry
- Notarization
- Not required
- Direct owner contractors and wage laborers are exempt; labor supply companies are not.
- A late notice generally protects only work furnished beginning 5 days after filing.
Utah Code §§ 38-1b-202, 63G-6a-1104
Action on the Public Payment Bond
- Who uses it
- Unpaid claimants on government projects
- When
- After the claim has been unpaid 90 days after last furnishing, and within 1 year after last furnishing
- Served on or filed with
- Filed in the county where the contract was performed, against the contractor and surety
- Notarization
- Not required
- If the government entity failed to obtain a required bond, the claimant gives written notice to the agency within 90 days after last furnishing and may sue it directly within 1 year (Utah Code § 14-1-19).
- Since May 6, 2026, bonding on contracts administered by the Division of Facilities Construction and Management is discretionary, and the failure-to-bond remedy does not apply to them. Confirm a bond exists.
Utah Code §§ 63G-6a-1103, 14-1-19
Frequently Asked Questions
Is there a statutory mechanics lien form in Utah?
Utah prescribes the required contents of the Preliminary Notice and the Notice of Construction Lien rather than a verbatim form (Utah Code §§ 38-1a-501, 38-1a-502). The residential Notification of Rights and the homeowner application served with a foreclosure complaint follow forms prescribed by rule.
Does a Utah mechanics lien have to be notarized?
The Notice of Construction Lien must be signed and carry an acknowledgment or certificate required for recording, so it is ordinarily notarized (Utah Code § 38-1a-502). The SCR Preliminary Notice does not need to be notarized.
Does Utah require a notice of intent to lien?
No. Utah has no separate notice of intent to lien. The required advance notice is the Preliminary Notice filed on the State Construction Registry (Utah Code § 38-1a-501).
Where do I file a mechanics lien in Utah?
Record the Notice of Construction Lien with the county recorder in each county where the property is located, then deliver or mail a copy to the owner by certified mail within 30 days (Utah Code § 38-1a-502).
Can a Utah lien be filed against an owner-occupied home?
Often not. Under the Residence Lien Restriction and Lien Recovery Fund Act, an owner who had a qualifying written contract with a licensed contractor and paid in full is protected, and a claimant then seeks payment from the Lien Recovery Fund (Utah Code §§ 38-11-107, 38-11-204).
What form releases a mechanics lien in Utah?
After full payment and a request, the claimant must submit a cancellation to each county recorder within 10 days or pay the greater of $100 per day or actual damages (Utah Code § 38-1a-803). An owner can also record a Notice of Release of Lien and Substitution of Alternate Security (Utah Code § 38-1a-804).
What form do I use for a Utah public project bond claim?
File a Preliminary Notice on Government Project on the SCR, then sue on the payment bond after the claim is unpaid 90 days and within 1 year after last furnishing (Utah Code §§ 38-1b-202, 63G-6a-1103). No separate pre-suit bond claim notice to the prime is required.
Related Utah Resources
Utah Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Utah Notice Requirements
Who must give notice, when, and how.
Utah Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Utah Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Utah law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.