Washington D.C. Mechanics Lien Forms

Washington D.C. Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on Washington D.C. construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A D.C. claimant needs, in order, a sworn and notarized notice of intent recorded with the Recorder of Deeds, a copy mailed to the owner by certified mail within 5 business days, a complaint to enforce within 180 days after recording, and a lis pendens within 10 days after suit (D.C. Code §§ 40-301.02, 40-303.13).

The notice of intent must be recorded during construction or within 90 days after the earlier of completion or termination of the project (§ 40-301.02). It must contain the statutory content, including the net amount due, property description, license and good-standing documents, and any home improvement contract.

Subcontractors must also serve the recorded notice on the owner by leaving it with the owner or agent or posting the premises (§ 40-303.03). Until they do, owner payments to the prime contractor can reduce the fund available to them.

On District public works, a claimant that contracted with a subcontractor rather than the prime gives the prime written notice within 90 days after last furnishing. Suit follows after 90 days and within 1 year after last furnishing (D.C. Code §§ 2-201.02, 2-357.02).

In the District of Columbia, the lien is preserved by one sworn document: the notice of intent, recorded with the Recorder of Deeds during construction or within 90 days after the earlier of completion or termination of the project. The 90 days run from the project, not from the claimant's own last day of work.

The claimant then mails a copy to the owner, subcontractors serve the owner, and suit must follow within 180 days with a lis pendens recorded within 10 days after filing. D.C. has no owner's notice of completion and no statutory lien waiver forms.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Washington D.C. Preliminary Notices

Written Notice of Amount Due

Optional
Who uses it
Subcontractors, suppliers and other lower-tier claimants
When
While the owner still has a balance due to the contractor at least equal to the amount noticed
Served on or filed with
The owner
Notarization
Not required
  • After this notice, the owner's later payment to the prime contractor is prima facie not in good faith under the stated conditions. Contract clauses barring this contact are void to that extent.

D.C. Code § 40-303.02(b)

Washington D.C. Lien Claim and Service

Notice of Intent to Hold a Mechanic's Lien

Notarized
Required When It Applies
Who uses it
Original contractors, subcontractors, suppliers and laborers
When
During construction or within 90 days after the earlier of completion or termination of the project
Served on or filed with
Recorded in the land records of the Recorder of Deeds
Notarization
Required (sworn, notarized statement)
  • The statute prescribes detailed content: parties and addresses, the net amount due, work and dates, legal description and street address, license and good-standing documents, and any home improvement contract. A notice lacking required content is void.
  • An agent or attorney who signs must attach evidence of authority.

D.C. Code §§ 40-301.01, 40-301.02

Certified Mail Copy of Recorded Notice to Owner

Required When It Applies
Who uses it
All lien claimants
When
Within 5 business days after the notice of intent is recorded
Served on or filed with
The owner at its current address, or last known address; if returned undelivered, posted visibly on the property
Notarization
Not required

D.C. Code § 40-301.02(a)(2)

Subcontractor's Service of Notice on Owner

Required When It Applies
Who uses it
Subcontractors and others employed by the original contractor
When
No fixed deadline, but owner payments made before service can reduce the claimant's security
Served on or filed with
Left with the resident owner or agent, or posted on the premises if neither can be found
Notarization
Not required
  • After service, the owner must retain enough of later payments to cover the claim.

D.C. Code §§ 40-303.01, 40-303.03

Washington D.C. Enforcing the Lien

Complaint to Enforce Mechanic's Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 180 days after the notice of intent is recorded
Served on or filed with
Filed in D.C. Superior Court; the prime contractor and other recorded lien claimants are joined when someone other than the prime sues
Notarization
Not required
  • The complaint states the contract, amount due, notice filing and owner service, completion date and property description, and asks for sale of the owner's interest.

D.C. Code §§ 40-303.08, 40-303.13(a)(1)(A)

Notice of Pendency of Action (Lis Pendens)

Notarized
Required When It Applies
Who uses it
Claimants enforcing a lien against the property
When
Within 10 days after filing the enforcement suit
Served on or filed with
Recorded in the land records of the Recorder of Deeds
Notarization
Required (signed by the party or counsel and notarized)
  • Omitting it ends the lien. Where a pre-suit undertaking has already discharged the property, a suit on the undertaking needs no lis pendens (King Carpentry, Inc. v. 1345 K St. SE, LLC, 262 A.3d 1105 (D.C. 2021)).

D.C. Code §§ 40-303.13(a)(1)(B), 42-1207(b)

Washington D.C. Releasing or Bonding Off a Lien

Undertaking to Discharge Lien

Optional
Who uses it
Owners, with a court-approved surety
When
Before suit or during suit; notice of the approval application must be given at least 5 days in advance
Served on or filed with
Filed with the court for approval, with notice to the claimant and affected lienors
Notarization
Surety's oath of financial sufficiency may be required
  • During suit, the owner may instead pay the lien amount plus court-directed interest and costs into court. The claimant then proceeds against the undertaking's obligors.

D.C. Code §§ 40-303.16, 40-303.17, 40-303.18

Entry of Satisfaction

Required When It Applies
Who uses it
Paid lien claimants, on demand of an interested person
When
After the claim and costs are satisfied and demand is made
Served on or filed with
Entered of record; recorded instruments must meet Recorder of Deeds notarization requirements
Notarization
Not required by the statute; the Recorder requires notarized signatures for recording
  • Failure or refusal carries a $50 forfeiture plus resulting damages. A recorded lis pendens must also be released, generally within 30 days after the case ends.

D.C. Code §§ 40-303.15, 42-1207

Washington D.C. Owner Notices and Forms

Demand for Statement of Contract Terms and Owner's Response

Optional
Who uses it
Subcontractors demand; owners or agents respond
When
No fixed deadline
Served on or filed with
The owner or its authorized agent
Notarization
Not required
  • The owner states the contract terms and the amount due or to become due. An owner who refuses or gives a willfully false statement may lose credit for earlier payments.

D.C. Code § 40-303.05

Washington D.C. Public Works and Payment Bond Claims

Written Notice of Bond Claim

Required When It Applies
Who uses it
Claimants that contracted with a subcontractor and have no contract with the bonded prime
When
Within 90 days after the claimant's last labor or materials
Served on or filed with
The prime contractor; registered mail under § 2-201.02, or personal or receipted delivery for bonds under § 2-357.02
Notarization
Not required
  • The notice states with substantial accuracy the amount claimed and the party supplied. Identify which statute governs the bond before choosing the delivery method.

D.C. Code §§ 2-201.02, 2-357.02

Suit on Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded District projects
When
After 90 days unpaid and within 1 year after the claimant's last labor or materials
Served on or filed with
D.C. Superior Court; under § 2-201.02 the suit is brought in the District's name for the claimant's use
Notarization
Not required
  • A claimant may apply, with an affidavit, for certified copies of the bond and contract.

D.C. Code §§ 2-201.02, 2-201.03, 2-357.02

Frequently Asked Questions

Is there a statutory mechanic's lien form in D.C.?

No verbatim form exists. D.C. Code § 40-301.02(b) prescribes detailed content for the notice of intent, and a notice missing required content is void. Section 40-301.03 contains definitions, not a form.

Does a D.C. mechanic's lien have to be notarized?

Yes. The notice of intent must include a sworn, notarized statement (D.C. Code § 40-301.02(b)). The lis pendens recorded after suit must also be notarized (§ 40-303.13).

When is the D.C. mechanic's lien deadline?

The notice of intent must be recorded during construction or within 90 days after the earlier of completion or termination of the project (D.C. Code § 40-301.02). The period runs from the project's completion or termination, not from the claimant's own last day of work.

Does D.C. have a notice of completion?

No. The D.C. mechanic's lien chapter has no owner's notice of completion. Actual completion or termination of the project controls the 90-day recording period.

What form releases a mechanic's lien in D.C.?

A paid claimant enters satisfaction on demand (D.C. Code § 40-303.15). An owner may discharge a disputed lien with a court-approved undertaking before or during suit, or by paying the amount into court (§§ 40-303.16, 40-303.17).

What form do I use for a D.C. public project bond claim?

D.C. prescribes no template. A claimant that contracted with a subcontractor gives the prime contractor written notice of the amount and the party supplied within 90 days after last furnishing, then sues after 90 days and within 1 year (D.C. Code §§ 2-201.02, 2-357.02).

How long do I have to enforce a D.C. mechanic's lien?

The complaint must be filed within 180 days after the notice of intent is recorded, and a notarized lis pendens must be recorded within 10 days after filing (D.C. Code § 40-303.13). Missing either step ends the lien.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.