HomeWashingtonLate Preliminary Notice
WA Late Preliminary Notice

What Happens If You Send a Preliminary Notice Late in Washington?

The Lien Shrinks Instead of Dying, Which Makes Washington Different From Most States

Washington Does Not Have a Notice Deadline

In most states a preliminary notice has a hard deadline running forward from first furnishing, and blowing it forfeits the lien. Washington does not work that way. RCW 60.04.031(1) says the Notice of Right to Claim Lien may be given at any time.

What the statute limits is coverage, not timing. The notice protects lien rights only for professional services, materials, or equipment furnished after a date 60 days before the notice is mailed by certified or registered mail, or personally served, on the owner or reputed owner.

For new construction of a single-family residence, that window is 10 days rather than 60.

What a Late Notice Actually Costs

Run the arithmetic. A subcontractor furnishes from January through August and serves its notice on August 1. The notice reaches back 60 days to June 2. Everything furnished from January through June 1 is outside the lien. The lien is valid, timely, and enforceable, and covers a fraction of the balance.

The damage is silent. Nothing about the recording process flags it. A claimant can record inside the 90-day window, foreclose inside the 8 months, and only discover at valuation that most of the claim was never protected.

What a Missing Notice Costs

Different question, worse answer. Under RCW 60.04.031(6) a lien cannot be enforced at all unless the claimant complied with the applicable provisions of the notice section. Late is survivable. Absent is not, for a claimant who owed one.

The Only Correct Practice

Serve the notice when the contract is signed or the purchase order is accepted. There is no advantage to waiting and no penalty for sending one you did not owe. Every day of delay is a day of furnishing that falls out of the look-back.

Frequently Asked Questions

Is a late preliminary notice fatal in Washington?

No. RCW 60.04.031(1) permits the notice at any time. A late notice reduces coverage rather than voiding the lien: it protects only what was furnished in the 60 days before service, or 10 days on new single-family construction.

What is the difference between a late notice and no notice in Washington?

A late notice shrinks the lien to the look-back window. No notice, where one was required, makes the lien unenforceable entirely under RCW 60.04.031(6).

When is the Washington look-back only 10 days?

On new construction of a single-family residence. The shorter window is keyed to new single-family construction, not to whether the owner occupies the property.

Can I fix a late notice in Washington?

Only going forward. Serving the notice now starts protecting furnishing from that date and reaches back the applicable 60 or 10 days. Nothing recovers furnishing that fell outside the window before service.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us