West Virginia Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on West Virginia construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A West Virginia subcontractor needs three core documents in order: a sworn Notice of Mechanic's Lien served on the owner, the same notice recorded with the county clerk, both within 100 days after completing its subcontract, and a suit to enforce within 6 months after recording (W. Va. Code §§ 38-2-9, 38-2-34).
Owner service is required of subcontractors, suppliers to a contractor or subcontractor, and laborers working for one (W. Va. Code §§ 38-2-9, 38-2-11, 38-2-13). A general contractor, a supplier to the owner, and a laborer for the owner only record within 100 days (W. Va. Code §§ 38-2-8, 38-2-10, 38-2-12).
West Virginia has no mandatory preliminary notice, but a laborer or other employee of a contractor may give the owner an optional written preliminary notice before working (W. Va. Code § 38-2-20). An owner may also demand an itemized account, which must be furnished within 10 days (W. Va. Code § 38-2-19).
On public buildings, no lien attaches; the contractor must furnish a payment bond that is recorded before the contract takes effect. The statute prescribes no claimant notice or suit deadline, so follow the bond's notice terms and sue before its stated deadline (W. Va. Code § 38-2-39).
West Virginia mechanic's lien law, W. Va. Code § 38-2-1 and following, prescribes sworn notice forms for each type of claimant. The core document is the Notice of Mechanic's Lien, recorded with the county clerk within 100 days. Subcontractors and claimants working for a contractor or subcontractor must also serve a more detailed notice on the owner within the same 100 days.
This page describes each West Virginia document a claimant, owner, or public works claimant uses, who uses it, when it is due, and where it goes. Public buildings are protected by the contractor's payment bond under § 38-2-39 rather than a lien.
West Virginia Preliminary Notices
Preliminary Notice to Owner
- Who uses it
- Laborers and others employed by a person contracting with the owner
- When
- Before doing work or furnishing materials or machinery
- Served on or filed with
- The owner
- Notarization
- Not required
- The notice states that the claimant will look to the owner if its employer does not pay. It does not replace serving and recording the Notice of Mechanic's Lien within 100 days.
W. Va. Code § 38-2-20
West Virginia Lien Claim and Service
Notice of Mechanic's Lien (Recorded)
- Who uses it
- General contractors, subcontractors, suppliers, laborers, and design professionals
- When
- Within 100 days after completing the contract or subcontract, ceasing to furnish materials, or ceasing work
- Served on or filed with
- Recorded with the clerk of the county commission of the county where the property is located
- Notarization
- Required; the statutory form is sworn by affidavit
- The statutory model identifies the amount claimed, the owner's interest, the property, and the buildings or improvements charged.
- A separate lien for labor against an incorporated company has a 90-day deadline (W. Va. Code § 38-2-32).
W. Va. Code §§ 38-2-8 to 38-2-13
Notice of Mechanic's Lien Served on Owner
- Who uses it
- Subcontractors, suppliers to a contractor or subcontractor, and laborers working for a contractor or subcontractor
- When
- Within 100 days after completing the subcontract, ceasing to furnish materials, or ceasing work
- Served on or filed with
- The owner or the owner's authorized agent, by a method valid for serving a legal notice or summons
- Notarization
- Required; sworn
- The served notice requires more detail than the recorded one, including the contracting chain and, for suppliers and laborers, an itemized account.
- If the owner is a nonresident or cannot be found, the claimant may publish and post the notice (W. Va. Code § 38-2-15).
W. Va. Code §§ 38-2-9, 38-2-11, 38-2-13
West Virginia Enforcing the Lien
Suit to Enforce Mechanic's Lien
- Who uses it
- Lien claimants
- When
- Within 6 months after recording the Notice of Mechanic's Lien
- Served on or filed with
- Filed in the circuit court for the county where the property is located
- Notarization
- Not required by the lien statute
- A timely suit by another lienholder on the same property also preserves the lien, and other lienholders may intervene.
- A lis pendens is not a separate condition of preserving a recorded lien (W. Va. Code § 55-11-2).
W. Va. Code § 38-2-34
West Virginia Releasing or Bonding Off a Lien
Release or Discharge of Lien
- Who uses it
- A lien creditor or assignee that has been paid in full
- When
- When the recorded lien debt is fully paid
- Served on or filed with
- Entered by the county clerk as a marginal discharge, or a release recorded with the county clerk
- Notarization
- A separately recorded release must be acknowledged for recording
- If the creditor refuses, the person entitled to the release may ask the circuit court to direct the clerk to discharge the lien at the refusing party's cost (W. Va. Code § 38-2-37).
W. Va. Code § 38-2-36(a)
Petition for Cash Escrow Release of Lien
- Who uses it
- Owners and others against whom a lien is claimed
- When
- After the lien is filed, following notice to the lien creditor of the time and place of the application
- Served on or filed with
- Filed in the circuit court with jurisdiction to enforce the lien; notice to the lien creditor by registered mail, return receipt requested
- Notarization
- Not required
- The cash deposit equals the amount claimed and may be increased for interest. West Virginia does not provide a general right to substitute a surety bond after a lien is filed.
- If no validity action is filed within 6 months after the lien was filed, the depositor may move for return of the escrow.
W. Va. Code § 38-2-36(b)
West Virginia Owner Notices and Forms
Demand of Account by Owner
- Who uses it
- Owners
- When
- At any time; the claimant must respond within 10 days after receiving the demand
- Served on or filed with
- The subcontractor, laborer, supplier, or other covered person
- Notarization
- Not required
- A claimant that fails to furnish an itemized account within 10 days loses its lien for work and materials furnished before the demand.
W. Va. Code § 38-2-19
Recorded General Contract and Contractor's Bond
- Who uses it
- Owners and general contractors
- When
- Recorded before construction begins
- Served on or filed with
- Recorded with the county clerk of the county where the property is located
- Notarization
- Required; the statutory bond form contains a notarial acknowledgment
- Recording the contract with a bond equal to the contract price limits the owner's lien exposure to the contract price.
W. Va. Code §§ 38-2-22, 38-2-24
West Virginia Public Works and Payment Bond Claims
Public Building Payment Bond
- Who uses it
- Contractors and sureties on public building contracts
- When
- Executed and delivered before the contract becomes effective; recorded immediately upon acceptance
- Served on or filed with
- Delivered to the public body's secretary or records custodian and recorded in each county where the work occurs
- Notarization
- Not required by the statute; recording requirements apply
- The contract is not binding until the bond is executed, delivered, and recorded. Obtain a copy of the recorded bond at the start of the job.
W. Va. Code § 38-2-39
Claim and Suit on Public Payment Bond
- Who uses it
- Unpaid subcontractors, suppliers, and laborers on public buildings
- When
- As the bond requires; the statute sets no claimant notice or suit deadline
- Served on or filed with
- The prime contractor and the surety under the bond's notice terms; suit in a court with jurisdiction
- Notarization
- Not required by statute
- Calendar the earliest deadline stated in the bond and sue before it. A bond clause shortening suit to less than 2 years may be unenforceable (W. Va. Code § 33-6-14; Gateway Communications v. John Hess, Inc., 208 W. Va. 505 (2000)).
W. Va. Code § 38-2-39
Frequently Asked Questions
Is there a statutory mechanics lien form in West Virginia?
Yes. The Code supplies sworn model notices for each type of claimant, which are sufficient in form and effect (W. Va. Code §§ 38-2-8 to 38-2-13). Failure to substantially comply with the notice, recording, and timing requirements can discharge the lien (W. Va. Code § 38-2-14).
Does a West Virginia mechanics lien have to be notarized?
Yes. The statutory Notice of Mechanic's Lien is sworn by affidavit before a notary or other officer (W. Va. Code § 38-2-8).
Where do I file a mechanics lien in West Virginia?
Record the Notice of Mechanic's Lien with the clerk of the county commission where the property is located within 100 days. Subcontractors and lower-tier claimants must also serve the owner within the same 100 days (W. Va. Code §§ 38-2-8 to 38-2-13).
Is a preliminary notice required in West Virginia?
No. West Virginia has no mandatory preliminary notice. An employee of a contractor may give the owner an optional written preliminary notice before working (W. Va. Code § 38-2-20).
What form releases a mechanics lien in West Virginia?
After full payment, the lien creditor causes the county clerk to enter a discharge or records a release (W. Va. Code § 38-2-36(a)). An owner can also obtain a court-ordered release by depositing cash in escrow (W. Va. Code § 38-2-36(b)).
Can an owner of a home avoid a subcontractor's lien in West Virginia?
On qualifying residential property, the owner may assert a complete or partial defense that it owed the contractor nothing, or less than the lien amount (W. Va. Code §§ 38-2-21, 38-2-34).
What form do I use for a West Virginia public project bond claim?
The statute prescribes no claim form or notice deadline. Obtain the recorded payment bond, give written notice to the prime contractor and surety as the bond requires, and sue before the bond's deadline (W. Va. Code § 38-2-39).
Related West Virginia Resources
West Virginia Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
West Virginia Notice Requirements
Who must give notice, when, and how.
West Virginia Lien Waivers
Statutory forms, waiver types, and enforceability rules.
West Virginia Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about West Virginia law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.