Every notice, lien, enforcement, release, and bond claim document used on West Virginia construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A West Virginia subcontractor needs three core documents in order: a sworn Notice of Mechanic's Lien served on the owner, the same notice recorded with the county clerk, both within 100 days after completing its subcontract, and a suit to enforce within 6 months after recording (W. Va. Code §§ 38-2-9, 38-2-34).

Owner service is required of subcontractors, suppliers to a contractor or subcontractor, and laborers working for one (W. Va. Code §§ 38-2-9, 38-2-11, 38-2-13). A general contractor, a supplier to the owner, and a laborer for the owner only record within 100 days (W. Va. Code §§ 38-2-8, 38-2-10, 38-2-12).

West Virginia has no mandatory preliminary notice, but a laborer or other employee of a contractor may give the owner an optional written preliminary notice before working (W. Va. Code § 38-2-20). An owner may also demand an itemized account, which must be furnished within 10 days (W. Va. Code § 38-2-19).

On public buildings, no lien attaches; the contractor must furnish a payment bond that is recorded before the contract takes effect. The statute prescribes no claimant notice or suit deadline, so follow the bond's notice terms and sue before its stated deadline (W. Va. Code § 38-2-39).

West Virginia mechanic's lien law, W. Va. Code § 38-2-1 and following, prescribes sworn notice forms for each type of claimant. The core document is the Notice of Mechanic's Lien, recorded with the county clerk within 100 days. Subcontractors and claimants working for a contractor or subcontractor must also serve a more detailed notice on the owner within the same 100 days.

This page describes each West Virginia document a claimant, owner, or public works claimant uses, who uses it, when it is due, and where it goes. Public buildings are protected by the contractor's payment bond under § 38-2-39 rather than a lien.

West Virginia Preliminary Notices

Preliminary Notice to Owner

Optional
Who uses it
Laborers and others employed by a person contracting with the owner
When
Before doing work or furnishing materials or machinery
Served on or filed with
The owner
Notarization
Not required
  • The notice states that the claimant will look to the owner if its employer does not pay. It does not replace serving and recording the Notice of Mechanic's Lien within 100 days.

W. Va. Code § 38-2-20

West Virginia Lien Claim and Service

Notice of Mechanic's Lien (Recorded)

Statutory Form
Notarized
Required When It Applies
Who uses it
General contractors, subcontractors, suppliers, laborers, and design professionals
When
Within 100 days after completing the contract or subcontract, ceasing to furnish materials, or ceasing work
Served on or filed with
Recorded with the clerk of the county commission of the county where the property is located
Notarization
Required; the statutory form is sworn by affidavit
  • The statutory model identifies the amount claimed, the owner's interest, the property, and the buildings or improvements charged.
  • A separate lien for labor against an incorporated company has a 90-day deadline (W. Va. Code § 38-2-32).

W. Va. Code §§ 38-2-8 to 38-2-13

Notice of Mechanic's Lien Served on Owner

Statutory Form
Notarized
Required When It Applies
Who uses it
Subcontractors, suppliers to a contractor or subcontractor, and laborers working for a contractor or subcontractor
When
Within 100 days after completing the subcontract, ceasing to furnish materials, or ceasing work
Served on or filed with
The owner or the owner's authorized agent, by a method valid for serving a legal notice or summons
Notarization
Required; sworn
  • The served notice requires more detail than the recorded one, including the contracting chain and, for suppliers and laborers, an itemized account.
  • If the owner is a nonresident or cannot be found, the claimant may publish and post the notice (W. Va. Code § 38-2-15).

W. Va. Code §§ 38-2-9, 38-2-11, 38-2-13

West Virginia Enforcing the Lien

Suit to Enforce Mechanic's Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 6 months after recording the Notice of Mechanic's Lien
Served on or filed with
Filed in the circuit court for the county where the property is located
Notarization
Not required by the lien statute
  • A timely suit by another lienholder on the same property also preserves the lien, and other lienholders may intervene.
  • A lis pendens is not a separate condition of preserving a recorded lien (W. Va. Code § 55-11-2).

W. Va. Code § 38-2-34

West Virginia Releasing or Bonding Off a Lien

Release or Discharge of Lien

Required When It Applies
Who uses it
A lien creditor or assignee that has been paid in full
When
When the recorded lien debt is fully paid
Served on or filed with
Entered by the county clerk as a marginal discharge, or a release recorded with the county clerk
Notarization
A separately recorded release must be acknowledged for recording
  • If the creditor refuses, the person entitled to the release may ask the circuit court to direct the clerk to discharge the lien at the refusing party's cost (W. Va. Code § 38-2-37).

W. Va. Code § 38-2-36(a)

Petition for Cash Escrow Release of Lien

Optional
Who uses it
Owners and others against whom a lien is claimed
When
After the lien is filed, following notice to the lien creditor of the time and place of the application
Served on or filed with
Filed in the circuit court with jurisdiction to enforce the lien; notice to the lien creditor by registered mail, return receipt requested
Notarization
Not required
  • The cash deposit equals the amount claimed and may be increased for interest. West Virginia does not provide a general right to substitute a surety bond after a lien is filed.
  • If no validity action is filed within 6 months after the lien was filed, the depositor may move for return of the escrow.

W. Va. Code § 38-2-36(b)

West Virginia Owner Notices and Forms

Demand of Account by Owner

Optional
Who uses it
Owners
When
At any time; the claimant must respond within 10 days after receiving the demand
Served on or filed with
The subcontractor, laborer, supplier, or other covered person
Notarization
Not required
  • A claimant that fails to furnish an itemized account within 10 days loses its lien for work and materials furnished before the demand.

W. Va. Code § 38-2-19

Recorded General Contract and Contractor's Bond

Statutory Form
Notarized
Optional
Who uses it
Owners and general contractors
When
Recorded before construction begins
Served on or filed with
Recorded with the county clerk of the county where the property is located
Notarization
Required; the statutory bond form contains a notarial acknowledgment
  • Recording the contract with a bond equal to the contract price limits the owner's lien exposure to the contract price.

W. Va. Code §§ 38-2-22, 38-2-24

West Virginia Public Works and Payment Bond Claims

Public Building Payment Bond

Required When It Applies
Who uses it
Contractors and sureties on public building contracts
When
Executed and delivered before the contract becomes effective; recorded immediately upon acceptance
Served on or filed with
Delivered to the public body's secretary or records custodian and recorded in each county where the work occurs
Notarization
Not required by the statute; recording requirements apply
  • The contract is not binding until the bond is executed, delivered, and recorded. Obtain a copy of the recorded bond at the start of the job.

W. Va. Code § 38-2-39

Claim and Suit on Public Payment Bond

Required When It Applies
Who uses it
Unpaid subcontractors, suppliers, and laborers on public buildings
When
As the bond requires; the statute sets no claimant notice or suit deadline
Served on or filed with
The prime contractor and the surety under the bond's notice terms; suit in a court with jurisdiction
Notarization
Not required by statute
  • Calendar the earliest deadline stated in the bond and sue before it. A bond clause shortening suit to less than 2 years may be unenforceable (W. Va. Code § 33-6-14; Gateway Communications v. John Hess, Inc., 208 W. Va. 505 (2000)).

W. Va. Code § 38-2-39

Frequently Asked Questions

Is there a statutory mechanics lien form in West Virginia?

Yes. The Code supplies sworn model notices for each type of claimant, which are sufficient in form and effect (W. Va. Code §§ 38-2-8 to 38-2-13). Failure to substantially comply with the notice, recording, and timing requirements can discharge the lien (W. Va. Code § 38-2-14).

Does a West Virginia mechanics lien have to be notarized?

Yes. The statutory Notice of Mechanic's Lien is sworn by affidavit before a notary or other officer (W. Va. Code § 38-2-8).

Where do I file a mechanics lien in West Virginia?

Record the Notice of Mechanic's Lien with the clerk of the county commission where the property is located within 100 days. Subcontractors and lower-tier claimants must also serve the owner within the same 100 days (W. Va. Code §§ 38-2-8 to 38-2-13).

Is a preliminary notice required in West Virginia?

No. West Virginia has no mandatory preliminary notice. An employee of a contractor may give the owner an optional written preliminary notice before working (W. Va. Code § 38-2-20).

What form releases a mechanics lien in West Virginia?

After full payment, the lien creditor causes the county clerk to enter a discharge or records a release (W. Va. Code § 38-2-36(a)). An owner can also obtain a court-ordered release by depositing cash in escrow (W. Va. Code § 38-2-36(b)).

Can an owner of a home avoid a subcontractor's lien in West Virginia?

On qualifying residential property, the owner may assert a complete or partial defense that it owed the contractor nothing, or less than the lien amount (W. Va. Code §§ 38-2-21, 38-2-34).

What form do I use for a West Virginia public project bond claim?

The statute prescribes no claim form or notice deadline. Obtain the recorded payment bond, give written notice to the prime contractor and surety as the bond requires, and sue before the bond's deadline (W. Va. Code § 38-2-39).