Every notice, lien, enforcement, release, and bond claim document used on Arizona construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Arizona claimant needs, in order, a Preliminary Twenty-Day Notice within 20 days after first furnishing, a sworn Notice and Claim of Lien recorded within 120 days after completion, and a foreclosure suit with a recorded lis pendens within 6 months after recording (A.R.S. §§ 33-992.01, 33-993, 33-998).

A late preliminary notice still protects work furnished within the 20 days before it was given and afterward. If the estimated total rises 30 percent or more above the notice, a supplemental notice is required (§ 33-992.01). Wage laborers are exempt on private projects.

If the owner records a valid Notice of Completion and mails the required copies within 15 days, the lien deadline becomes 60 days after recording (§ 33-993). Completion is a statutory event, not the claimant's own last day of work.

On public works, a claimant that contracted with a subcontractor of the bonded prime gives the prime a twenty-day notice and a 90-day notice after last furnishing. Suit follows after 90 days and within 1 year after last furnishing (A.R.S. § 34-223).

Arizona lien rights start with the Preliminary Twenty-Day Notice, a statutory form served on the owner, original contractor, construction lender and hiring party. Without it, there is no lien for work furnished more than 20 days before the notice.

The lien itself is a sworn Notice and Claim of Lien recorded with the county recorder, followed by foreclosure and a lis pendens. Arizona also offers stop notices to owners and lenders, four mandatory statutory lien waiver forms, and payment bond claims on public works under A.R.S. § 34-223.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Arizona Preliminary Notices

Preliminary Twenty-Day Notice

Statutory Form
Required When It Applies
Who uses it
All lien claimants other than wage laborers, including original contractors
When
Within 20 days after first furnishing; a late notice protects work from 20 days before it is given
Served on or filed with
The owner or reputed owner, original contractor, construction lender if any, and the hiring party
Notarization
Not required
  • Serve by first-class mail with certificate of mailing, or registered or certified mail; service is complete on mailing. A supplemental notice is needed if the estimate rises 30 percent or more.
  • Since 2024, a notice is not defective solely for missing the prescribed boldface or type size.

A.R.S. § 33-992.01

Amended Preliminary Twenty-Day Notice

Statutory Form
Required When It Applies
Who uses it
Claimants whose notice was inaccurate after receiving corrected project information
When
Within 30 days after receiving the corrected information
Served on or filed with
The same statutory recipients
Notarization
Not required
  • Owners must answer a claimant's written request for project information, including any recorded payment bond, within 10 days.

A.R.S. § 33-992.01(J), (K)

Stop Notice and Bonded Stop Notice

Notarized
Optional
Who uses it
Lien claimants other than the original contractor (to the owner); any lien claimant, including the original contractor (to the lender)
When
Before the lien recording period expires, or within 30 days after a written demand from the owner or lender
Served on or filed with
The owner, under § 33-1054, or the construction lender office holding the construction funds, under § 33-1055
Notarization
Required (signed and verified)
  • A bonded stop notice carries a surety bond of 150 percent of the claim. Missing a demand forfeits stop notice rights for that work, not lien rights. Owner-occupied dwellings are excluded.
  • Suit on a stop notice may begin 10 days after service and must begin within 3 months after the lien recording period expires.

A.R.S. §§ 33-1051 to 33-1058

Arizona Lien Claim and Service

Notice and Claim of Lien

Notarized
Required When It Applies
Who uses it
All lien claimants
When
Within 120 days after statutory completion, or 60 days after an effective Notice of Completion is recorded
Served on or filed with
Recorded with the county recorder; a copy is served on the owner within a reasonable time if the owner can be found in the county
Notarization
Required (made under oath by the claimant or a person with knowledge)
  • Attach the written contract or state the oral terms, the net demand, completion date, preliminary notice date, a copy of the notice and proof of mailing.
  • Proof of mailing is the recipient's signed acknowledgment or, if not returned within 30 days, an affidavit of mailing.

A.R.S. §§ 33-992.02, 33-993

Arizona Enforcing the Lien

Complaint to Foreclose Lien and Lis Pendens

Required When It Applies
Who uses it
Lien claimants
When
Suit within 6 months after recording; lis pendens within 5 days after filing and within the 6-month period
Served on or filed with
Complaint filed in superior court; lis pendens recorded with the county recorder
Notarization
Not required
  • Filing on the last day does not give five more days to record the lis pendens beyond the 6 months. A lien-asserting answer or cross-claim in another claimant's suit also counts.

A.R.S. §§ 33-998, 12-1191

Arizona Releasing or Bonding Off a Lien

Bond to Discharge Lien

Optional
Who uses it
Owners, contractors, subcontractors, mortgagees or other lien creditors
When
After the lien is recorded, before or after foreclosure begins
Served on or filed with
Recorded with the county recorder and served on the claimant within a reasonable time
Notarization
Not required
  • The bond equals 150 percent of the lien demand with a corporate surety. Recording discharges the property. A claimant with a pending suit must add the principal and surety within 90 days after receiving the bond.

A.R.S. § 33-1004

Release of Mechanic's and Materialman's Lien

Required When It Applies
Who uses it
Lienholders
When
Within 20 days after satisfaction, or within 20 days after an owner-occupant's written request to release a prohibited lien
Served on or filed with
Issued to the owner as a recordable instrument for the county recorder
Notarization
Not required by the lien statute; recording rules apply
  • Failure to release carries $1,000 plus actual damages. A dismissed foreclosure also requires release of the lis pendens.

A.R.S. § 33-1006

Arizona Owner Notices and Forms

Notice of Completion

Statutory Form
Notarized
Optional
Who uses it
Owners or their agents
When
After statutory completion; copies and recording information must be mailed within 15 days after recording
Served on or filed with
Recorded with the county recorder; copies mailed by certified or registered mail to the original contractor and prior preliminary notice claimants
Notarization
Required (signed and verified, with acknowledgment)

A.R.S. § 33-993

Payment Bond in Lieu of Lien Rights

Optional
Who uses it
Owners who require the contractor to furnish a bond
When
Recorded with the contract; protection operates from recording
Served on or filed with
Recorded with the county recorder, with the contract containing the legal description
Notarization
Not required
  • Once recorded, claimants look to the bond rather than the property, except a claimant with a direct written contract with the owner.

A.R.S. § 33-1003

Contractor's Notice of Intent to Dispute Lien

Required When It Applies
Who uses it
Original contractors receiving a lien claim forwarded by the owner
When
Within 10 days after receiving the owner's copy of the claim
Served on or filed with
The owner
Notarization
Not required
  • Without it, the contractor is treated as assenting to the claim, and the owner may withhold and recoup.

A.R.S. § 33-994

Arizona Public Works and Payment Bond Claims

Public Works Preliminary Twenty-Day Notice and 90-Day Notice

Required When It Applies
Who uses it
Claimants with a direct contract with a subcontractor of the bonded prime but none with the prime
When
Twenty-day notice within 20 days after first furnishing; 90-day notice within 90 days after the last furnishing claimed
Served on or filed with
The bonded prime contractor; the 90-day notice by any means giving written third-party verification of delivery to its office, place of business or residence
Notarization
Not required
  • The 90-day notice states the amount claimed with substantial accuracy and the party supplied. Registered or certified mail is not required.

A.R.S. § 34-223

Suit on Public Payment Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public works
When
After 90 days without payment and within 1 year after the claimant's last labor or materials
Served on or filed with
Filed in court in the claimant's name against the contractor and surety
Notarization
Not required
  • Mechanics liens cannot attach to public property. A claimant may apply for certified copies of the bond and contract.

A.R.S. §§ 34-222, 34-223

Frequently Asked Questions

Is there a statutory mechanics lien form in Arizona?

Arizona prescribes the Preliminary Twenty-Day Notice form (A.R.S. § 33-992.01), the Notice of Completion form (§ 33-993) and four lien waiver forms (§ 33-1008). The Notice and Claim of Lien has prescribed contents and attachments but no fill-in template (§ 33-993).

Does an Arizona mechanics lien have to be notarized?

The Notice and Claim of Lien must be made under oath by the claimant or someone with knowledge of the facts (A.R.S. § 33-993). The preliminary notice and the lien waivers need no notarization.

Where do I file a mechanics lien in Arizona?

The Notice and Claim of Lien is recorded with the county recorder where the property is located, within 120 days after completion or 60 days after an effective Notice of Completion (A.R.S. § 33-993). A copy is then served on the owner within a reasonable time.

What happens if I miss the Arizona 20-day notice deadline?

A late Preliminary Twenty-Day Notice still protects labor and materials furnished within the 20 days before it was given and afterward (A.R.S. § 33-992.01). Work furnished earlier is not covered, so serve the notice at the start of every job.

What form releases a mechanics lien in Arizona?

A paid lienholder must issue a release within 20 days after satisfaction, or face $1,000 plus actual damages (A.R.S. § 33-1006). An owner may also record a bond for 150 percent of the claim, which discharges the property (§ 33-1004).

What form do I use for an Arizona public project bond claim?

A claimant that contracted with a subcontractor of the bonded prime serves a twenty-day notice and, within 90 days after last furnishing, a written notice of the amount claimed by any means with third-party delivery verification. Suit follows within 1 year after last furnishing (A.R.S. § 34-223).

Does missing an Arizona stop notice demand forfeit my lien?

No. Failing to serve a stop notice within 30 days after an owner's or lender's written demand forfeits stop notice rights for the work described, not mechanics lien rights (A.R.S. §§ 33-1054, 33-1055).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.