All Articles
December 15, 2019Guide4 min read

Private Project Performance Bonds VS Mechanics Lien

T
By Thomas Emalfarb, Esq. · Updated January 19, 2024

What are private project performance bonds and how do they work? Construction is a very risky business but several tools have been developed over time to reduce these risks. You've likely seen many of these tools when working on construction jobs including insurance, retention rights, off-set, and risk apportioning indemnity agreements. One powerful tool which is not regularly used on private construction projects are payment and performance bonds.

When public money is funding the construction

On public projects, payment and performance bonds are by law because the "owner" is a governmental entity using tax dollars to fund the project. Since public money is funding the construction, extra guarantees are needed to ensure the successful completion of the project to prevent loss of our hard-earned tax dollars. Also, mechanic liens are not allowed to be filed against public property, so the payment bond acts as the alternative protection for non-payment of subcontractors and suppliers.

Private Project Performance Bonds

Payment and performance bonds can also be used for private projects even when no public funds are at risk and filing mechanic liens against the project property is an option. These bonds on a private project provide the owner with the same protections as on a public construction project. The difference is, the contract between the owner and general contractor requires the general contractor to furnish a payment and performance bond. The general contractor purchases the bonds from a bonding company, often referred to as a "surety", for a fee equal to a small percentage of the bond value. The surety then acts as a guarantor for the general contractor's contractual payment and performance obligations.

What happens when there's a failure to perform?

If the general contractor or one of its subcontractors is unable to complete a portion of the work correctly or on time, the private project performance bonds kicks in. The surety assesses what is causing the delay or the faulty work and acts as a liaison between the relevant parties to formula a plan to correct the work. If the surety is unable to fix the problem by working with the parties, then the surety has two options.

The "Tender Option"

The first option is the "Tender Option" which means the surety offers the owner a new contractor who can take over the work. The owner will remove the previous contractor and work with the new contractor to complete the work. The second option is the "Take Over Option" which means the surety itself takes over the work completes the work itself. If either of these options are used, the general contractor must reimburse the surety for the costs of fixing the performance problem.

What happens when there's a failure to pay?

As the owner makes payments to the general contractor for the work and materials to complete the project, the owner expects those payments to flow down to every tier of subcontractor and supplier under the general contract. If a subcontractor or supplier is not being paid for its work or materials, it must submit a claim against the private project performance bonds to the surety. Like with the performance bond, the surety steps in to investigate the non-payment claim and assist with a resolution, if possible.

the surety will pay you for your work

If the claim is found to be legitimate and you are owed money that has not been paid, then the surety will pay you for your work and materials. The surety will then go to the general contractor to be reimbursed for the money it paid to you. Also like the performance bond scenario, if the general contractor is not the cause for the non-payment, the general contractor must still reimburse the surety and seek its own reimbursement from the defaulting party.

So should I use a Private payment bond or my state's mechanics lien system?

It may sound like the private project performance bonds are a lot easier than the typical mechanics lien process. While this is somewhat true, there may still be several requirements you must meet to file a proper bond claim. Each bonding company has its own rules for submitting a claim for non-payment. While these requirements may be simpler than a typical state mechanics lien system, you should still seek assistance from a construction payment expert.

performance bonds
payment bonds
surety
private projects
mechanics lien
bond claim

Related Articles

Unpaid-balance lien states infographic - in unpaid balance lien states you are racing against two deadlines: the statutory deadline to file a mechanics lien, and the moment the owner pays the general contractor in full, which can limit or eliminate your lien rights.
June 26, 2026Guide

Unpaid-Balance Lien States: Why You're Racing Against Two Deadlines, Not One

In an unpaid-balance lien state, the calendar deadline to record your lien is only half the race. The hidden second deadline is the moment the owner finishes paying the general contractor - because that payment can shrink or erase the fund your lien attaches to. This guide explains both deadlines, why subcontractors and suppliers lose money even when they file 'on time,' and the notice-and-timing strategy that protects your leverage.

Read Article
Connecticut Mechanics Lien Law guide - the lower-tier notice of intent, the 90-day certificate recording deadline, the 30-day owner-service requirement, the one-year foreclosure and lis pendens deadline, the lienable-fund limit, and contractor registration.
June 20, 2026Guide

Connecticut Mechanics Lien Law: Notices, Deadlines, Lien Rights, and Contractor Registration

Connecticut treats original contractors and lower-tier claimants differently. This guide covers the lower-tier notice of intent, the 90-day certificate recording deadline, the 30-day owner-service requirement, the one-year foreclosure-and-lis-pendens deadline, the lienable-fund limit on subcontractor liens, who can claim, and how Home Improvement Act and New Home Construction registration affect enforcement.

Read Article
Delaware Mechanics Lien Law guide - the statement of claim, the 180-day and 120-day filing deadlines, the prior-written-consent rule for tenant work, the $25 threshold, the pleading elements, and contractor registration.
June 20, 2026Guide

Delaware Mechanics Lien Law: Statement of Claim, Deadlines, Lien Rights, and Contractor Registration

Delaware enforces mechanics liens through a strictly construed statement of claim filed in Superior Court. This guide covers the 180-day and 120-day filing deadlines, the prior-written-consent rule for tenant work, the statement-of-claim pleading elements, the $25 threshold, who can claim, and Delaware contractor registration and business licensing.

Read Article
Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us