Can You File a Mechanics Lien on a Public Project in California?
No. The Remedies Are a Stop Payment Notice and the Payment Bond
Public Work Sits Under a Different Title
The mechanics lien chapter is part of the private works title of the Civil Code, and that title applies only to a work of improvement that is not governed by the public works title. Civ. Code §8160. The public works title applies to a work of improvement contracted for by a public entity. Civ. Code §9000.
The public works title gives unpaid claimants two remedies in place of a lien on the property: a stop payment notice to the public entity, and a claim against the payment bond. Civ. Code §9100(a). They may be given or asserted by a person that provides work for a public works contract, if the work is authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of all or part of the contract, and by a laborer. A direct contractor may use neither. Civ. Code §9100(b).
These are the statutory payment security remedies on a public work governed by the public works title. The absence of a lien does not remove contract remedies that are otherwise available to the claimant.
Preliminary Notice on Public Work
Before giving a stop payment notice or asserting a payment bond claim, a claimant must give Preliminary Notice to the public entity and to the direct contractor to which the claimant provides work. A laborer is exempt, and so is a claimant that has a direct contractual relationship with a direct contractor. Civ. Code §9300.
A claimant that owes the notice may give a stop payment notice or assert a bond claim only for work provided within 20 days before giving Preliminary Notice and at any time thereafter. Civ. Code §9304.
The Stop Payment Notice
A stop payment notice is not effective unless it is given within 30 days after a notice of completion, acceptance, or cessation is recorded, or, if no such notice is recorded, within 90 days after cessation or completion. Civ. Code §9356.
Completion of a public work occurs at the earlier of acceptance of the work of improvement by the public entity, or cessation of labor for a continuous period of 60 days. The cessation rule does not apply to a contract awarded under the State Contract Act. Civ. Code §9200.
The notice is given to the public entity, not to the direct contractor. On a state contract it goes to the director of the department that awarded the contract. On any other public contract it goes to the office of the controller, auditor, or other public disbursing officer whose duty it is to make payment, or to the body by which the contract was awarded. Civ. Code §9354.
An action to enforce the stop payment notice against the public entity and the direct contractor may be commenced at any time after 10 days from the date the notice is given, and must be commenced not later than 90 days after expiration of the time within which a stop payment notice must be given. If it is not, the notice ceases to be effective and the public entity releases the withheld funds. Civ. Code §9502.
The Payment Bond
A direct contractor awarded a public works contract involving an expenditure in excess of $25,000 must give a payment bond before commencement of work. Civ. Code §9550(a). The bond must be in an amount not less than 100 percent of the total amount payable under the contract. Civ. Code §9554(a). Section 9550 does not apply to a contract with a state entity as defined in Public Contract Code §7103(d). Civ. Code §9550(e).
A claimant may commence an action on the bond at any time after it ceases to provide work, but not later than six months after the period in which a stop payment notice may be given. Civ. Code §9558. That places the outside date six months after the 30-day or 90-day period in Civ. Code §9356.
A claimant that was required to give Preliminary Notice and did not may still be able to enforce a bond claim by written notice to both the surety and the bond principal, given in compliance with Civ. Code §9562, within 15 days after recordation of a notice of completion, or 75 days after completion of the work of improvement if none is recorded. Civ. Code §9560(b), (c). That route is not available in the circumstances listed in Civ. Code §9560(d), where all progress payments other than amounts disputed in good faith have been paid to the relevant first-tier subcontractor, including where that subcontractor was terminated.
Frequently Asked Questions
Can you file a mechanics lien on a public project in California?
No. The mechanics lien chapter applies only to work not governed by the public works title, and the public works title applies to work contracted for by a public entity. Civ. Code §§8160, 9000. The remedies are a stop payment notice and a payment bond claim. Civ. Code §9100.
What is the deadline for a California public works stop payment notice?
30 days after a notice of completion, acceptance, or cessation is recorded, or 90 days after cessation or completion if none is recorded. Civ. Code §9356.
How long do you have to sue on a California public works payment bond?
Not later than six months after the period in which a stop payment notice may be given under Civ. Code §9356. Civ. Code §9558. The action may be commenced at any time after the claimant ceases to provide work.
Who must give Preliminary Notice on a California public project?
A claimant with no direct contractual relationship with a direct contractor, other than a laborer. The notice goes to the public entity and the direct contractor. Civ. Code §9300.
Can a general contractor use these remedies on a California public project?
No. A direct contractor may not give a stop payment notice or assert a claim against a payment bond under the public works title. Civ. Code §9100(b).
Related California Resources
Explore other critical compliance areas for California construction mechanic lien law.
Notice Requirements
20-day preliminary notice obligations for private works, stop notices, and public works bond claims under California Civil Code
Mechanic Lien Deadlines
Mechanic Lien recording deadlines based on Notice of Completion status, stop notice filing requirements, and public works claim procedures
Mechanic Lien Enforcement Deadlines
90-day suit deadlines, stop notice enforcement, payment bond claim suit timelines, and public works enforcement
California Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in California
California Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in California
California Overview
Return to the main California construction mechanic lien law page