HomeCaliforniaGC Preliminary Notice
CA GC Preliminary Notice

Does a General Contractor Need to Send a Preliminary Notice in California?

Not to the Owner, But a Construction Lender Changes the Answer

No Notice to the Owner

California calls the general contractor a direct contractor, meaning a contractor that has a direct contractual relationship with an owner. Civ. Code §8018.

The general rule in Civ. Code §8200(a) is that a claimant must give Preliminary Notice to the owner or reputed owner, the direct contractor or reputed direct contractor, and the construction lender or reputed construction lender, if any, before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond.

Subdivision (e)(2) narrows that rule for anyone who contracts with the owner. A claimant with a direct contractual relationship with an owner or reputed owner is required to give Preliminary Notice only to the construction lender or reputed construction lender, if any. On a project with no construction lender, a direct contractor has no Preliminary Notice to give.

The Construction Lender Notice

Where the project has a construction lender, the direct contractor's notice is subject to the same timing rule as everyone else's. A Preliminary Notice must be given not later than 20 days after the claimant has first furnished work on the work of improvement. Civ. Code §8204(a).

The consequence is stated in general terms. Compliance with Civ. Code §8200 is a necessary prerequisite to the validity of a lien claim or stop payment notice. Civ. Code §8200(c). The text of the section does not exempt a direct contractor from that sentence. On a lender-financed project, a direct contractor must give the lender notice to preserve its lien rights.

A notice given after the 20th day is still permitted, but it supports a lien, stop payment notice, or payment bond claim only for work performed within 20 days before service of the notice and afterward. Civ. Code §8204(a).

What a Direct Contractor Should Still Calendar

A direct contractor may not enforce a lien unless it records the claim of lien after it completes the direct contract, and before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a Notice of Completion or Notice of Cessation. Civ. Code §8412.

An action to enforce the lien must be commenced within 90 days after the claim of lien is recorded, or the claim of lien expires and is unenforceable. Civ. Code §8460(a).

On a public work the answer is different in kind. A direct contractor may not give a stop payment notice or assert a claim against the payment bond under the public works title. Civ. Code §9100(b).

Frequently Asked Questions

Does a general contractor need a preliminary notice in California?

Not to the owner. Under Civ. Code §8200(e)(2), a claimant with a direct contractual relationship with the owner gives Preliminary Notice only to the construction lender or reputed construction lender, if there is one. On a project with a construction lender, the direct contractor must give that notice to preserve lien rights. Civ. Code §8200(c).

When must a California direct contractor notify the construction lender?

Not later than 20 days after first furnishing work on the work of improvement. Civ. Code §8204(a). A later notice covers only work performed within 20 days before it was served and afterward.

What if there is no construction lender?

Then Civ. Code §8200(e)(2) leaves a direct contractor with no Preliminary Notice to give. The lien recording deadline in Civ. Code §8412 and the 90-day enforcement deadline in Civ. Code §8460 still apply.

Can a California general contractor make a bond claim on a public project?

No. Civ. Code §9100(b) provides that a direct contractor may not give a stop payment notice or assert a claim against a payment bond under the public works title.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us