Does a Material Supplier Need to Send a Preliminary Notice in California?
Yes, and Selling to the Direct Contractor Does Not Change That on Private Work
Suppliers Have Lien Rights, and a Notice Duty
A material supplier is a person that provides material or supplies to be used or consumed in a work of improvement. Civ. Code §8028. A material supplier that provides work authorized for a work of improvement has a lien right. Civ. Code §8400(c).
That right depends on the Preliminary Notice. Before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond, a claimant must give Preliminary Notice to the owner or reputed owner, the direct contractor or reputed direct contractor, and the construction lender or reputed construction lender, if any. Civ. Code §8200(a).
The section has two exceptions, for laborers and for claimants in direct contract with the owner. Civ. Code §8200(e). A supplier selling to the direct contractor or to a subcontractor is inside the general rule and owes notice to all three parties.
When the Supplier Sells Directly to the Owner
A claimant with a direct contractual relationship with an owner or reputed owner is required to give Preliminary Notice only to the construction lender or reputed construction lender, if any. Civ. Code §8200(e)(2). A supplier whose customer is the owner therefore has no notice to give the owner, but does have one to give the lender on a financed project.
Timing, and Why Open Accounts Are Exposed
The notice must be given not later than 20 days after the claimant has first furnished work on the work of improvement. Civ. Code §8204(a).
A supplier that misses that date may still give notice later, but may then record a lien, give a stop payment notice, and assert a payment bond claim only for work performed within 20 days before service of the notice and afterward. Civ. Code §8204(a). On a long-running account, a first notice sent when the account goes past due can leave most of the earlier deliveries outside the lien.
One notice to each required recipient covers all work the supplier provides for the work of improvement. A supplier that furnishes under contracts with more than one subcontractor on the same project must give a separate notice for each contract. Civ. Code §8206.
An Invoice Can Serve as the Notice
If an invoice for material contains the information required by Civ. Code §§8102 and 8202, a copy of the invoice, given in compliance with the statutory notice requirements, is sufficient. Civ. Code §8202(c). The required content includes a general description of the work, an estimate of the total price, and the boldface Notice to Property Owner. Civ. Code §8202(a). An ordinary invoice that lacks those items, or that is sent by a method the statute does not authorize, does not qualify.
Public Projects
On public work, the Preliminary Notice goes to the public entity and the direct contractor to which the claimant provides work. A claimant with a direct contractual relationship with a direct contractor is not required to give it. Civ. Code §9300. A supplier selling to a subcontractor is not within that exemption, and its stop payment notice and payment bond rights reach only work provided within 20 days before the notice and afterward. Civ. Code §9304.
Frequently Asked Questions
Does a material supplier need a preliminary notice in California?
Yes on private work. Civ. Code §8200 requires Preliminary Notice to the owner or reputed owner, the direct contractor, and any construction lender, not later than 20 days after first furnishing. Civ. Code §8204(a). Selling to the direct contractor is not an exemption.
Is any California supplier exempt from notifying the owner?
A supplier with a direct contractual relationship with the owner gives Preliminary Notice only to the construction lender or reputed construction lender, if any. Civ. Code §8200(e)(2).
Can a supplier's invoice count as the Preliminary Notice?
Only if it contains everything required by Civ. Code §§8102 and 8202, including the boldface Notice to Property Owner and an estimate of the total price, and is given by a method the statute authorizes. Civ. Code §8202(c).
What does a California supplier send on a public project?
A supplier with no direct contract with the direct contractor gives Preliminary Notice to the public entity and the direct contractor. Civ. Code §9300. A supplier in direct contract with the direct contractor is not required to give it.
Related California Resources
Explore other critical compliance areas for California construction mechanic lien law.
Notice Requirements
20-day preliminary notice obligations for private works, stop notices, and public works bond claims under California Civil Code
Mechanic Lien Deadlines
Mechanic Lien recording deadlines based on Notice of Completion status, stop notice filing requirements, and public works claim procedures
Mechanic Lien Enforcement Deadlines
90-day suit deadlines, stop notice enforcement, payment bond claim suit timelines, and public works enforcement
California Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in California
California Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in California
California Overview
Return to the main California construction mechanic lien law page