Does a Notice of Completion Shorten the Mechanics Lien Deadline in California?

Yes, to 60 or 30 Days, But Only a Valid Notice the Owner Actually Sends You

What the Notice Does to the Deadline

Without a recorded notice, every claimant has until 90 days after completion of the work of improvement to record a claim of lien. Civ. Code §§8412, 8414.

When the owner records a Notice of Completion or Notice of Cessation, a second deadline appears and the earlier of the two controls. A direct contractor must record within 60 days after the owner records the notice. Civ. Code §8412(b). Every other claimant must record within 30 days after the owner records the notice. Civ. Code §8414(b)(2).

The shortened period runs from the date the notice is recorded, not from the date the claimant learns of it.

The Notice Has to Be Valid

An owner may record a Notice of Completion on or within 15 days after the date of completion of a work of improvement. The notice must be signed and verified by the owner and must state the date of completion, among other required contents. Civ. Code §8182(a) to (c).

An erroneous statement of the date of completion does not affect the notice if the true date of completion is 15 days or less before the date the notice is recorded. Civ. Code §8182(c)(4). A Notice of Completion that does not comply with the section is not effective. Civ. Code §8182(d).

The Owner Must Give You a Copy

An owner that records a Notice of Completion or Notice of Cessation must, within 10 days of the date the notice is filed for record, give a copy to the direct contractor and to every claimant that has given the owner Preliminary Notice. Civ. Code §8190(a).

If the owner fails to give the copy to a person entitled to it, the notice is ineffective to shorten the time within which that person may record a claim of lien. Civ. Code §8190(c). That person keeps the 90-day period.

This protection reaches only a direct contractor and a claimant that gave the owner Preliminary Notice. A claimant that never gave the owner a Preliminary Notice is not among the persons the owner must notify.

The Residential Exception

The duty to give a copy does not apply to an owner that occupies the real property as a personal residence, if the dwelling contains four or fewer residential units. Civ. Code §8190(d)(1). The statutory Notice to Property Owner in the Preliminary Notice says the same thing to the homeowner. Civ. Code §8202(a)(3).

On those projects a claimant cannot assume a copy of a recorded notice will arrive, and cannot rely on the absence of a copy to preserve the 90-day period. The county recorder's index is the only dependable source.

Frequently Asked Questions

Does a Notice of Completion shorten the lien deadline in California?

Yes. After the owner records a Notice of Completion or Notice of Cessation, a direct contractor has 60 days and every other claimant has 30 days from recording, if that date is earlier than 90 days after completion. Civ. Code §§8412, 8414.

What if the California owner never sent me a copy of the Notice of Completion?

If you are the direct contractor, or you gave the owner Preliminary Notice, and the owner did not give you a copy within 10 days of the date the notice was filed for record, the notice is ineffective to shorten your recording period. Civ. Code §8190(a), (c).

Does the copy requirement apply to homeowners in California?

Not to an owner that occupies the property as a personal residence where the dwelling contains four or fewer residential units. Civ. Code §8190(d)(1).

When can a California owner record a Notice of Completion?

On or within 15 days after the date of completion of the work of improvement. Civ. Code §8182(a). A notice that does not comply with the section is not effective. Civ. Code §8182(d).