HomeCaliforniaSubcontractor Preliminary Notice
CA Subcontractor Preliminary Notice

Does a Subcontractor Need to Send a Preliminary Notice in California?

Yes on Private Work at Every Tier, With a Different Rule on Public Work

The General Rule: Yes

A subcontractor is a contractor that does not have a direct contractual relationship with an owner. The term includes a contractor that contracts with a direct contractor or with another subcontractor. Civ. Code §8046.

Before recording a lien claim, giving a stop payment notice, or asserting a claim against a payment bond on a private work, a claimant must give Preliminary Notice. Civ. Code §8200(a). The only exceptions in the section are for a laborer and for a claimant that contracts directly with the owner. Civ. Code §8200(e). A subcontractor hired by the direct contractor fits neither, so first-tier and lower-tier subcontractors are treated alike.

Compliance is a necessary prerequisite to the validity of the lien claim or stop payment notice, and a claimant may enforce a lien only if it gave Preliminary Notice to the extent required and made proof of notice. Civ. Code §§8200(c), 8410.

Who Receives It, and When

The notice goes to three parties: the owner or reputed owner, the direct contractor or reputed direct contractor to which the claimant provides work, either directly or through one or more subcontractors, and the construction lender or reputed construction lender, if any. Civ. Code §8200(a).

It must be given not later than 20 days after the claimant has first furnished work on the work of improvement. Civ. Code §8204(a). This notice is commonly called the 20-Day Preliminary Notice for that reason.

Notice is given by personal delivery, by registered or certified mail, express mail, or overnight delivery by an express service carrier, or by leaving the notice and mailing a copy in the manner allowed for substituted service of a summons. Civ. Code §§8106, 8110. Mailed notice is complete when deposited in the mail or with the express service carrier. Civ. Code §8116.

What the Notice Must Contain

The Preliminary Notice must comply with Civ. Code §8102 and must also include a general description of the work to be provided, an estimate of the total price of the work provided and to be provided, and the statutory Notice to Property Owner in boldface type. Civ. Code §8202(a).

A subcontractor that has not paid all compensation due to a laborer must include the name and address of the laborer and of any entity to which payments are due on the laborer's behalf. Civ. Code §8202(b).

One notice to each required recipient covers all work the claimant provides for the work of improvement. A claimant that provides work under contracts with more than one subcontractor must give a separate Preliminary Notice for each contract. Civ. Code §8206.

Public Projects Are Different

On a public work, the notice goes to the public entity and to the direct contractor to which the claimant provides work. A claimant that has a direct contractual relationship with a direct contractor is not required to give it. Civ. Code §9300. So a first-tier subcontractor is exempt on public work and not exempt on private work.

A lower-tier subcontractor on public work is not exempt, and may give a stop payment notice or assert a payment bond claim only for work provided within 20 days before giving Preliminary Notice and afterward. Civ. Code §9304.

Frequently Asked Questions

Does a subcontractor need a preliminary notice in California?

Yes on private work. Civ. Code §8200 requires Preliminary Notice to the owner or reputed owner, the direct contractor, and any construction lender, and exempts only laborers and claimants that contract directly with the owner. It is due not later than 20 days after first furnishing work. Civ. Code §8204(a).

Is a subcontractor hired by the general contractor exempt in California?

Not on private work. Civ. Code §8200(e) contains no exemption for a claimant that contracts with the direct contractor. On public work the rule is the opposite: a claimant with a direct contractual relationship with a direct contractor is not required to give Preliminary Notice. Civ. Code §9300(b)(2).

How is a California Preliminary Notice served?

By personal delivery, by registered or certified mail, express mail, or overnight delivery by an express service carrier, or by leaving the notice and mailing a copy in the manner allowed for substituted service of a summons. Civ. Code §§8106, 8110. Mailed notice is complete on deposit. Civ. Code §8116.

Does a subcontractor need a new notice for each delivery or pay period?

No. One Preliminary Notice to each required recipient covers all work the claimant provides for the work of improvement. A separate notice is required only where the claimant works under contracts with more than one subcontractor. Civ. Code §8206.