How Long Do You Have to Enforce a Mechanics Lien in California?
90 Days From Recording, With One Narrow Extension
90 Days, Measured From Recording
The claimant must commence an action to enforce a lien within 90 days after recordation of the claim of lien. If the claimant does not commence an action within that time, the claim of lien expires and is unenforceable. Civ. Code §8460(a).
The anchor is the recording date, not completion of the project and not the claimant's last day of work. The enforcement period opens the day the claim is recorded and should be calendared that day.
The owner is told the same thing. The Notice of Mechanics Lien that must accompany every claim states that a foreclosure action must be filed with the court no later than 90 days after the date the mechanics lien is recorded. Civ. Code §8416(a)(8).
The Extension of Credit
The 90-day rule does not apply if the claimant and owner agree to extend credit, and notice of the fact and terms of the extension of credit is recorded within 90 days after recordation of the claim of lien, or later but before a purchaser or encumbrancer for value and in good faith acquires rights in the property. Civ. Code §8460(b).
In that case the claimant must commence the action within 90 days after the expiration of the credit, but in no case later than one year after completion of the work of improvement. If it does not, the claim of lien expires and is unenforceable. Civ. Code §8460(b).
The extension requires both an agreement with the owner to extend credit and a recorded notice of its fact and terms, recorded within the time Civ. Code §8460(b) allows. An informal promise of payment does not move the deadline. The one-year limit is part of the extension provision. It caps an extended deadline and does not replace the ordinary 90-day rule for a claimant with no recorded extension.
Why Recording Early Has a Cost
Because the 90 days starts at recording, a claimant that records well before its recording deadline also starts its enforcement period early. The recording deadline in Civ. Code §§8412 and 8414 and the enforcement deadline in Civ. Code §8460 are separate periods, and both must be met.
Public Projects Run on Different Deadlines
None of this applies to public work, where the remedies are the stop payment notice and the payment bond. An action on a stop payment notice may be commenced at any time after 10 days from the date the notice is given, and not later than 90 days after expiration of the time within which a stop payment notice must be given. Civ. Code §9502.
An action on the payment bond may be commenced at any time after the claimant ceases to provide work, but not later than six months after the period in which a stop payment notice may be given. Civ. Code §9558.
Frequently Asked Questions
How long do you have to enforce a mechanics lien in California?
An action to enforce the lien must be commenced within 90 days after the claim of lien is recorded. If it is not, the claim of lien expires and is unenforceable. Civ. Code §8460(a).
Can the 90-day deadline be extended in California?
Only by an agreement between the claimant and the owner to extend credit, with notice of the fact and terms of the extension recorded as Civ. Code §8460(b) requires. The action is then due within 90 days after the credit expires, and never later than one year after completion of the work of improvement.
Does the California 90 days run from completion or from recording?
From recordation of the claim of lien. Civ. Code §8460(a). Completion of the work of improvement governs the separate deadline to record the lien.
What happens to a California lien that is not enforced in time?
The claim of lien expires and is unenforceable. Civ. Code §8460(a).
Related California Resources
Explore other critical compliance areas for California construction mechanic lien law.
Notice Requirements
20-day preliminary notice obligations for private works, stop notices, and public works bond claims under California Civil Code
Mechanic Lien Deadlines
Mechanic Lien recording deadlines based on Notice of Completion status, stop notice filing requirements, and public works claim procedures
Mechanic Lien Enforcement Deadlines
90-day suit deadlines, stop notice enforcement, payment bond claim suit timelines, and public works enforcement
California Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in California
California Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in California
California Overview
Return to the main California construction mechanic lien law page