What Happens If You Send a Preliminary Notice Late in California?
The Claim Shrinks to a 20-Day Look-Back, and No Notice at All Is Worse
A Late Notice Is Allowed
A Preliminary Notice must be given not later than 20 days after the claimant has first furnished work on the work of improvement. Civ. Code §8204(a). Missing that date does not end the claimant's rights.
The same subdivision provides that a claimant who did not give a Preliminary Notice is not precluded from giving one at any time afterward. The claimant is then entitled to record a lien, give a stop payment notice, and assert a claim against a payment bond only for work performed within 20 days prior to the service of the Preliminary Notice, and at any time thereafter.
What a Late Notice Costs
Take a subcontractor that first furnishes work on March 1 and serves its Preliminary Notice on June 1. The notice reaches back 20 days, to May 12. Work performed from March 1 through May 11 is outside the lien, the stop payment notice, and the payment bond claim. Work performed on and after May 12 is covered.
The measuring date is service of the notice. Notice given by mail is complete when deposited in the mail or with an express service carrier, and notice given by personal delivery is complete when delivered. Civ. Code §8116. Each day of delay moves the look-back date forward by one day.
What No Notice Costs
For a claimant that owed the notice and never gave it, the result is not a reduced claim. Compliance with Civ. Code §8200 is a necessary prerequisite to the validity of a lien claim or stop payment notice, and a claimant may enforce a lien only if it gave Preliminary Notice to the extent required and made proof of notice. Civ. Code §§8200(c), 8410. A private stop payment notice is likewise not valid unless the claimant gave the required Preliminary Notice. Civ. Code §8508(a).
Public Projects: The Same Look-Back, Plus a Limited Bond Notice
On public work, a claimant may give a stop payment notice or assert a payment bond claim only for work provided within 20 days before giving Preliminary Notice and at any time thereafter. Civ. Code §9304.
For the payment bond only, the statute provides a second route. If Preliminary Notice was not given, a claimant may enforce a bond claim by giving written notice to both the surety and the bond principal, in compliance with Civ. Code §9562, within 15 days after recordation of a notice of completion, or within 75 days after completion of the work of improvement if no notice of completion has been recorded. Civ. Code §9560(b), (c).
That route is restricted. It is unavailable where all progress payments, except those disputed in good faith, have been made to the first-tier subcontractor to which the claimant furnished, or where that subcontractor was terminated from the project and was paid, apart from amounts disputed in good faith, through the termination date. Civ. Code §9560(d). It does not revive a stop payment notice, which depends on compliance with Civ. Code §9300. A laborer and a claimant in direct contract with a direct contractor are exempt from the public works Preliminary Notice and do not need this route. Civ. Code §9300(b).
Frequently Asked Questions
Is a late preliminary notice fatal in California?
No. Civ. Code §8204(a) allows a Preliminary Notice at any time. A late notice supports a lien, stop payment notice, or payment bond claim only for work performed within 20 days before the notice was served and afterward.
What is the difference between a late notice and no notice in California?
A late notice reduces the claim to the 20-day look-back and everything after. No notice, where one was required, leaves the claimant unable to enforce a lien at all, because Civ. Code §§8200(c) and 8410 make the notice a prerequisite.
From what date is the 20-day look-back measured?
From service of the Preliminary Notice. Civ. Code §8204(a). Mailed notice is complete when deposited in the mail or with an express service carrier. Civ. Code §8116.
Can a missed preliminary notice be cured on a California public project?
Partly, and only for the payment bond. Civ. Code §9560 allows written notice to both the surety and the bond principal, in compliance with Civ. Code §9562, within 15 days after a notice of completion is recorded, or 75 days after completion if none is recorded, subject to the limits in subdivision (d). The stop payment notice remedy is not restored.
Related California Resources
Explore other critical compliance areas for California construction mechanic lien law.
Notice Requirements
20-day preliminary notice obligations for private works, stop notices, and public works bond claims under California Civil Code
Mechanic Lien Deadlines
Mechanic Lien recording deadlines based on Notice of Completion status, stop notice filing requirements, and public works claim procedures
Mechanic Lien Enforcement Deadlines
90-day suit deadlines, stop notice enforcement, payment bond claim suit timelines, and public works enforcement
California Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in California
California Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in California
California Overview
Return to the main California construction mechanic lien law page