The Default Is 1 Year, But the Owner Controls the Clock
A Florida lien continues for 1 year after the Claim of Lien is recorded unless an action to enforce it is commenced within that time. Fla. Stat. §713.22(1). The statutory Claim of Lien form itself warns that the lien may remain valid for one year unless the owner takes action to shorten the time period. §713.08(3).
Florida gives the owner two ways to do that. A lienor who records a Claim of Lien should be prepared to file suit on short notice from the day of recording.
Notice of Contest of Lien: 60 Days
An owner or the owner's attorney may elect to shorten the time to commence an action by recording a Notice of Contest of Lien in the clerk's office. The notice tells the lienor that the time to file suit to enforce the lien is limited to 60 days from the date of service of the notice. §713.22(2).
The consequence is automatic. The lien of any lienor upon whom the notice is served and who fails to institute a suit to enforce the lien within 60 days after service is extinguished automatically. §713.22(2).
The clerk serves the notice, in accordance with §713.18, on the lienor at the address shown in the Claim of Lien or its most recent amendment, certifies the service and the date of service on the face of the notice, and records the notice with that certification. §713.22(2). The 60 days run from that date of service, not from the owner's recording.
The same procedure may be used to shorten the time to enforce a claim against a bond or other security under §713.23 or §713.24. §713.22(2).
Summons to Show Cause: 20 Days
The second tool is faster. Upon the filing of a complaint by any interested party in the circuit court of the county where the property is located, the clerk issues a summons to the lienor to show cause within 20 days after service of the summons why the lien should not be enforced by action or vacated and canceled of record. §713.21(4).
If the lienor fails to show cause why the lien should not be enforced, or fails to commence the action before the return date of the summons, the court must order cancellation of the lien. §713.21(4). The procedure requires a filed complaint and a served summons. Recording a notice, or obtaining a summons that is not served, does not start the 20 days.
Why the Address in the Claim of Lien Matters
The Notice of Contest is served at the address shown in the Claim of Lien or its most recent amendment. §713.22(2). The Claim of Lien must state the address where notices or process under the lien law may be served on the lienor. §713.08(1)(a).
Under §713.18(3), a document sent to the last known address of the person to be served is effective on the date of mailing or shipping if it is returned as refused, moved and not forwardable, or unclaimed, or is otherwise not delivered through no fault of the sender. A lienor who does not collect its mail should not assume the 60 days has not started.
Contractors Have an Extra Step Inside the Shortened Period
A contractor must deliver the Contractor's Final Payment Affidavit to the owner at least 5 days before instituting an action to enforce its lien. §713.06(3)(d)1. Sections 713.06(3)(d)1, 713.21(4), and 713.22(2) do not state an exception to that requirement when the period has been shortened. A contractor that has recorded a Claim of Lien should consider delivering the affidavit before a contest or summons arrives.
Payment Bond Claims Can Be Contested Too
On a private bonded project, the contractor or its attorney may use a Notice of Contest of Claim Against Payment Bond after a Notice of Nonpayment, if required, has been served. The contractor or its attorney must serve the notice of contest, certify that service on its face, and record it. The clerk then serves the recorded notice on the lienor and on the contractor or its attorney. A lienor who fails to institute suit on the bond within 60 days after service loses the claim automatically. §713.23(1)(e).
Section 255.05(2)(a)1 provides the same 60-day Notice of Contest of Claim Against Payment Bond on public projects, available where the claimant is no longer furnishing labor, services, or materials on the project. That procedure requires service by the contractor and subsequent service by the clerk, and the 60 days run from service.
Frequently Asked Questions
Can an owner shorten the deadline to enforce a mechanics lien in Florida?
Yes. By recording a Notice of Contest of Lien, the owner limits the time to file suit to 60 days after service of the notice, and the lien is extinguished automatically if suit is not instituted in that time. Fla. Stat. §713.22(2).
What is a Florida summons to show cause on a lien?
Under §713.21(4), on a complaint by any interested party the clerk issues a summons requiring the lienor to show cause within 20 days after service why the lien should not be enforced by action or vacated and canceled. If the lienor fails to show cause or to commence the action before the return date, the court must order cancellation of the lien.
Who serves a Florida Notice of Contest of Lien?
The clerk. Section 713.22(2) directs the clerk to serve a copy on the lienor, in accordance with §713.18, at the address shown in the Claim of Lien or its most recent amendment, and to certify the service and its date on the face of the notice.
Can a Florida payment bond claim be contested the same way?
Yes. The contractor or its attorney may serve, certify, and record a Notice of Contest of Claim Against Payment Bond, which the clerk then serves. It limits the time to sue on the bond to 60 days after service. §713.23(1)(e) for private bonds; §255.05(2)(a)1 for public bonds.
Related Florida Resources
Explore other critical compliance areas for Florida construction mechanic lien law.
Notice Requirements
Statutory preliminary notice obligations for private works, private payment bonds, and public works bond claims under Florida law
Mechanic Lien Deadlines
Mechanic Lien recording requirements, 90-day filing deadline, statutory form, and mechanic lien amount limitations
Mechanic Lien Enforcement Deadlines
Foreclosure deadlines, Notice of Contest, bond claim suit timelines, and public works enforcement
Florida Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in Florida
Florida Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in Florida
Florida Overview
Return to the main Florida construction mechanic lien law page