Can You File a Mechanics Lien on a Public Project in Florida?

No. The Remedy Is the Payment Bond Under Section 255.05, With Its Own Notices and Deadlines

No Lien on Public Property

Florida's lien law reaches only real property as the statute defines it, and that definition excludes property owned by the state or any county, municipality, school board, or governmental agency, commission, or political subdivision. Fla. Stat. §713.01(27). The definition of owner likewise excludes any political subdivision, agency, or department of the state, a municipality, or other governmental entity. §713.01(24).

The substitute is a bond. A person entering into a formal contract with the state, a county, a city, a political subdivision, or other public authority for the construction of a public building, the prosecution and completion of a public work, or repairs upon either must execute and record a payment and performance bond before commencing the work. §255.05(1). The bond is conditioned on promptly making payments to all persons defined in §713.01 who furnish labor, services, or materials for the work, and the claimant has a cause of action against the contractor and the surety. §255.05(1)(c).

Confirm That a Bond Exists

Not every public contract is bonded. When the work is done for the state and the contract is for $100,000 or less, no payment and performance bond is required. For a county, city, political subdivision, or public authority, the awarding official or board has discretion to exempt a contract of $200,000 or less. §255.05(1)(d). The statute also permits alternative forms of security in place of the bond. §255.05(7). A public project therefore does not necessarily have a payment bond.

A claimant may apply to the governmental entity having charge of the work for copies of the contract and bond, and must be furnished with them. §255.05(1)(c).

Notices for Claimants Not in Privity With the Contractor

A claimant, except a laborer, who is not in privity with the contractor must serve the contractor with a written notice that it intends to look to the bond for protection, before commencing or not later than 45 days after commencing to furnish labor, services, or materials. If the bond was not recorded before work commenced as §255.05(1) requires, the claimant may serve the notice up to 45 days after the date it is served with a copy of the bond. §255.05(2)(a)2.

A claimant who is not in privity with the contractor and who has not been paid must also serve a written Notice of Nonpayment on the contractor, with a copy on the surety. It must be under oath. It may not be served earlier than 45 days after the claimant's first furnishing or later than 90 days after the claimant's final furnishing, or, for rental equipment, later than 90 days after the equipment was last on the site and available for use. The 90 days are measured from the claimant's last furnishing and may not be measured by the issuance of a certificate of substantial completion. Qualifying work under the original contract that is furnished after that certificate can count toward final furnishing. The certificate does not exclude later work and does not start the 90-day period. §255.05(2)(a)2.

An action may not be instituted against the contractor or the surety unless the notice to the contractor and the Notice of Nonpayment have been served, if required. The statute requires these two notices only of claimants who are not in privity with the contractor. §255.05(2)(a)2.

A Notice of Nonpayment that includes retainage must specify the retainage portion, and a claimant who serves a fraudulent Notice of Nonpayment forfeits its rights under the bond. §255.05(2)(a)2. Notices under this section are served in accordance with §713.18.

Suit on the Bond: 1 Year

An action, other than an action for recovery of retainage, must be instituted against the contractor or the surety within 1 year after the performance of the labor or completion of delivery of the materials or supplies. §255.05(10). The time periods are measured from the claimant's last day of furnishing and may not be measured by other standards, such as a certificate of occupancy or a certificate of substantial completion. §255.05(2)(a)2.

An action for retainage is subject to the same 1-year period, but it may not be instituted until one of the conditions listed in §255.05(10) is satisfied. If none is satisfied and the action cannot be instituted within the year, the period is extended until 120 days after one of the conditions is satisfied. §255.05(10).

If the claimant is no longer furnishing on the project, the contractor may record a Notice of Contest of Claim Against Payment Bond. The procedure requires service by the contractor and subsequent service by the clerk. A claimant who fails to institute suit within 60 days after service of that notice loses the claim automatically. §255.05(2)(a)1.

Demand for a Sworn Statement of Account

When the public authority makes a payment, the contractor may serve a written demand on any claimant not in privity with it for a written statement of account under oath. Failure to furnish the statement within 30 days after the demand, or furnishing a false or fraudulent statement, deprives the claimant of its rights under the bond, subject to the exceptions stated in §255.05(8).

Scope of This Page

This page describes §255.05. The statute notes that its 2020 amendments do not apply to contracts executed under chapter 337, and those contracts are not covered here.

Frequently Asked Questions

Can you file a mechanics lien on a public project in Florida?

No. Fla. Stat. §713.01(27) excludes property owned by the state or any county, municipality, school board, or governmental agency, commission, or political subdivision from the real property that can be liened. The remedy is ordinarily a claim on the payment bond under §255.05, where a bond is required.

What notices does a Florida public works claimant have to serve?

A claimant not in privity with the contractor, except a laborer, must serve the contractor with notice that it intends to look to the bond before commencing or within 45 days after commencing, or within 45 days after being served with a copy of the bond if the bond was not timely recorded. An unpaid claimant not in privity must also serve a sworn Notice of Nonpayment on the contractor and the surety, no earlier than 45 days after first furnishing and no later than 90 days after final furnishing. §255.05(2)(a)2.

How long do you have to sue on a Florida public payment bond?

Within 1 year after the performance of the labor or completion of delivery of the materials or supplies. §255.05(10). Retainage claims have additional prerequisites and a possible extension. A Notice of Contest of Claim Against Payment Bond can limit the period to 60 days after service. §255.05(2)(a)1.

Is every Florida public project bonded?

No. No bond is required on state work when the contract is for $100,000 or less, and a local public body has discretion to exempt contracts of $200,000 or less. §255.05(1)(d). The statute also permits alternative security. §255.05(7). Request a copy of the bond from the governmental entity in charge of the work. §255.05(1)(c).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.