FL Subcontractor Preliminary Notice

Does a Subcontractor Need to Send a Notice to Owner in Florida?

Yes. It Is a Prerequisite to Recording a Claim of Lien, and the Time Limit Is Strict

The Rule: Every Lienor Not in Privity With the Owner, Except Laborers

A subcontractor contracts with the contractor, not with the owner. §713.01(29). Its lien therefore arises under Fla. Stat. §713.06, and §713.06(2)(a) requires all lienors under that section, except laborers, to serve a notice on the owner as a prerequisite to perfecting a lien and recording a Claim of Lien.

The notice must set forth the lienor's name and address, a description sufficient for identification of the real property, and the nature of the services or materials furnished or to be furnished. §713.06(2)(a). It may be in substantially the statutory form, and it must include the information and the warning contained in that form. §713.06(2)(c).

When It Must Be Served

The Notice to Owner must be served before commencing, or not later than 45 days after commencing, to furnish labor, services, or materials. In any event it must be served before the date of the owner's disbursement of the final payment after the contractor has furnished its final payment affidavit. §713.06(2)(a).

Both limits apply. A notice served on day 30 is still too late if the owner has already disbursed final payment on the contractor's affidavit.

A lienor must strictly comply with these time requirements. Errors or omissions in the content of the notice do not prevent enforcement against a person who was not adversely affected, but that relief does not extend to timing. §713.06(2)(f).

The date of service is determined under §713.18. A notice mailed by one of the postal methods in §713.18(2) within 40 days after first furnishing, properly addressed and supported by the required postal records, is effective on the date of mailing.

Who Else Receives a Copy

A first-tier subcontractor serves the owner. A sub-subcontractor must also serve a copy of the notice on the contractor, and that copy is itself a prerequisite to perfecting the lien. §713.06(2)(a).

If the owner's Notice of Commencement designates another person to receive a copy of the lienor's notice, the lienor must serve a copy on that person. Failure to serve that copy does not invalidate an otherwise valid lien. §713.06(2)(b).

If no Notice of Commencement has been recorded, the lienor may rely on the information in the building permit application to serve the notice. §713.06(2)(e).

Projects With a Payment Bond

If the contractor furnishes a payment bond under §713.23, the owner is exempt from the other provisions of the lien law as to that direct contract, and the bond secures the liens that would otherwise accrue. §713.02(6).

On a bonded private project, a lienor who is not in privity with the contractor, except a laborer, must serve the contractor with written notice that it will look to the bond, before beginning or within 45 days after beginning to furnish. A Notice to Owner that was timely served on the contractor satisfies that requirement. If a Notice of Commencement with the bond attached was not recorded before construction commenced, the lienor may instead serve the notice up to 45 days after the date it is served with a copy of the bond. §713.23(1)(c). A first-tier subcontractor is in privity with the contractor, so this preliminary notice is directed at sub-subcontractors and lower tiers.

Every unpaid lienor claiming on the bond, including a first-tier subcontractor, must serve a sworn Notice of Nonpayment on the contractor, with a copy on the surety, not later than 90 days after its final furnishing. It is a condition precedent to recovery under the bond. Nonpayment of retainage that does not exceed 10% of the value furnished does not by itself require the notice. Where the bond was not recorded, the statute provides a special timing option for the notice. §713.23(1)(d). This differs from a public project under §255.05, where the Notice of Nonpayment is required only of claimants not in privity with the contractor.

Two Limits on Who Can Lien

Lien rights stop at a defined tier. The lienors are the contractor, subcontractor, sub-subcontractor, laborer, a materialman who contracts with the owner, a contractor, a subcontractor, or a sub-subcontractor, and professional lienors. No other person may have a lien. §713.01(19).

An improvement for which the direct contract price is $2,500 or less is exempt from all provisions of the lien law except §713.05, the section for lienors in privity with the owner. §713.02(5).

Frequently Asked Questions

Does a subcontractor need to send a Notice to Owner in Florida?

Yes. Fla. Stat. §713.06(2)(a) requires all lienors not in privity with the owner, except laborers, to serve a Notice to Owner as a prerequisite to perfecting a lien and recording a Claim of Lien.

What is the deadline for a Florida subcontractor's Notice to Owner?

Before commencing, or not later than 45 days after commencing, to furnish labor, services, or materials, and in any event before the owner's disbursement of final payment after the contractor has furnished its final payment affidavit. §713.06(2)(a). The time requirements must be strictly complied with. §713.06(2)(f).

Does a Florida sub-subcontractor serve anyone besides the owner?

Yes. A sub-subcontractor must also serve a copy of the notice on the contractor as a prerequisite to perfecting a lien. §713.06(2)(a). A copy also goes to any person the owner designated in the Notice of Commencement. §713.06(2)(b).

Do laborers have to serve a Notice to Owner in Florida?

No. Section 713.06(2)(a) applies to all lienors under that section except laborers. A laborer is a person who personally performs labor or services on the site and does not furnish materials or the labor of others. §713.01(17).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.