HomeFloridaLien Filing Deadline
FL Lien Filing Deadline

How Long Do You Have to File a Mechanics Lien in Florida?

90 Days After Your Own Final Furnishing, and Corrective Work Does Not Extend It

90 Days After Final Furnishing

A Florida Claim of Lien may be recorded at any time during the progress of the work or thereafter, but not later than 90 days after the final furnishing of the labor, services, or materials by the lienor. Fla. Stat. §713.08(5). The deadline is the same for contractors, subcontractors, sub-subcontractors, laborers, and suppliers, because §713.08(1) requires every lienor, including laborers and persons in privity, to record a Claim of Lien.

If the original contract is terminated under §713.07(4), a claim for a lien attaching before the termination may not be recorded after 90 days following the date of termination or 90 days after the lienor's final furnishing, whichever occurs first. §713.08(5).

What Counts as Final Furnishing

Final furnishing is the last date that the lienor furnishes labor, services, or materials. It may not be measured by other standards, such as the issuance of a certificate of occupancy or a certificate of final completion. §713.01(12).

It does not include the correction of deficiencies in the lienor's previously performed work or materials supplied. §713.01(12). Returning to repair your own work does not restart the 90 days.

For rental equipment, final furnishing is the date the equipment was last on the site of the improvement and available for use. §713.01(12).

Where and How to Record

The Claim of Lien is recorded in the clerk's office, which is the office of the clerk of the circuit court, or other county recorder, of the county where the real property is located. If the property lies in two or more counties, it must be recorded in each. §713.08(5); §713.01(4).

The claim must be signed and sworn to or affirmed by the lienor or the lienor's agent acquainted with the facts. §713.08(2). It is sufficient if it is in substantially the statutory form and includes the statutory warning. §713.08(3).

A lienor not in privity with the owner must state the date and method of service of its Notice to Owner in the claim. §713.08(1)(h). The Notice to Owner is a prerequisite to recording, so a timely Claim of Lien does not cure a missing or late notice. §713.06(2)(a).

Serve the Owner Within 15 Days

The Claim of Lien must be served on the owner. Failure to serve it in the manner provided in §713.18 before recording or within 15 days after recording renders the claim voidable to the extent that the failure or delay is shown to have been prejudicial to any person entitled to rely on the service. §713.08(4)(c).

Amending a Recorded Claim

A recorded Claim of Lien may be amended at any time during the period allowed for recording it, provided the amendment does not cause detriment to a person who acted in good faith in reliance on the claim as originally recorded. §713.08(4)(b). An amendment is not a way to add time after the 90 days have run.

Frequently Asked Questions

How long do you have to file a mechanics lien in Florida?

Not later than 90 days after the final furnishing of labor, services, or materials by the lienor. Fla. Stat. §713.08(5). Record in the clerk's office of the county where the property is located.

Does the Florida 90 days run from project completion?

No. It runs from the lienor's own final furnishing, which may not be measured by other standards such as a certificate of occupancy or a certificate of final completion. §713.01(12).

Does punch list or warranty repair work extend the Florida deadline?

The statute excludes the correction of deficiencies in the lienor's previously performed work or materials supplied from the definition of final furnishing. §713.01(12).

What happens if the Florida lien is not served on the owner within 15 days?

The Claim of Lien is voidable to the extent the failure or delay is shown to have been prejudicial to any person entitled to rely on the service. §713.08(4)(c).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.