The Consequence Is Stated in the Statute
Fla. Stat. §713.06(2)(a) makes the Notice to Owner a prerequisite to perfecting a lien and recording a Claim of Lien, and then states the consequence in plain terms: the failure to serve the notice, or to timely serve it, is a complete defense to enforcement of a lien by any person.
Florida is forgiving about mistakes in what the notice says. If a lienor has substantially complied, errors or omissions do not prevent enforcement against a person who was not adversely affected. The same paragraph then removes timing from that relief: a lienor must strictly comply with the time requirements. §713.06(2)(f).
There Are Two Ways to Be Late
The notice must be served before commencing, or not later than 45 days after commencing, to furnish labor, services, or materials. It must also be served, in any event, before the date of the owner's disbursement of the final payment after the contractor has furnished its final payment affidavit. §713.06(2)(a).
A notice can therefore be late on a short job even though fewer than 45 days have passed. On work near the end of a project, do not treat 45 days as available time.
When a Mailed Notice Counts as Served
Service is governed by §713.18. The permitted methods are hand delivery, common carrier delivery service or registered, Global Express Guaranteed, or certified mail with evidence of delivery, and posting on the site only if the other methods cannot be accomplished. §713.18(1).
A Notice to Owner is effective as of the date of mailing if it is mailed by registered, Global Express Guaranteed, or certified mail within 40 days after the lienor first furnishes, to the address the statute prescribes, and the sender keeps either a mail log showing the certified or registered number, the name and address of the person served, and the Postal Service date stamp confirming the mailing date, or Postal Service tracking records showing the tracking number and the date the Postal Service received it. §713.18(2).
A document sent to the last address shown in the Notice of Commencement, or in the building permit application if there is no Notice of Commencement, or to the last known address of the person to be served, is also effective on the date of mailing or shipping if it is returned as refused, moved and not forwardable, or unclaimed, or is otherwise not delivered through no fault of the sender. §713.18(3).
A notice mailed after day 40 does not have the benefit of the date-of-mailing rule in §713.18(2). Plan service so that delivery is complete inside the 45 days.
What Late Notice Costs Before Any Lien Is Recorded
The notice also controls how the owner must pay. The owner is under no obligation to any lienor, except laborers, from whom it has not received a Notice to Owner at the time of making a payment. §713.06(3)(c)1.
A lienor who was required to serve the notice, did not, and whose time has expired is not entitled to be paid by the owner because the contractor listed it in an affidavit. §713.06(3)(c)4. At final payment, no lienor whose notice time has expired may be paid by the owner or by any other person except the person with whom that lienor has a contract. §713.06(3)(d)2.
That last clause marks what remains. A late notice is a complete defense to enforcement of the lien on the property. The statute does not treat it as ending every payment right, and it does not address the lienor's contract claim against its own customer.
Bonded and Public Projects
On a private project with a payment bond, a lienor not in privity with the contractor, except a laborer, must serve notice on the contractor before beginning or within 45 days after beginning to furnish. If a Notice of Commencement with the bond attached was not recorded before construction commenced, the lienor may instead serve the notice up to 45 days after the date it is served with a copy of the bond. §713.23(1)(c).
On public work, an action may not be instituted against the contractor or the surety unless the notice to the contractor and the Notice of Nonpayment have been served, if required. §255.05(2)(a)2.
Frequently Asked Questions
Is a late Notice to Owner fatal in Florida?
It can be. Fla. Stat. §713.06(2)(a) provides that the failure to serve the notice, or to timely serve it, is a complete defense to enforcement of a lien by any person, and §713.06(2)(f) requires strict compliance with the time requirements.
Can I be late even if I serve within 45 days?
Yes. The notice must in any event be served before the date of the owner's disbursement of the final payment after the contractor has furnished its final payment affidavit. §713.06(2)(a).
Is a Florida Notice to Owner effective when mailed?
Only if the conditions in §713.18 are met. Under §713.18(2), it is effective on the date of mailing if sent by registered, Global Express Guaranteed, or certified mail within 40 days after first furnishing, properly addressed, with the required Postal Service mail log or tracking records. Section 713.18(3) separately covers mail that is returned as refused, unclaimed, or undeliverable through no fault of the sender.
Do mistakes in the notice have the same effect as serving it late?
No. Where the lienor has substantially complied, errors or omissions do not prevent enforcement against a person who has not been adversely affected. That relief does not apply to the time requirements. §713.06(2)(f).
Related Florida Resources
Explore other critical compliance areas for Florida construction mechanic lien law.
Notice Requirements
Statutory preliminary notice obligations for private works, private payment bonds, and public works bond claims under Florida law
Mechanic Lien Deadlines
Mechanic Lien recording requirements, 90-day filing deadline, statutory form, and mechanic lien amount limitations
Mechanic Lien Enforcement Deadlines
Foreclosure deadlines, Notice of Contest, bond claim suit timelines, and public works enforcement
Florida Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in Florida
Florida Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in Florida
Florida Overview
Return to the main Florida construction mechanic lien law page