When Georgia lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Georgia requires statutory lien waiver forms

Georgia requires a payment waiver of lien or payment bond rights to substantially follow its statutory interim or final form, and other waivers are generally unenforceable (O.C.G.A. § 44-14-366).

Quick Answer

Yes. Georgia requires a payment waiver of lien or payment bond rights to substantially follow its statutory interim or final form, in at least 12-point type, with the statutory warning (O.C.G.A. § 44-14-366(c)-(e)). Omitting the warning invalidates the waiver.

A statutory waiver becomes effective at the earliest of actual receipt of the stated funds, a separate written acknowledgment of payment in full, or 90 days after execution unless the claimant first records an Affidavit of Nonpayment (§ 44-14-366(g)). Recording a Claim of Lien alone does not stop the waiver from taking effect.

Waivers of lien or payment bond rights made before labor, services, or materials are furnished are null, void, and unenforceable (§ 44-14-366(b)). Subordination agreements and settlements of bona fide disputes over work already performed are excepted.

The interim and final waivers are signed, dated, sealed, and witnessed, but not notarized. The Affidavit of Nonpayment must be sworn before a witness and a notary, and a copy sent to the owner within 7 days after filing.

Georgia prescribes two waiver forms: the Waiver and Release of Lien and Payment Bond Rights Upon Interim Payment, and the Waiver and Release of Lien and Payment Bond Rights Upon Final Payment. When a payment waiver is used, it must substantially follow the applicable form and include the statutory warning.

Since January 1, 2021, a statutory waiver releases only lien and payment bond rights; it does not release the underlying contract debt. A claimant that signs a waiver and is not paid preserves its rights by recording an Affidavit of Nonpayment before 90 days pass.

Georgia Lien Waiver Types

Waiver and Release of Lien and Payment Bond Rights Upon Interim Payment

Statutory Form
When to use it
Exchanged for a progress payment. It releases lien and bond rights through the date stated, except retainage.
When it takes effect
Effective on actual receipt of the stated funds, a written acknowledgment of payment in full, or 90 days after execution unless an Affidavit of Nonpayment is timely recorded.

Waiver and Release of Lien and Payment Bond Rights Upon Final Payment

Statutory Form
When to use it
Exchanged for final payment. It releases lien and bond rights for all furnishing on the described property, with no standard retainage exception.
When it takes effect
Effective on actual receipt of the stated funds, a written acknowledgment of payment in full, or 90 days after execution unless an Affidavit of Nonpayment is timely recorded.

Affidavit of Nonpayment

Statutory Form
When to use it
Recorded by a claimant that signed a statutory waiver but did not receive the stated payment.
When it takes effect
Suspends the waiver until payment in full. Once paid, the claimant must on request record an affidavit of payment, which voids the nonpayment affidavit.

Statutory forms are required

Georgia does not require a waiver on every payment, but a payment waiver of lien or bond rights must substantially follow the statutory interim or final form. Other oral or written waivers generally have no enforceable or estoppel effect (O.C.G.A. § 44-14-366(c)).

The form must be in at least 12-point type. Boldface capitals are no longer required. Incorrect blanks do not necessarily invalidate the waiver if its subject matter can reasonably be determined.

The 90-day Affidavit of Nonpayment

A claimant that has not been paid must record an Affidavit of Nonpayment in the property county before 90 days pass after the waiver was executed, and send a copy to the owner within 7 days after filing (§ 44-14-366(g)(2)(C)).

The 90-day window applies to waivers governed by the 2021 amendments. Older cases applying the former 60-day period, such as Bibler Masonry Contractors, Inc. v. J. T. Turner Construction Co., 340 Ga. App. 490 (2017), are obsolete on that point.

Advance waivers are void

A waiver of lien or payment bond rights made before furnishing labor, services, or materials is null, void, and unenforceable, and so is an attempt to waive section 44-14-366 itself (§ 44-14-366(b)).

The statute expressly permits subordination of lien rights, waivers settling a bona fide dispute over work already furnished, and releases of recorded liens or preliminary notices (§ 44-14-366(f)).

Payment bond rights

Section 44-14-366 governs labor and material bond rights as well as liens. An advance no-bond-claim clause in a subcontract is unenforceable, and the statutory waivers release payment bond rights along with lien rights.

A waiver does not excuse compliance with the separate public bond notice and suit deadlines.

Do not rely on custom check-clearing language

Both statutory forms already contemplate payment, but adding conditional or check-clearing language does not displace the 90-day deemed effectiveness rule. No controlling appellate decision since the 2021 amendments validates custom clearance language as an override.

The reliable protection is a timely recorded Affidavit of Nonpayment. Do not sign a separate acknowledgment of payment in full before funds are actually received.

Exchange Georgia lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Frequently Asked Questions

Does Georgia require a statutory lien waiver form?

Yes. When a payment waiver of lien or payment bond rights is used, it must substantially follow the statutory interim or final form in O.C.G.A. § 44-14-366, including the statutory warning. Other waivers are generally unenforceable.

Does a Georgia lien waiver have to be notarized?

No. The interim and final waivers are signed, dated, sealed, and witnessed. The Affidavit of Nonpayment, by contrast, must be sworn before a witness and a notary (§ 44-14-366(g)).

What happens if I sign a Georgia lien waiver and do not get paid?

Record an Affidavit of Nonpayment in the county where the property is located before 90 days pass after you signed the waiver, and send a copy to the owner within 7 days after filing. Otherwise the waiver becomes effective and your lien and bond rights for that amount are released (§ 44-14-366(g)).

Does a Georgia lien waiver release my contract claim?

Not for waivers governed by the current statute. Since January 1, 2021, a statutory waiver releases only lien and payment bond rights and does not affect other rights or remedies (§ 44-14-366(a)). Earlier cases holding otherwise applied the former statute.

Are advance lien waivers enforceable in Georgia?

No. A waiver of lien or payment bond rights made before labor, services, or materials are furnished is null, void, and unenforceable (§ 44-14-366(b)).

Does filing a Claim of Lien protect me after signing a waiver?

No. Since 2021, recording a Claim of Lien alone does not stop a statutory waiver from becoming effective. The claimant must record a timely Affidavit of Nonpayment, and must separately meet the 90-day lien deadline (§ 44-14-366(g)).

Deadlines Are Unforgiving